Martel v. Bulotti

65 P.3d 192, 138 Idaho 451, 2003 Ida. LEXIS 17
CourtIdaho Supreme Court
DecidedJanuary 28, 2003
Docket27695
StatusPublished
Cited by18 cases

This text of 65 P.3d 192 (Martel v. Bulotti) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Martel v. Bulotti, 65 P.3d 192, 138 Idaho 451, 2003 Ida. LEXIS 17 (Idaho 2003).

Opinion

KIDWELL, Justice.

The district court confirmed an arbitration award in favor of Michel Martel (Martel) and entered judgment against John Bulotti (Bulotti) pursuant to the Uniform Arbitration Act (UAA). I.C. §§ 7-901 to -922 (2002). Bulotti appeals on the grounds that the district court erred in finding that he did not properly request formal arbitration and that the “award” was not confirmable pursuant to the UAA. This Court affirms the judgment of the district court on alternative grounds.

I.

FACTS AND PROCEDURAL BACKGROUND

Martel contracted with Bulotti to build an addition to her home. On July 12, 1999, Martel and Bulotti entered into a written contract using an American Institute of Architects (ALA) contract form (the contract).

The contract incorporated by reference General Conditions (conditions) that provided a process for resolving disputes arising out of the contract. Pursuant to the conditions, the parties were to submit disputes to the pro *453 ject architect for decision. Then, the architect was to provide a written decision to each party. The architect’s decision was “final and binding on the parties subject to arbitration.” After the architect submitted a written decision to the parties that stated it was “final but subject to arbitration,” either party could demand arbitration of the dispute. The conditions instructed the party demanding arbitration that “[njotice of demand for arbitration shall be filed in writing with the other party to the Agreement ... and with the American Arbitration Association [ (AAA) ], and a copy shall be filed with the architect.” Failure to demand arbitration within thirty days would result in “the Architect’s decision becoming final and binding upon [the parties].”

A dispute arose between Martel and Bulotti regarding Bulotti’s performance. The parties submitted the dispute to the architect for a decision. The architect issued a written decision on March 26, 2001, awarding Martel damages totaling $11,594.94. The decision stated: “This decision is final but subject to a demand for arbitration and a demand for arbitration of this claim must be made within thirty (30) days of Ms. Martel’s receipt of this certification. Ms. Martel received a copy of this certification on March 27, 2001.” Bulotti received the architect’s decision on March 29,2001.

Bulotti faxed a demand for arbitration to the architect’s office on April 26, 2001, one day before the running of the thirty-day period in which to demand arbitration. Bulotti did not send the demand to Martel or to the AAA as required by the conditions of the contract.

On May 25,2001, Martel applied for confirmation of the architect’s award and moved for entry of judgment. Bulotti filed an objection to confirmation of the award on the grounds that there was no arbitration award to confirm “notwithstanding the fact that Mr. Bulotti, pursuant to the contract of the parties, specifically requested arbitration within the time permitted under the contract ...”. At hearing, Bulotti offered additional grounds for his objection which included: (1) the conditions never became part of the contract because he neither received nor read them; and (2) even if the conditions became part of the contract, he substantially complied with the requirements for demanding arbitration. Bulotti only pursues the latter appeal.

On June 28, 2001, the district court entered a judgment that included the following findings of fact and conclusions of law:

The Court'finds and concludes as follows: (1) that no facts are in dispute which would be dispositive of the matter and that all issues are questions of law; (2) that [Martel] has followed the contract between the parties; (3) that there is no legal significance to when Defendant received a copy of the General Conditions because they were incorporated into the contract he signed; (4) that the contract between the parties says that the architect’s decision is final and binding; and (5) that the architect’s decision is an arbitration award subject to confirmation by the Court.
Based on the foregoing, the arbitration award of $11,594.94 to [Martel] from [Bulotti] is affirmed.

Bulotti timely filed this appeal.

II.

STANDARD OF REVIEW

This Court exercises free review over matters of law. Polk v. Larrabee, 135 Idaho 303, 308, 17 P.3d 247, 252 (2000). Determining the meaning of a statute or applying law to undisputed facts constitute matters of law. Id.; Melendez v. Hintz, 111 Idaho 401, 402, 724 P.2d 137, 138 (Ct.App.1986).

This Court may uphold decisions on alternate grounds from those stated in the findings of fact and conclusions of law on appeal. See Hanf v. Syringa Realty Co., Inc., 120 Idaho 364, 370, 816 P.2d 320, 326 (1991) (citing Foremost Ins. Co. v. Putzier, 102 Idaho 138, 627 P.2d 317 (1981) and Anderson & Nafzigerv. G.T. Newcomb, Inc., 100 Idaho 175, 179, 595 P.2d 709, 713 (1979)).

*454 III.

ANALYSIS

A. The Architect’s Decision Does Not Constitute An Arbitration Award.

Bulotti argues that the district court erred in confirming the architect’s decision as an arbitration award because the architect was not an “arbitrator” for purposes of I.C. § 7-908. Rather than seeking confirmation, the proper method for enforcing the architect’s decision was a breach of contract claim. Then, the architect’s decision would be mere evidence subject to attack on grounds of bias. Martel, on the other hand, contends that the architect was an arbitrator under the terms of the contract even though his decision could be appealed through further arbitration. Consequently, the court’s confirmation of the architect’s award should be affirmed.

Whether the decision of an architect constitutes an arbitration award for purposes of I.C. § 7-911 presents an issue of first impression in Idaho. Section 7-911 states that:

Upon application of a party, the court shall confirm an [arbitration] award, unless within, the time limits hereinafter imposed grounds are urged for vacating or modifying or correcting the award ....

Section 7-912(a)(2) sets out grounds on which a party may seek to vacate an arbitration award, including bias of the arbitrator, corruption, or fraud; it states in pertinent part:

(a) Upon application of a party, the court shall vacate an award where;[:]
(1) The award was procured by corruption, fraud or other undue means;
(2) There was evident partiality by an arbitrator appointed as a neutral, or corruption in any of the arbitrators, or misconduct prejudicing the rights of any party

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Berglund v. Dix
511 P.3d 260 (Idaho Supreme Court, 2022)
Martin v. Garrett Living Trust
Idaho Supreme Court, 2022
Cuozzo v. State, d/b/a University of North Dakota
2019 ND 95 (North Dakota Supreme Court, 2019)
Swafford v. Huntsman Springs Inc
Idaho Supreme Court, 2017
Maravilla v. J. R. Simplot Co.
387 P.3d 123 (Idaho Supreme Court, 2016)
David Kosmann v. Leo Gilbride
386 P.3d 504 (Idaho Supreme Court, 2016)
Thomas C. Millard v. ABCO Construction
384 P.3d 958 (Idaho Supreme Court, 2016)
State v. John Huntington Wilks
Idaho Court of Appeals, 2013
Shapley v. Centurion Life Insurance
303 P.3d 234 (Idaho Supreme Court, 2013)
County of Boise v. Idaho Counties Risk Management Program
265 P.3d 514 (Idaho Supreme Court, 2011)
State v. Doe
195 P.3d 745 (Idaho Court of Appeals, 2008)
Commercial Ventures, Inc. v. Rex M. & Lynn Lea Family Trust
177 P.3d 955 (Idaho Supreme Court, 2008)
Union School District 45 v. Wright & Morrissey, Inc.
2007 VT 129 (Supreme Court of Vermont, 2007)
VFP VC v. Dakota Co.
109 P.3d 714 (Idaho Supreme Court, 2005)
SE/Z Construction, L.L.C. v. Idaho State University
89 P.3d 848 (Idaho Supreme Court, 2004)
Summers v. Cambridge Joint School District No. 432
88 P.3d 772 (Idaho Supreme Court, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
65 P.3d 192, 138 Idaho 451, 2003 Ida. LEXIS 17, Counsel Stack Legal Research, https://law.counselstack.com/opinion/martel-v-bulotti-idaho-2003.