Union School District 45 v. Wright & Morrissey, Inc.

2007 VT 129, 945 A.2d 348, 183 Vt. 555, 2007 Vt. LEXIS 297
CourtSupreme Court of Vermont
DecidedDecember 11, 2007
DocketNo. 06-033
StatusPublished
Cited by10 cases

This text of 2007 VT 129 (Union School District 45 v. Wright & Morrissey, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Union School District 45 v. Wright & Morrissey, Inc., 2007 VT 129, 945 A.2d 348, 183 Vt. 555, 2007 Vt. LEXIS 297 (Vt. 2007).

Opinion

Cook and Katz, JJ.

¶ 1. December 11, 2007. Defendant Wright & Morrissey, Inc. (Wright) appeals from a superior court judgment awarding $102,477 to plaintiff Union School District #45 for the costs to reconstruct sidewalks damaged by frost heaves less than a year after they were built. Wright contends the judgment must be reversed because: (1) an arbitration agreement between the parties divested the court of subject matter jurisdiction; (2) the District failed to comply with the contract’s alternative-dispute resolution procedures; (3) the court based its decision upon an erroneous finding that the project architect had determined Wright to be liable for the costs to implement recommended design changes; and (4) the court improperly declined to award prejudgment interest on its counterclaim. We reverse the court’s prejudgment interest ruling and affirm in all other respects.

¶ 2. In 1996, the District entered into a contract with Wright for the construction of a new middle school designed by the architectural firm of Banwell White Arnold Hemberger & Partners, Inc. (Banwell). The school was completed in the summer of 1997 and in use by September. That winter, however, a stretch of sidewalk adjacent to the school suffered damage due to frost heaves. The damage became more acute over the next several winters. In May 2000, an engineering firm hired by Banwell to determine the cause of the problem issued a report (the Knight report) indicating that it was partly the result of sub-base gravel which did not conform to the design specifications. Wright, the contractor, was made aware of the Knight report and, in response, engaged its own expert who issued an analysis (the Willis report) concluding that the frost heaves were primarily caused by the architect’s failure to include adequate drainage, or “groundwater control” in its original design. Neither the architect nor the contractor, therefore, accepted responsibility for the frost-heave problem or the cost of repair.

¶ 3. To resolve the apparent deadlock, the District hired its own engineering firm, Lamoureux & Dickinson, to assess what went wrong and recommend a remedy. The resulting report (the Lamoureux report) contained a detailed, comprehen[556]*556sive analysis of the soil and groundwater characteristics of the project area and their relation to the frost-heave problem. The report essentially concluded that the contractor and architect shared responsibility, indicating that tests had revealed some deviation from the original plans as well as the need for some additional groundwater control measures. The report set forth five specific “recommendations to remedy the sidewalk heaving problem.” Subsequent efforts by the District to negotiate an allocation of costs for reconstruction of the sidewalk in accordance with the Lamoureux report recommendations, however, proved to be unsuccessful.

¶ 4. Accordingly, in December 2001, the District, through its attorney, notified Banwell’s attorney that it was implementing § 4.3.2 of the General Conditions of the Contract for Construction (General Conditions), a standard form agreement promulgated by the American Institute of Architects that was incorporated as an addendum to the construction contract. The provision invoked by the District establishes a two-step alternative-dispute-resolution (ADR) process for claims relating to the contract. It states, in pertinent part, that “[cjlaims, including those alleging an error or omission by the Architect, shall be referred initially to the Architect for action as provided in Paragraph 4.4.” The latter provision prescribes a series of steps to be taken by the contractually designated “Architect,” in this case Banwell, in response to a claim. After reviewing the claim, “the Architect” is to issue a preliminary response, which may include a request for additional data, rejection of the claim in whole or part, approval of the claim, or a proposal for compromise. Thereafter, if the claim has not been resolved, “the Architect” is to issue a final decision “which decision shall be final and binding on the parties but subject to arbitration.” General Conditions, § 4.4.4. Either party may then proceed to the second step in the ADR process, arbitration. As provided in the General Conditions, when a decision of “the Architect” states that it is “final but subject to arbitration,” a demand for arbitration “must be made within 30 days after the date on which the party making the demand receives the final written decision.” General Conditions, § 4.5.4.1 Furthermore, a “failure to demand arbitration within said 30 days’ period shall result in the Architect’s decision becoming final and binding upon the Owner [i.e., the District] and Contractor.” Id.

¶ 5. The District’s letter identified four claims: (1) that the sidewalks were improperly designed; (2) that Wright failed to notify the District and the architect in a timely manner of errors or omissions in the design plans; (3) that Wright failed to construct the sidewalks in conformance with the plans and specifications; and (4) any combination of the above. The District requested “that these claims be resolved by implementation, at no cost to the District, of the recommendations set forth” in the Lamoureux report. In early January 2002, Banwell’s attorney sent a letter to the District “to serve as Banwell Architect’s Decision under § 4.4, et seq. of the General Conditions.” The letter succinctly responded to each of the four claims. With respect to the claim of design error, the letter stated that “[t]he Architect rejects this claim in its entirety.” As to the failure to notify, the letter reiterated Banwell’s conclusion that there were no errors or omissions in the design plans, but “assuming arguendo that there were” agreed that the contractor was required to report them. Finally, with respect to the claim that Wright had failed to construct the sidewalks in accordance with the plans, the letter indicated that “[t]he Architect agrees with this claim in its entirety.” The letter closed with the conclusion “that the responsibility for this claim rests with the Contractor, as supported by the 7/01 [Lamoureux & Dickinson] report.”

[557]*557¶ 6. For reasons unclear from the record, Banwell’s attorney issued a second letter, in April 2002, restating the findings from the first letter.1 This was followed within several days by a brief notice on behalf of Banwell, dated April 18, 2002, stating that, as provided in the General Conditions, the second letter “constitutes the Architect’s final decision,” that the “decision is final but subject to arbitration,” that any demand for arbitration must be made within thirty days, and that failure to demand arbitration within the thirty-day period “shall result in the Architect’s decision becoming final and binding upon the [District] and Contractor.”

¶ 7. Wright neither requested arbitration following Banwell’s decision nor undertook to reconstruct the sidewalks in accordance with recommendations in the Lamoureux report. Accordingly, in August 2002, the District filed a complaint in superior court seeking to enforce Banwell’s “final and binding” decision by compelling Wright to perform the corrective work. The action was later amended to one for monetary damages to recover the costs of performing the work in question.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stacey Martin v. Christine Lyon
2024 VT 68 (Supreme Court of Vermont, 2024)
Peterson v. Binnacle Capital Servs. LLC
364 F. Supp. 3d 108 (District of Columbia, 2019)
Littlejohn v. Timberquest Park at Magic, LLC
116 F. Supp. 3d 422 (D. Vermont, 2015)
TD Bank, N.A. v. Burke
Vermont Superior Court, 2015
LaFrance Architect v. Point Five Development South Burlington, LLC
91 A.3d 364 (Supreme Court of Vermont, 2013)
Glassford v. BrickKicker and GDM Home Services, Inc.
2011 VT 118 (Supreme Court of Vermont, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
2007 VT 129, 945 A.2d 348, 183 Vt. 555, 2007 Vt. LEXIS 297, Counsel Stack Legal Research, https://law.counselstack.com/opinion/union-school-district-45-v-wright-morrissey-inc-vt-2007.