Knoblock v. Arenguena

380 P.2d 898, 85 Idaho 503, 1963 Ida. LEXIS 331
CourtIdaho Supreme Court
DecidedApril 19, 1963
Docket9185
StatusPublished
Cited by8 cases

This text of 380 P.2d 898 (Knoblock v. Arenguena) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Knoblock v. Arenguena, 380 P.2d 898, 85 Idaho 503, 1963 Ida. LEXIS 331 (Idaho 1963).

Opinion

KNUDSON, Chief Justice.

This action was commenced by plaintiff-appellant, Rich Knoblock, to foreclose a lien *505 for labor and materials furnished in the drilling of a well upon land owned by defendant-respondent, Daniel Arenguena. The issues involve the terms and conditions of an oral agreement entered into by the parties on or about July 20, 1960, under which appellant agreed to drill a well upon land of respondent. Aside from the parties no witnesses were present to hear the discussion between the parties or the terms agreed upon.

Trial was had before the court, sitting without a jury, and from a judgment for respondent, this appeal is taken.

It is not disputed by either party that appellant was to drill the well and install ten inch casing for which he was to be paid at the rate of $9.50 per lineal foot.

Appellant testified that he drilled to a depth of 220 feet, and that following the completion of the drilling he test-pumped the well for which he was to receive additional compensation, and that there is due and owing him the sum of $2,119.18.

The area of dispute is whether appellant was required, under the terms of the agreement, to drill a hole sufficiently straight to accommodate the proper functioning of a turbine type pump with capacity to provide a flow of between 40 to 50 miner inches of water.

The first three assignments of error challenge the sufficiency of the evidence to support the following quoted findings of fact made by the trial court, to-wit:

“That the defendant was never able to straighten the well and that as a result the well was not such a well as would be drilled in a good and workmanlike manner so as to fulfill the purpose for which it was intended, it being intended that the well be used for irrigation purposes.
“That the plaintiff did not substantially complete his oral contract with the defendant to drill an irrigation well.
“That the plaintiff did not sustain the burden of proof.”

The following quoted testimony of appellant is an acknowledgment on his part that the well as originally drilled was crooked:

“Q. Isn’t it a fact Mr. Knoblock, that you told Mr. Reed that you admitted the well was crooked and that you would fix it?
“A. I told him that I knew it was crooked, sure, and I would attempt to straighten it up but that was to satisfy Mr. Arenguena but I still insisted all the way along putting in an oversized test pump would be a better indication of what was going to work than anything else.
“Q. You did for about two weeks try to straighten the well, is that right ?
“A. Correct.”

*506 The evidence is conflicting as to whether the contract contemplated a straight well. Respondent insists that appellant guaranteed “a straight well.” Appellant argues that it is virtually impossible to drill a perfectly straight well. Appellant is corroborated in this contention by qualified experts who testified that normally an irrigation well is neither plumb nor straight.

On the issue as to whether or not appellant was able to straighten the well, the record is clear that after some discussion between the parties appellant attempted to straighten it by drilling a 12 or 16 inch hole alongside the original casing to a depth of between 50 and 60 feet and moving the casing over somewhere between 10 and 12 inches. It is not clear to what extent, if any, such effort on the part of appellant accomplished correction.

Two witnesses besides respondent testified that from their observations made after appellant attempted to straighten the well, it still remained in about the same condition as when they first observed it. We therefore conclude that from the conflicting evidence the trial court was justified in finding as he did that appellant was never able to straighten the well.

By the remaining findings which are complained of, the court in effect found that appellant did not establish by a preponderance of the evidence that he substantially performed his oral contract with respondent by drilling a well in a good and workmanlike manner, so as to fulfill the purpose for which it was intended.

Under respondent’s affirmative defense it is alleged that the well has not been completed. In this connection the court found that appellant “did not substantially complete his oral agreement” but did not specify in what respect appellant failed to complete the agreement. It is admitted that respondent told appellant he wanted a well that would produce from 40 to 50 inches of water, however, it is not contended that there was any expressed or even implied agreement on the part of appellant that the well would be a success as to quantity or quality of the water obtained. Respondent also alleged in his affirmative defense and strenuously contends that the well was drilled in such a manner that it is of no use or benefit whatsoever to him.

After appellant drilled to a depth of 220' feet, a test pump was installed by him and the evidence shows that between 40 and 50 miner inches of water was produced, although sand in varying amounts was present. After the test pump was removed five witnesses examined the well using lights, mirrors and some used a plumb-bob. Several of the witnesses testified that when using the light test, the light would go out of sight at a depth of approximately 90 *507 feet. Those who used the plumb-bob testified that when they would hang the string over one side of the casing the plumb-bob would touch the other side at a depth of from I61/2 to 18 feet. One of respondent’s witnesses testified that he re-examined the well after appellant endeavored to straighten the casing and by using both mirror and light tests he was able to see water in approximately 1/2 of an inch of the outside arc of the well. The water level in the casing was at a depth of approximately 95 feet from the top.

The trial court found that the oral agreement between the parties provided that the well wotdd be a serviceable irrigation well capable of producing 40 to 50 inches of water and capable of being used with a Parma Water Lifter Turbine pump. No error is assigned to such finding and we therefore assume that the parties concede that it is supported by competent evidence.

Forest L. Reed, assistant manager of the Parma Water Lifter Co., whom respondent had consulted relative to a pump for the well and who was the only expert witness who examined the well before and after appellant had attempted to straighten it, testified that in his opinion the well was not sufficiently straight to put a pump in and expect it to operate satisfactorily. Said witness examined the well after appellant’s attempt to straighten it and the following quoted testimony discloses his opinion as to the condition of the well as it was left by appellant:

“Q. After you looked at the well that time, did you change your opinion Mr. Reed as to whether or not you could install a pump and expect it to operate satisfactorily in that well?

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Biersdorff v. Brumfield
468 P.2d 301 (Idaho Supreme Court, 1970)
Dick v. Reese
412 P.2d 815 (Idaho Supreme Court, 1966)
Durfee v. Parker
410 P.2d 962 (Idaho Supreme Court, 1965)
Nelson v. Hazel
406 P.2d 138 (Idaho Supreme Court, 1965)
Cantlin v. Carter
397 P.2d 761 (Idaho Supreme Court, 1964)
Andrus v. Irick
394 P.2d 304 (Idaho Supreme Court, 1964)
Stout v. Boise Cascade Corp.
390 P.2d 63 (Idaho Supreme Court, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
380 P.2d 898, 85 Idaho 503, 1963 Ida. LEXIS 331, Counsel Stack Legal Research, https://law.counselstack.com/opinion/knoblock-v-arenguena-idaho-1963.