C. R. Crowley, Inc. v. Soelberg

346 P.2d 1063, 81 Idaho 480, 1959 Ida. LEXIS 243
CourtIdaho Supreme Court
DecidedNovember 23, 1959
Docket8779
StatusPublished
Cited by16 cases

This text of 346 P.2d 1063 (C. R. Crowley, Inc. v. Soelberg) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
C. R. Crowley, Inc. v. Soelberg, 346 P.2d 1063, 81 Idaho 480, 1959 Ida. LEXIS 243 (Idaho 1959).

Opinion

*483 McQUADE, Justice.

This is an action for damages for breach of a written well-drilling contract. Charles P. Cope, cross-defendant and respondent herein, contracted to drill a serviceably straight 20-inch irrigation well on defendant Soelberg’s property near Arco, Idaho. Under terms of the contract, the well was to be at least 200 feet deep, and drilling was to continue until either (1) sufficient water was obtained (2) Soelberg requested it be halted, or (3) a depth of 250 feet was reached. It was specifically provided the driller did not agree to find nor develop water. Contract price for the well was $14 per foot; payment of a note bearing eight per cent interest was to be secured by a crop mortgage.

The drilling contractor warranted the well would be “serviceably straight, round and aligned, and of full size, so as to allow the installation and operation of pumping equipment designed for a hole of that nominal diameter.”

Work was undertaken pursuant to the contract. By a subsequent written instrument, Soelberg authorized the driller to continue beyond 250 feet. There is evidence to show the drilling continued to the 380 foot depth.

Soelberg allegedly paid no part of the contract price. The driller assigned his claim for the sum due on the contract to C. R. Crowley, Inc., a bonded collection agency. The agency then brought this action.

The complaint alleged the parties had executed the contract; the driller began the work and drilled a well of 20 inches diameter to a depth of 380 feet at the request of the purchaser; the defendant refused to execute the promissory note and the crop mortgage provided for in the contract ; the plaintiff is assignee of Cope’s claim; there is due thereon the sum of $5,320, to *484 gether with interest; Soelberg had agreed to pay reasonable attorney fees for such a proceeding, and the sum of $600 is a reasonable fee to be allowed.

In an amended answer and cross-complaint, defendant Soelberg admitted plaintiff’s corporate existence, the execution of the contract, and the commencement of drilling operations; he denied all other allegations of the complaint.

As an affirmative defense, Soelberg alleged the driller contracted to furnish all labor, tools and machinery and to carry out the work “diligently and in good workmanlike manner”; that the well was to be serviceably straight, round and aligned, and of full size to allow installation and operation of pumping equipment for a hole of that nominal diameter; the driller stopped work before the well was deep enough to furnish sufficient water for irrigation; he promised to return and finish drilling, but failed to do so, and as a consequence the defendant lost his entire crop.

By way of cross-complaint, the defendant set forth the following additional allegations: After Cope left the premises with his drilling rig, it was found the hole was so crooked it would not accommodate a 16-inch pump; relying upon completion of the well, the defendant had planted 160 acres of wheat and 60 acres of barley on the land to be irrigated; had the well been completed, he would have harvested crops having a net value of $9,968 after deduction of expenses.

Defendant prayed plaintiff take nothing by reason of its complaint, and the defendant have judgment of $9,968 against Cope as cross-defendant.

In the course of the trial, the court granted a motion for nonsuit as to the cross-complaint. The jury returned a verdict of $5,320 for the plaintiff against the defendant, upon which verdict judgment was granted. Defendant then moved for a new trial, supporting his motion by affidavits. This motion was denied. Defendant appeals from the judgment, from orders of the trial court denying his motions for nonsuit and for a directed verdict, and from denial of the motion for new trial.

Defendant-appellant sets forth numerous specifications of error, most of them directed toward the trial court’s rulings on admission of testimony and exhibits. He further assigns as error denial of his motion for nonsuit to the complaint; granting of plaintiff’s motion for nonsuit; denial of defendant’s motion for judgment non obstante veredicto; denial of the motion for new trial; giving of an instruction as to liability based on the driller’s compliance or noncompliance, and his readiness to comply, with the contract; and that the verdict was against the weight of the evidence in that there was no competent evidence supporting the amount awarded.

*485 The evidence in this case — most of it going to the straightness, depth, and serviceability of the well — is in sharp conflict.

Cope testified the drillers struck water at 245 feet, and the water stood at 210 feet in the well. He said drilling continued to 380 feet. He testified he asked Soelberg to furnish 16-inch casing to use below the 250-foot level (the contract providing for a reduction in diameter of the well if this should become necessary) and this was refused. The witness said he then left the job. The well log showed drilling stopped at 380 feet. The witness also related because of lack of proper casing the lower portion of the well caved, filling it up to the 300 foot level.

The drilling contractor further testified a 14-inch pump had been contemplated when the contract was entered into, but the well would in fact accommodate a 16-inch pump.

A consulting engineer, R. T. Michener, testified he tested the well with a “cage”— a heavy ring slightly smaller than the diameter of the well, suspended over the center and lowered to measure deflections in the shaft. During the course of the test, the cage turned sideways and became jammed in the well. The engineer said in his opinion a 16-inch pump could be used in the area between 280 and 300 feet, and it would hang plumb and free. He explained the water level must be above the pump bowls, but generally the source is below them. The witness further testified it was customary in that area to drill a well of greater diameter than the pump contemplated, to allow for reductions.

Two other witnesses, a pump dealer and a well-drilling contractor, testified a 16-inch pump would operate satisfactorily. A driller employed by Cope testified he drilled the well 380 feet with a 20-inch bit.

A pump installer estimated the cage obstructing the well could be removed in an hour’s time with proper tools, at a cost of about $50. Cope, on further examination and just before the closing of plaintiff’s case, testified he had that day sent equipment to the Soelberg place to remove the obstruction.

Soelberg, testifying in his own behalf, said during the course of the drilling Cope wanted to reduce the diameter of the well and put in 16-inch casing, and the defendant refused to agree to this. Then, he said, the driller took out his equipment and did not return. The defendant said he measured the well, using a weighted length of twine, and found it was 300 feet deep. He said he also used a mirror to look down the shaft, and saw “several different crooks.” Soelberg further testified a drawing made under his supervision showed the hole was “very irregular.”

*486

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lunneborg v. My Fun Life, Corp.
421 P.3d 187 (Idaho Supreme Court, 2018)
Lamb v. Robinson
620 P.2d 276 (Idaho Supreme Court, 1980)
Rosecrans v. Intermountain Soap & Chemical Co.
605 P.2d 963 (Idaho Supreme Court, 1980)
Anderson & Nafziger v. G. T. Newcomb, Inc.
595 P.2d 709 (Idaho Supreme Court, 1979)
Clark v. International Harvester Co.
581 P.2d 784 (Idaho Supreme Court, 1978)
Ross v. Olson
523 P.2d 518 (Idaho Supreme Court, 1974)
Big Butte Ranch, Inc. v. Grasmick
415 P.2d 48 (Idaho Supreme Court, 1966)
Dick v. Reese
412 P.2d 815 (Idaho Supreme Court, 1966)
Durfee v. Parker
410 P.2d 962 (Idaho Supreme Court, 1965)
H. J. Wood Co. v. Jevons
400 P.2d 287 (Idaho Supreme Court, 1965)
Stout v. Boise Cascade Corp.
390 P.2d 63 (Idaho Supreme Court, 1964)
Curzon v. Wells Cargo, Inc.
382 P.2d 906 (Idaho Supreme Court, 1963)
Knoblock v. Arenguena
380 P.2d 898 (Idaho Supreme Court, 1963)
Dawson v. Eldredge
372 P.2d 414 (Idaho Supreme Court, 1962)
Anderson v. Smith Frozen Foods of Idaho, Inc.
365 P.2d 965 (Idaho Supreme Court, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
346 P.2d 1063, 81 Idaho 480, 1959 Ida. LEXIS 243, Counsel Stack Legal Research, https://law.counselstack.com/opinion/c-r-crowley-inc-v-soelberg-idaho-1959.