Connell v. Higgins

150 P. 769, 170 Cal. 541, 1915 Cal. LEXIS 433
CourtCalifornia Supreme Court
DecidedJuly 15, 1915
DocketL.A. No. 3499.
StatusPublished
Cited by59 cases

This text of 150 P. 769 (Connell v. Higgins) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Connell v. Higgins, 150 P. 769, 170 Cal. 541, 1915 Cal. LEXIS 433 (Cal. 1915).

Opinion

*546 SHAW, J.

The defendant appeals from the judgment and from an order denying his motion for a new trial.

1. The preliminary objections of the respondent to the consideration of the appeal from the judgment and of the statement on motion for new trial are not well taken.

The order made reducing the amount of the judgment, in pursuance of the acceptance by the plaintiff of the conditional order denying a new trial, was not the entry of a new judgment. It did not destroy the appeal from the judgment already entered, nor make it necessary to take a new appeal from the judgment as so reduced, after the order reducing it was entered. It was a mere reduction of the judgment previously entered and left the appeal therefrom in full force, except that the damages were reduced by one thousand dollars.

February 12, 1912, was a legal holiday. Consequently, the stipulation of the parties extending to that day the time to propose the statement on motion for new trial, operated, under the law, to extend the time to and including February 13, 1912. Therefore, the order of the court, made on February 13, 1912, extending the time further until March 13, was within time and was effective to extend the time to the latter date. The rule of the superior court of Los Angeles County, then in force, providing, in substance, that where time had been extended by stipulation the court could not order a further extension beyond the period of thirty days, inclusive of the time given by the stipulation, did not deprive the superior court of power to grant an extension of time where there had been a previous extension by stipulation covering the period of thirty days. The superior- court, by section 1054 of the Code of Civil Procedure, is given power to extend the time for proposing a statement for a period of thirty days. This power it has and it cannot by its own rule divest itself thereof. Furthermore, in the absence of any showing to the contrary, this court would presume that the superior court disregarded the rule for sufficient cause and to subserve the ends of justice. This it has the power to do. (Sullivan v. Wallace, 73 Cal. 307, [14 Pac. 789]; Pickett v. Wallace, 54 Cal. 147; People v. Williams, 32 Cal. 287.) There is nothing to show that it was not done for-this reason. The presumption is that sufficient cause existed.

*547 The case was tried upon a third amended complaint. In such a case the previous pleadings need not be included in the transcript on appeal, unless they are necessary to present the question of the statute of limitations or the question of a departure from the original cause of action. Neither of these questions is presented upon these appeals. It was, therefore, unnecessary to insert the original complaint in the transcript. The objection that the statement is unintelligible because the plans and specifications of the contract which the plaintiff was required to perform are not set forth in full, goes to the merits of the ease and need not be considered here. It is for the appellant to present sufficient of the evidence and proceedings below to enable the court, on appeal, to decide the questions presented upon their merits. If he has not done this, the rulings of the court below cannot be disturbed. We proceed to consider the appeal on its merits.

2. On February 12, 1910, Connell and Higgins executed a contract in writing whereby Connell agreed to make and install a power plant in a building in Los Angeles, then in process of erection by Higgins. The contract price was $28,530, payable in three installments, one of $7,132.50, payable during the process of erection, a like amount payable at completion and acceptance, and a third of $14,265 payable thirty days thereafter. The first payment has been made, the others remain unpaid. Connell was to have the plant completed on or before July 1, 1910, and he was to have it so far completed as to be ready to furnish power to operate elevators in the building by May 1,1910, or, if unable to do so by that time, he was to provide a temporary plant for that purpose. He was not to be responsible for delays in the work caused by labor strikes or by the conduct of other contractors or persons performing work on said building. To facilitate the work, Higgins agreed that on March 1, 1910, he would give Connell possession of the engine room and sufficient space on the first floor of the building to handle and install machinery. The contract further provided that the work should be done according to the plans and specifications and to the satisfaction of “A. L. Haley, Architect, Inc.,” and one Martin, an engineer. There was also a provision in the form usual in such contracts declaring that if Connell neglected to supply sufficient workmen and materials, or to prosecute the work with diligence, and such, failure was sufficient *548 in the opinion of said architect and engineer to justify it, then, upon their certificate to that effect, and upon notice thereof to Connell, Higgins should have the right to terminate the contract, take possession of the premises, and complete the work himself, and that the expense of such completion by him should be deducted from any balance remaining unpaid upon the contract price. This clause of the contract was numbered IX therein and it is identical in terms with that of paragraph 16 of the contract set forth in the opinion in American-Hawaiian etc. Co. v. Butler, 165 Cal. 504, [133 Pac. 280], Connell was delayed in the beginning of his work by the failure of Higgins to have the engine room and space on the first floor ready. Other delays occurred by reason of labor strikes and from interference by other contractors and persons working upon the other portions of the building. Disputes arose from time to time between the parties concerning these delays and concerning the manner of performance by Connell of the work contracted for. On December 21, 1910, Connell gave notice to Higgins that he claimed that the work was complete and demanded its acceptance. Thereupon, on December 31, 1910, the architect and engineer named in the contract sent to Óonnell a letter stating that the power plant was not yet Complete, that it had not been installed in a good or substantial manner, or according to the contract, and including a list of the defects and matters in which the plant was unsound and not in conformity with the contract, and demanding that he immediately proceed to complete the same in accordance with the statements made. On January 6, 1911, the architect and engineer made their certificate in pursuance of paragraph IX of said contract, declaring that Connell has refused and neglected to supply skilled workmen and proper materials for the work or to pursue it with diligence, that the plant was still unsound and improper and failed to conform to the contract, and that the said refusal of Connell to make the plant conform to the contract was sufficient ground to justify Higgins in terminating the contract, taking-possession of the premises and the tools therein in use by Connell and, thereupon, proceeding to finish the work himself. On the same day Higgins served upon Connell a notice terminating the contract, in pursuance of said certificate, and stating that three days thereafter he would take possession of the' building, *549

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hohenshelt v. Superior Court
California Supreme Court, 2025
William Rouser v. Theo White
825 F.3d 1076 (Ninth Circuit, 2016)
Jeff D. Ex Rel. Belodoff v. Otter
643 F.3d 278 (Ninth Circuit, 2011)
Opinion No. (2000)
California Attorney General Reports, 2000
American Continental Life Insurance v. Ranier Construction Co.
607 P.2d 372 (Arizona Supreme Court, 1980)
Snyder v. State
577 P.2d 160 (Court of Appeals of Washington, 1978)
MacOmber v. State of California
250 Cal. App. 2d 391 (California Court of Appeal, 1967)
Wells Benz, Inc. v. United States
333 F.2d 89 (Ninth Circuit, 1964)
C. J. Wood, Inc. v. Sequoia Union High School District
199 Cal. App. 2d 433 (California Court of Appeal, 1962)
Gollaher v. Midwood Construction Co.
194 Cal. App. 2d 640 (California Court of Appeal, 1961)
Stevens v. Torregano
192 Cal. App. 2d 105 (California Court of Appeal, 1961)
1st Olympic Corp. v. Hawryluk
185 Cal. App. 2d 832 (California Court of Appeal, 1960)
Bonadelle Construction Co. v. Hernandez
337 P.2d 85 (California Court of Appeal, 1959)
Ansco Construction Co. v. Ocean View Estates, Inc.
337 P.2d 146 (California Court of Appeal, 1959)
Pacific Allied v. Century Steel Products, Inc.
327 P.2d 547 (California Court of Appeal, 1958)
Martin v. Karsh
298 P.2d 635 (California Court of Appeal, 1956)
Larson v. Thoresen
254 P.2d 656 (California Court of Appeal, 1953)
Magee v. Breckenridge
244 P.2d 103 (California Court of Appeal, 1952)
In Re Kinney Aluminum Co.
78 F. Supp. 565 (S.D. California, 1948)

Cite This Page — Counsel Stack

Bluebook (online)
150 P. 769, 170 Cal. 541, 1915 Cal. LEXIS 433, Counsel Stack Legal Research, https://law.counselstack.com/opinion/connell-v-higgins-cal-1915.