Ansco Construction Co. v. Ocean View Estates, Inc.

337 P.2d 146, 169 Cal. App. 2d 235, 1959 Cal. App. LEXIS 2059
CourtCalifornia Court of Appeal
DecidedMarch 30, 1959
DocketCiv. 23557
StatusPublished
Cited by18 cases

This text of 337 P.2d 146 (Ansco Construction Co. v. Ocean View Estates, Inc.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ansco Construction Co. v. Ocean View Estates, Inc., 337 P.2d 146, 169 Cal. App. 2d 235, 1959 Cal. App. LEXIS 2059 (Cal. Ct. App. 1959).

Opinion

ASHBURN, J.

This is an action for recovery of compensation for certain labor and materials furnished defendant (general contractor) in the excavation and construction of certain streets, curbs, gutters, etc., in a designated tract in the city of Palos Verdes Estates. The judgment runs in favor of plaintiff, but it appeals from (1) that portion which denies any interest prior to date of judgment, and (2) that portion which fixes an attorney fee for plaintiff, the claim being that the allowance of $264.20 was so small as to amount to an abuse of discretion. Respondent has filed no brief.

Appellant submitted a written bid for the job consisting of nine separate items, exemplified by number 1: “Excavate *237 from street areas and spread on adjacent lots and/or street areas. Approx: 8000 cu yds of earth at $0.61 per cu. yd.= 4880.00.” The bid items were carried into a written contract in the same form and figures. The total set forth in each document was: “Approx: total cost $28,590.56.” The addition was erroneous. The total should have been $33,421.76 j 1 difference was $4,831.20. Apparently the error was mutual and was not discovered until about May 27, 1957, when plaintiff billed defendant, after completion of the work, for the sum of $33,541.44, less a progress payment defendant had made in the sum of $5,240; net amount claimed being $28,301.44. Thereupon a controversy arose as to whether the contract was one for doing the work at an agreed price or upon a unit basis. Plaintiff sued for $28,301.44 with interest at 10 per cent per annum from June 10, 1957; its portion of the work was completed on May 25, 1957, and accepted by the city on June 11, 1957. The complaint also prayed for a reasonable attorney fee of $3,500.

The contract contained these pertinent provisions which enter into the determination of the questions of right to interest and amount of attorney fees: “That quantities of excavation and fill to be calculated from grade sheets established by your Engineer for the rough grading of tract. . . . Terms : Net cash, labor, material and equipment jobs, each completed portion payable within 10 days after date of completion of such portion. ... 1. If account is not paid when due, interest will be charged at the rate of 10% per annum. ... 9. Any attorney fees, costs or other expenses which may be incurred in the collection of monies due under this contract and/or in connection with any action involving this contract, will be paid by the buyer.”

The action was filed on August 1, 1957. Before trial and on November 6, 1957, defendant paid to plaintiff $23,356.56. After crediting this sum and the progress payment of $5,240 the court reached the conclusion that the net amount due was $4,504.81 for which amount judgment was rendered. This was predicated upon a finding that “the- actual quantities of materials and work performed by the plaintiff” at the prescribed rates was $33,101.37. Defendant did not dispute this at the trial but rested its defense upon a denial of any amount due, this upon the theory that the contract required plaintiff to do the work at a stipulated cost of $28,590.56. “Plaintiff’s *238 Exhibit III was introduced in evidence, without objection, which document contains a statement of the final quantities of labor and materials furnished to the defendant for the improvement of the defendant’s tract of land. No evidence whatsoever was introduced by the defendant tending to show that plaintiff had not, in fact, furnished the quantities of labor and materials stated in plaintiff’s Exhibit III.” (Narrative Statement p. 2.) Respondent’s failure to file a brief confesses the correctness of the findings and the sufficiency of the evidence to support them. (See 4 Cal.Jur.2d, § 496, p. 334.)

Plaintiff claimed interest from June 10, 1957, upon the sum of $28,301.44, at 10 per cent per annum. The court found the amount due to be $4,504.81 and denied interest except upon the judgment rendered on April 3, 1958.

The contract itself provides for interest from due date at 10 per cent per annum. Section 3289, Civil Code, says: “Any legal rate of interest stipulated by a contract remains chargeable after a breach thereof, as before, until the contract is superseded by a verdict or other new obligation.”

Aside from any contractual provision interest is awarded as damages by way of compensation for wrongful detention of money due plaintiff. (Sears, Roebuck & Co. v. Blade, 139 Cal.App.2d 580, 595 [294 P.2d 140].) But this occurs only when the sum is liquidated within the purview of Civil Code, section 3287 and the pertinent authorities. That section says: “Every person who is entitled to recover damages certain, or capable of being made certain by calculation, and the right to recover which is vested in him upon a particular day, is entitled also to recover interest thereon from that day, except during such time as the debtor is prevented by law, or by the act of the creditor, from paying the debt.” Liquidated damages have been defined “as those which were certain by computation from the face of the contract, or which might be made certain by reference to well-established market values plus computation.” (Lineman v. Schmid, 32 Cal.2d 204, 209 [195 P.2d 408, 4 A.L.R.2d 1380].) “The contention is made that the amount which the plaintiffs are entitled to recover in this case is unliquidated, and therefore interest should not be allowed until the entry of judgment. This contention, however, is not determinative of the question of interest. If the amount of the indebtedness or the amount owing can be calculated and determined from the statements rendered by the plaintiffs to the defendants, and that statement is found to be true and correct, it is a matter of mere *239 calculation. ’ ’ (Anselmo v. Sebastiani, 219 Cal. 292, 301 [26 P.2d 1].) To the same effect, see Engelberg v. Sebastiani, 207 Cal. 727, 729 [279 P. 795]; Chase v. National Indemnity Co., 129 Cal.App.2d 853, 865 [278 P.2d 68]; 28 Cal.Jur.2d § 5, pp. 399-400. Such was the situation at bar.

The trial judge’s ruling was controlled by the consideration that liability for any amount in excess of the sums paid before trial (i.e. $4,504.81) was the subject and the only subject of a bona fide dispute. But that is a false quantity in the problem. “The amount of interest to which the one party is entitled or for which the other is bound is not determinable by the misconceptions of the parties as to their rights or duties under the terms of their express contract, but by the terms of the contract itself as finally interpreted by the court. By the terms of this contract the defendant was bound to pay plaintiff the amount due upon his delivery as specified therein within a stated time after such delivery had been made and interest began to run upon such deferred payments under the foregoing provisions of the law relating to interest from the date they became due.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hakim v. Beshay CA2/7
California Court of Appeal, 2014
Cruz v. Ayromloo
66 Cal. Rptr. 3d 725 (California Court of Appeal, 2007)
Chesapeake Industries, Inc. v. Togova Entreprises, Inc.
149 Cal. App. 3d 901 (California Court of Appeal, 1983)
A. A. Baxter Corp. v. Colt Industries, Inc.
10 Cal. App. 3d 144 (California Court of Appeal, 1970)
Chandler-Simpson, Inc. v. Gorrell
464 P.2d 849 (Wyoming Supreme Court, 1970)
Heidt v. Miller Heating & Air Conditioning Co.
271 Cal. App. 2d 135 (California Court of Appeal, 1969)
Distefano v. Hall
263 Cal. App. 2d 380 (California Court of Appeal, 1968)
Rabinowitch v. Cal. Western Gas Co.
257 Cal. App. 2d 150 (California Court of Appeal, 1967)
Worthington Corp. v. El Chicote Ranch Properties, Ltd.
255 Cal. App. 2d 316 (California Court of Appeal, 1967)
Coleman Engineering Co. v. North American Aviation, Inc.
420 P.2d 713 (California Supreme Court, 1966)
Lucky Auto Supply v. Turner
244 Cal. App. 2d 872 (California Court of Appeal, 1966)
Conderback, Inc. v. Standard Oil Co.
239 Cal. App. 2d 664 (California Court of Appeal, 1966)
Peoples Finance & Thrift Co. v. Mike-Ron Corp.
236 Cal. App. 2d 897 (California Court of Appeal, 1965)
Adams v. Sharp
394 P.2d 943 (California Supreme Court, 1964)
Munier v. Hawkins
190 Cal. App. 2d 655 (California Court of Appeal, 1961)
Tevis v. Beigel
344 P.2d 360 (California Court of Appeal, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
337 P.2d 146, 169 Cal. App. 2d 235, 1959 Cal. App. LEXIS 2059, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ansco-construction-co-v-ocean-view-estates-inc-calctapp-1959.