Mahoney v. Oxford Realty Co.

133 A.D. 656, 118 N.Y.S. 216, 1909 N.Y. App. Div. LEXIS 2246
CourtAppellate Division of the Supreme Court of the State of New York
DecidedJuly 13, 1909
StatusPublished
Cited by5 cases

This text of 133 A.D. 656 (Mahoney v. Oxford Realty Co.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mahoney v. Oxford Realty Co., 133 A.D. 656, 118 N.Y.S. 216, 1909 N.Y. App. Div. LEXIS 2246 (N.Y. Ct. App. 1909).

Opinion

Laughlin, J.:

This action is brought to recover damages for the breach of a contract made between the parties and reduced to writing and signed by them on the 26th day of October, 1903. The contract provided for the construction .by the plaintiff of an eleven-story hotel building on premises known as Nos. 70, 72 and 74 West Fifty-fifth street in the borough of Manhattan, New York, according to plans and specifications, for the gross sum of $46,000. It was provided that the work should be completed on June 1, 1904, and it was understood, although not staled in the agreement, that . the foundation would be ready for plaintiff to proceed about the middle of November, 1903. The contractor who was constructing [658]*658the foundation disappointed the owner and the foundation was not ready for the performance of the Work by plaintiff until about the 3d day of May, 1904. Plaintiff neither refused to proceed . nor objected to this delay, and commenced, the work after May 1, 1904, on being notified so to do by the architect, without any further agreement or understanding. In these circumstances, the only effect of the delay was to extend the time of performance' for a period equal to the time plaintiff was ttyus delayed in Commencing the work and perhaps such additional time as might necessarily be required on.account of the postponement of the -commencement of the work. " The plaintiff alleges that he entered'upon the. performance of the work and continued the same with' due- diligence in all . respects as provided by the contract and. plans arid specifications, but that on the 11th day of October, 1904, the defendant'took pos- . session of the work and premises'and removed the plaintiff and his agents therefrom and terminated the contract and refused to permit the plaintiff to further perform- the same'. The plaintiff further alleges that the acts of the defendant in terminating the employment of the plaintiff and in taking possession of .the premises “ were in assumed complianeé and pretended conformity .with' the provisions and terms of article Y ” of the contract, but were actually in violation, thereof because he at no time refused or neglected to supply a sufficient number of.properly skilled workmen or materials of the proper quality, or to ■ prosecute "the work with promptness and diligence, or to perform any obligation resting upon him by virtue of the contract; and that the defendant failed to give the plaintiff the. three days’ written notice before terminating his employment and taking charge of the work, required by the contract, and no certificate was made by the architects as required by said article 5 of the contract. The' damages which the. plaintiff, according . to the.allegations of his complaint, .claims to have sustained and seeks to recover are the difference between the value of the work done on the contract, which is alleged to have been the sum of $40,137.56, and the amount paid on account of the contract work, which is alleged to have -been the sum of $30,0.42, and the loss of profits which the plaintiff would have made had he been permitted to fully . perform the contract, which he alleges would have- been the sum of $1,500, aggregating in all the sum of $11,595.56, for which, together [659]*659with the interest thereon from the 11th day of October, 1904, he demands judgment. The plaintiff recovered a verdict for $10,309.78 damages, to which was added interest from October 11, 1904, making the verdict as finally recorded $12,217.78.

Article 5 of the contract to which reference has been made provides as follows:

Art. V. Should the contractor at any time refuse or neglect to supply a sufficiency of properly skilled workmen, or of materials of the proper quality, or fail in any respect to prosecute the work with promptness and diligence, or fail in the performance of any of the agreements herein contained, such refusal, neglect or failure being certified by the architects, the ownér shall be at liberty, after three (3) days written notice to the contractor, to provide any such labor or materials, and to deduct the cost thereof from any money then due or thereafter to become due to the contractor under this contract; and if - the architects shall certify that such refusal, neglect or failure is sufficient ground for such action, the owner shall also be at liberty to terminate the employment of the contractor for the said work and to enter upon the premises and take possession, for the purpose of completing the work included under this contract, of all materials, tools and appliances thereon, and to employ any other person or persons to finish the work, and to provide the materials therefor; and in case of such discontinuance of the employment of the contractor he shall not he entitled to receive any further payment under this contract until the said work shall be wholly finished, at which time, if the unpaid balance of the amount to be paid under this contract shall exceed the expense incurred by the owner in finishing the work, such excess shall be paid by the owner to the contractor; but if such expense shall exceed such unpaid balance, the contractor shall pay the difference to the owner. The expense incurred by the owner as herein provided, either for furnishing materials or for finishing tbe work, and any damage incurred through such default, shall be audited and certified by the' architects, whose certificate thereof shall be conclusive upon the parties.”

The architects were Israels & Harder. On the 10th day of October, 1904, they made, executed and delivered to the defendant a certificate as follows:

[660]*660“ In accordance with the provisions of Article 5 of your contract under date of October 26th, 1903, with Robert J. Mahoney, we hereby certify that said Robert J. Mahoney has failed to supply a sufficiency of properly skilled workmen and materials on. the work called for under the above contract, upon which he hás been ordered to proceed by repeated notices duly served upon him in .accordance with the contract, and you are now, therefore, warranted in ter minating the employment of said Robert J. Mahoney as the contractor for the work and materials mentioned in the contract, and yourself to enter upon the premises and take possession for the purpose of completing the work and to employ any other person or persons to finish the same and to provide the materials therefor.
“ Very truly yours,
“ ISRAELS & HARDER.”

On the following day the defendant caused a notice to be served on the plaintiff, reciting that the defendant having duly given the plaintiff the three days’ notice required by the contract, and that the architects having duly certified that the “ refusal and neglect and failure ” on the part of the plaintiff “ to supply a sufficiency of properly skilled workmen and to prosecute the work with promptness and diligence ” constitutéd sufficient ground for. the termination of the contract — the owner thereby terminated the contract and had entered upon the premises and taken possession thereof for the purpose of completing the work in accordance with the provisions of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Duffy Bros. v. Bing & Bing, Inc.
217 A.D. 10 (Appellate Division of the Supreme Court of New York, 1926)
Faillace v. Village of Mamaroneck
207 A.D. 143 (Appellate Division of the Supreme Court of New York, 1923)
Connell v. Higgins
150 P. 769 (California Supreme Court, 1915)
Midtown Contracting Co. v. Goldsticker
165 A.D. 264 (Appellate Division of the Supreme Court of New York, 1914)
Willson & Adams Co. v. Mack Paving & Construction Co.
147 A.D. 141 (Appellate Division of the Supreme Court of New York, 1911)

Cite This Page — Counsel Stack

Bluebook (online)
133 A.D. 656, 118 N.Y.S. 216, 1909 N.Y. App. Div. LEXIS 2246, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mahoney-v-oxford-realty-co-nyappdiv-1909.