Jones v. City of New York

57 A.D. 403, 68 N.Y.S. 228

This text of 57 A.D. 403 (Jones v. City of New York) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jones v. City of New York, 57 A.D. 403, 68 N.Y.S. 228 (N.Y. Ct. App. 1901).

Opinion

Patterson, J.:

This cause is before us a second time, and now, as upon the former occasion, the sole question here is whether the referee’s conclusion that the plaintiffs were not entitled to the profits which they would have realized upon their contract but for the defendant’s breach, thereof, was correct.” (Jones v. City of New York, 47 App. Div. 39.) The question arises upon an appeal by the plaintiffs from a judgment entered in their own favor. The action was brought to recover damages for the breach of a contract entered into in the year 1896 between the plaintiffs and the proper authorities of the then city of New York for building an outlet sewer and appurtenances in Farragut street, from the East river to Hunt’s Point road, and in Hunt’s [404]*404Point road from Farragut street to Whittier street, and in Whittier street from Hunt’s Point road to Whitlock avenue, and in Whitlock avenue from Whittier street to Westchester avenue, and in Westchester avenue from Whitlock avenue to Edgewater road, and in Edgewater road from Westchester avenue to Jennings street. The work to be performed was extensive and important, and consisted of three classes. Of what was known as class 1, there were' to be 378 linear feet of construction; of class. 2,4,470 linear feet; of class 3, 6,835 linear-feet; and the total amount of compensation to be paid the plaintiffs as contractors was the sum of $408,211. All the work was to be completed according to the terms of the contract within 750 days. The plaintiffs "commenced work on the 12th of October, 1896. On or about the 22d of April, 1898, they stopped under circumstances presently to be adverted to. At that time but little more than one-quarter of the sewer had been built. By. a provision of the contract the plaintiffs were to receive payments from time- to time as the work progressed, and on the 20th of March, 1898, they were entitled to a payment of $4,535.51. All the conditions precedent' to the right to receive that sum were seemingly complied with, and a requisition or certificate for it was duly forwarded to the comptroller of the city of New York. It was not honored, payment being refused by the comptroller. The original contract was with the mayor, aldermen and commonalty of the city of New York and was one of those under which work was being done at the time the Greater New York charter went into effect and the consolidation of various municipal corporations, into the. present city of New York' took place. It would appear that sometime in or prior to March, 1898, a question arose as to the condition of the public debt of the city of New York and as to the constitutional limit of indebtedness of the old city of New York having, been.reached or exceeded before the 23d day of September, 1896, which was the date of the plaintiffs’ contract. The requisition for the payment of the $4,535.51 was not honored or paid by the comptroller because of a doubt existing in his mind respecting the constitutional debt limit above mentioned. Various conversations were had between the plaintiffs and their -attorney at law with the deputy comptroller and with the comptroller of the city of New York after March, 1898. They will [405]*405be referred to hereafter. On the 22d day of April, 1898, the plaintiffs served upon the commissioner and the deputy commissioner of sewers for the borough of the Bronx a written notice, in which, referring to their contract and to the payment due them of $4,535.51 and to the refusal of the compti-oller of the city of Mew York to pay that sum to them or their assigns, they proceed to state,, “ By reason of this act of the city in violation of the terms of the; contract in failing to make the said payment above referred to and by reason of other failures on the part of the city to keep the terms of the said contract, we have elected to treat the said failure to pay, as well as the other wrongful acts upon the part of the city as a breach of contract; to stop all work under the contract and to hold the city responsible for all loss and damages in the premises.”

Mothing more was ever done by the ¡fiaintiffs in performance of the contract, but they waited until the 28th of June, 1898, when they began this action in which they sought to recover for the value of the work they had actually performed and also for the alleged profits that would have accrued to them had they gone on and completed the whole work under the contract according to its requirements. On the first trial of the cause, the referee found that the plaintiffs were entitled to recover for work actually done and materials actually furnished under the contract, and this for the reason that the refusal of the comptroller to pay the requisition of March 24, 1898, was a breach of the contract on the part of the city. He declined to allow them as damages the anticipated profits they claimed, but in his report made a finding of fact which, had it been sustained by the evidence, we considered would have authorized a recovery of those profits. That finding was that the plaintiffs were informed by the officers of the. defendant that the contract was invalid and that no further payment could Or would be made thereunder. It was thought by this court that if that finding were properly made on the evidence, the conclusion that the plaintiffs were not entitled to the profits was au inaccurate one, and in the consideration of the subject the rule of law applicable to the case was sufficiently announced, at least for all the purposes of its disposition at the present time. We held, in substance, that the breach of the contract resulting from the refusal of the comptroller to pay the requisition of March 24, 1898, [406]*406was such as entitled the plaintiffs to abandon the work under.the contract and to recover for what had already been done, but that such a simple breach would not entitle the plaintiffs to prospective profits. On the second trial the learned referee has followed the rule laid down by this court respecting the effect of the breach. On this appeal we are in effect asked to hold that the breach carried with it the right to recover anticipated profits as well as the value of the work actually performed. TJpon a re-examination of the case, we find no reason for changing our view respecting the general effect upon the plaintiffs’ rights of this breach so far as we have now considered it. The case of Moore v. Taylor (42 Hun, 58) is quite in point, and Wharton v. Winch (140 N. Y. 290) is also a direct authority for the proposition as stated in the former opinion in this case. It is urged by the learned counsel for the appellants that the opinion in Wharton v. Winch (supra) contains merely dicta of the learned judge who wrote it, as to the effect of a breach of a contract by failure to pay an installment when 'due, but an examination of that opinion shows what is therein said on this subject was concurred in by the whole court, namely, that the failure to pay the installment when due upon the contract' involved in that case was not such a breach of the entire contract as would authorize the contractor to refuse to proceed further and to recover the profits he would have earned had the contract been fully performed. Our view of the contract in this cause, as set forth in our former opinion and now restated, is, that from the structure of the contract it is clear the mere failure to make payment of an installment due according to, its provisions, was not a breach of the entire contract entitling the plaintiffs to recover damages for profits as upon full completion of the contract. .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jones v. City of New York
47 A.D. 39 (Appellate Division of the Supreme Court of New York, 1900)

Cite This Page — Counsel Stack

Bluebook (online)
57 A.D. 403, 68 N.Y.S. 228, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jones-v-city-of-new-york-nyappdiv-1901.