Wells Benz, Inc. v. United States

333 F.2d 89, 1964 U.S. App. LEXIS 5211
CourtCourt of Appeals for the Ninth Circuit
DecidedJune 2, 1964
Docket18436_1
StatusPublished
Cited by5 cases

This text of 333 F.2d 89 (Wells Benz, Inc. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wells Benz, Inc. v. United States, 333 F.2d 89, 1964 U.S. App. LEXIS 5211 (9th Cir. 1964).

Opinion

333 F.2d 89

WELLS BENZ, INC., a corporation, Dale Benz, Inc., a
corporation, and The Fidelity and Casualty Company
of New York, a corporation, Appellants,
v.
UNITED STATES of America for the Use of MERCURY ELECTRIC
COMPANY, a corporation, and Founders Insurance
Company, a corporation, Appellees.

Nos. 18435, 18436.

United States Court of Appeals Ninth Circuit.

June 2, 1964.

Betts & Loomis, Albert H. Ebright, James A. Williams, Los Angeles, Cal., for appellants.

Wiseman & Elmore, Aaron Elmore, Beverly Hills, Cal., Anderson, McPharlin & Conners, Kenneth E. Lewis, Los Angeles, Cal., for appellees.

Before POPE, KOELSCH and BROWNING, Circuit Judges.

KOELSCH, Circuit Judge.

These are two separate suits which were heard together, both here and in the district court. They involve four Miller Act Claims (40 U.S.C. 270a and 270b), prosecuted by Mercury Electric Company (Mercury), a subcontractor, against Wells Benz, Inc. and Dale Benz, Inc. (Wells and Benz), the prime contractors, together with their surety, the Fidelity and Casualty Company of New York. They also include counter-claims asserted by Wells and Benz.1 The district court rendered judgment for Mercury on three of its claims and against Wells and Benz on all the counter-claims. Only Wells and Benz have appealed.

In December, 1958, Wells and Benz, as prime contractors, awarded Mercury, the subcontractor, contracts for the electrical work and equipment on several construction projects of the Federal Government at Point Arguello and Point Mugu, California. There were four jobs, each of which was the subject of a separate contract. They were known as the 'Instrumentation Job,' the 'Photo Tracking Job,' the 'Range Job' and the 'Supply Department Job.' Mercury fully performed the contract for the Range Job, but before the others were completed Wells and Benz ordered it to leave the materials and get off the jobs. Wells and Benz then engaged Dimac Electric Company, who finished the jobs on a cost-plus basis.2

These suits followed. Charging that Wells and Benz had wrongfully prevented performance of the contracts, Mercury sought damages on the theory of rescission. Wells and Benz admitted they had terminated Mercury's work, but alleged that Mercury had failed to 'live up to the terms and conditions of the subcontract(s)'; they filed counter-claims against Mercury for breach of contract.

The case was heard without a jury. At the close of the evidence, the court announced generally that Mercury was entitled to judgment on all its claims except the one relating to the Photo Tracking Job; that Wells and Benz had overpaid Mercury for work on that job and should recover the overpayment; the court further stated that Wells and Benz should take nothing by their counter-claims and directed counsel for Mercury to prepare and submit findings of fact and conclusions of law consistent with its views. At the settlement hearing, however, there was considerable discussion and controversy concerning the basis for the court's decision and the findings that the judge entered were much briefer and somewhat different than the ones proposed by Mercury. On appeal, Wells and Benz vigorously attack these findings on the grounds that they are insufficient to support the judgments, analytically incorrect and clearly erroneous, and above all, 'contrary to the real findings * * * and impressions of the trial court * * *.'

A comparison discloses that, aside from dates, job references and monetary amounts, the findings in each suit are substantially the same. Thus, so far as pertinent, those in the Instrumentation Job suit read:

'8. On (here appears the date) the Contractor (i.e., Wells and Benz) gave notice * * * to the plaintiff * * * cancelling said subcontract and ordering plaintiff to remove all its personnel from the job and cease further work thereon, but to leave its equipment and materials, and pursuant only to such order, plaintiff complied therewith and ceased further work thereon. Prior to said cessation, plaintiff substantially performed and complied with each and all of the terms, conditions and obligations of said subcontract on its part to be performed and at the time of said notice stood ready, able and willing to complete the performance of the balance of its work under said subcontract.

'9. On (here appears the date) plaintiff gave a notice in writing to contractor declaring a rescission of said subcontract, on the grounds among others as follows: '(a) Prevention of performance on the part of the contractor in peremptorily ordering plaintiff off the job; '(b) * * *

'10. At the time of the termination by contractor of said subcontract, there was and is due, owing and unpaid to plaintiff, after allowing full credits to the defendants for payments made by them, or either of them, thereafter to material suppliers and after allowing for and deducting any and all other credits and offsets to which they, or either of them, were, or might be, entitled, a balance of ( ) Dollars for the work and materials delivered by plaintiff on the basis of the contract price * * *. The following Conclusions of Law, insofar as they may be considered Findings of Fact, are so found by this court to be true in all respects * * *

'Conclusions of Law:

'4. The third party plaintiffs and counter-claimants are not entitled to any judgment whatsoever on the third party claim or cross-claim against third party defendants * * *.'

We agree with Wells and Benz that the judgments cannot be sustained unless these findings clearly reflect that Wells and Benz were not justified in preventing Mercury from performing the contracts. That is the gist of Mercury's claims and the rule is well settled that a claim '* * * may not be upheld as to any item that is not supported by definite findings of fact extending to all essential issues * * *.' United States v. Seminole Nation, 299 U.S. 417, 422, 57 S.Ct. 283, 287, 81 L.Ed. 316 (1937). But we reject Wells and Benz' thesis that these findings are fatally deficient. We refer especially to Finding No. 8. As already noted, the court therein stated (a) that Wells and Benz stopped Mercury's work; (b) that up to that time Mercury had substantially performed and complied with its contract, and (c) that Mercury stood ready, able and willing to complete the performance of the balance of its work under said contract. These three findings are tantamount to and require the conclusions that Wells and Benz' act was not warranted and afforded Mercury just cause to treat the contracts at an end.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Warren v. City of Chico
E.D. California, 2025
Pottinger v. City of Miami
359 F. Supp. 3d 1177 (S.D. Florida, 2019)
Martin Bloom Associates, Inc. v. Manzie
389 F. Supp. 848 (D. Nevada, 1975)
United States v. Cornish
348 F.2d 175 (Ninth Circuit, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
333 F.2d 89, 1964 U.S. App. LEXIS 5211, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wells-benz-inc-v-united-states-ca9-1964.