Smith v. Mathews Construction Co.

179 P. 206, 179 Cal. 797, 1919 Cal. LEXIS 608
CourtCalifornia Supreme Court
DecidedFebruary 24, 1919
DocketSac. No. 2719.
StatusPublished
Cited by4 cases

This text of 179 P. 206 (Smith v. Mathews Construction Co.) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Smith v. Mathews Construction Co., 179 P. 206, 179 Cal. 797, 1919 Cal. LEXIS 608 (Cal. 1919).

Opinion

MELVIN, J.

Defendants appeal from a judgment for something more than five thousand dollars, balance due for work done and materials furnished in the construction of improvements on the Forum building, in Sacramento. A lien on the property was also adjudged.

The action was based on a contract between plaintiff and defendant Mathews Construction Company and the work done and materials furnished thereunder. The contract price to be paid for plaintiff’s work and materials used for metal furring, lathing, and corner-beads and plastering and ceipenting the five-story addition to the building was $14,790, of which plain *799 tiff alleged $11,021.50 had been paid, leaving a balance of $3,768.50, which defendants owed but refused to pay. There was a separately stated cause of action for extra work and material amounting in value to $1,596.29. All of the defendants, except the Mathews Construction Company, were sued as claiming some ownership and interest in the 'real property involved.

By their answer defendants admitted that at all times in the complaint mentioned the Mathews Construction Company was a copartnership composed of C. J. and Lettie P. Mathews, but denied that said copartnership was at any time owner of the building or the land on which it was located. There was also an allegation that the copartnership was dissolved by the death of Lettie P. Mathews in November, 1915 (a time long subsequent to the filing of the complaint). The contract and its terms were admitted to be as pleaded, but there were elaborate pleadings to the effect that the work had not been done according to the contract and that the materials were deficient in amount and quantity. There was an allegation that Forum Investment Company, C. J. Mathews, R. A. Herold, and Frank J. Ruhstaller were at all pertinent times the owners of the property. It was admitted that extra work had been ordered, but defendants averred that this work was done in a crude, improper manner. It was also pleaded that by reason of changes in the original plans necessitating the extra work, “plaintiff was relieved from the necessity of using material required by the original plans and specifications, of the value of about Five Hundred Dollars ($500.00) which was to be credited upon said extra work.”

By way of counterclaim defendants alleged that at plaintiff’s instance and because of his defective work they did extra work on the building to the value of $674.05; that by reason of the omission by plaintiff of materials' required by the contract, they were entitled to judgment for $4,346.37; and that by reason of the improper and crude workmanship employed by plaintiff in applying the plaster and cement to the building, defendants had been damaged in the sum of twelve thousand dollars. There was a cross-complaint based upon the alleged insufficiency of the quantities of materials used by James F. Smith, the improper preparation and application of materials, and the poor workmanship. Damages were demanded in the sum of ten thousand dollars.

*800 The judgment was for plaintiff’s entire demand and against defendants on the counterclaim and cross-complaint.

Defendants contend that the judgment against the Mathews Construction Company was erroneous. The court found it to be true, as alleged in the answer, that the copartnership had been dissolved by the death of one of its members, which occurred subsequently to the execution of the contract and after the filing of plaintiff’s liens. It is insisted that the court was powerless to render a judgment against a copartnership no longer existing. When the complaint was filed the Mathews Construction Company was an existing copartnership. It is true that by their answer defendants alleged the dissolution of the copartnership by death of one of the partners, but nevertheless counsel appeared for all of the defendants, including the copartnership, and defended for them as they had a right to do. (Sec. 1585, Code Civ. Proc.) They may not complain, therefore, at the form of the judgment.

The principal attack of appellants is directed against certain findings with reference to the manner of performance of the contract. It was found that the work was done in accordance with the plans and specifications; that the materials used were proper, and mixed in the specified proportions; and that the work was done in a good and workmanlike manner, as required by the contract, plans, and specifications, except as follows:

‘ ‘ Some of the plastered surfaces were not straight and true, and some of the angles were not worked plumb, the exadt amount or number of which the evidence does not definitely disclose. This was caused by the act of the defendants in rushing the work and in requiring the plaintiff to place and apply second and third coats of plaster before previous coats of plaster were dry, and also from the fact that some of the lathing underlying said surface and said work was not laid on true and smooth by a previous contractor in charge thereof. That plaintiff notified defendants of such fact that such lathing was not so laid and defendants directed plaintiff to proceed with his work and to place the plaster upon such" surfaces and upon such lathing so, as aforesaid, improperly laid on by such other and independent contractor.
“That the scratch coat was not carried to the floor but to within less than five inches thereof,- and that such space was later filled in with the second or brown coat. This departure *801 from the terms of the contract was not willful or done with the purpose or intention to deceive or defraud the defendants, and it did not deceive them. It was done openly by the plaintiff, in good faith and in the belief that it was a performance of his contract, and was offered by him as a performance of the contract. It was in plain view of the defendants, who were constantly in and about the building, and they made no objection to this work, and it was at the time accepted by them as a performance of the contract. That the departures from the contract as herein stated were slight and unimportant and immaterial; that they were each and all known of by defendants and that such defendants were not deceived, defrauded or injured thereby.”

Appellants insist that the deviations from the strict letter of the contract (such, for example, as the failure in each room to carry the “scratch coat” clear to the floor at that part of the wall subséquently concealed by the baseboard) were intentional, willful violations of the agreement necessarily involving bad faith, and that the doctrine of substantial performance has no application. They also assert that such doctrine may only be invoked by pleading, and where, as here, plaintiff alleged full performance and the court found that there were any deviations, however slight, from strict performance on the part of the lien claimant, the judgment must be against him.

In support of the point last stated appellants cite such cases as Herdal v. Sheehy, 173 Cal. 163, [159 Pac. 422], and Daley v. Russ, 86 Cal. 114, [24 Pac.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Patrick J. Ruane, Inc. v. Parker
185 Cal. App. 2d 488 (California Court of Appeal, 1960)
Martin v. Karsh
298 P.2d 635 (California Court of Appeal, 1956)
Sparling v. Housman
214 P.2d 837 (California Court of Appeal, 1950)
Thomas Haverty Co. v. Jones
197 P. 105 (California Supreme Court, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
179 P. 206, 179 Cal. 797, 1919 Cal. LEXIS 608, Counsel Stack Legal Research, https://law.counselstack.com/opinion/smith-v-mathews-construction-co-cal-1919.