Practical Construction Company, a Corporation v. Granite City Housing Authority, a Corporation

416 F.2d 540, 1969 U.S. App. LEXIS 10871
CourtCourt of Appeals for the Seventh Circuit
DecidedSeptember 9, 1969
Docket16825
StatusPublished
Cited by11 cases

This text of 416 F.2d 540 (Practical Construction Company, a Corporation v. Granite City Housing Authority, a Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Practical Construction Company, a Corporation v. Granite City Housing Authority, a Corporation, 416 F.2d 540, 1969 U.S. App. LEXIS 10871 (7th Cir. 1969).

Opinion

KERNER, Circuit Judge.

Plaintiff-appellant, Practical Construction Co., filed suit against the Public Housing Administration under 28 U.S.C. § 1346 and the Granite City Housing Authority under 28 U.S.C. § 1332 to recover its cost of construction over and above the contract price. The suit against the Public Housing Administration, one of the defendants, was dismissed by the district court and no. appeal was taken. The district court granted summary judgment for the defendant-appellee, Granite City Housing Authority, on the basis of affidavits and documentary evidence and plaintiff appeals.

After an invitation for bids for the construction of housing for the elderly, Granite City entered into a written contract with Practical Construction for *542 construction of the housing on February-15, 1962. The contract contains certain provisions regarding procedures as to changes or disputes arising from the construction:

Paragraph 11(a) provides:

If the Contractor claims that any instructions by drawings or otherwise involve extra cost or extension of time, he shall, within ten days after the receipt of such instructions and in any event before proceeding to execute the work, submit his protest thereto in writing to the Local Authority, stating clearly and in detail the basis of his objections. No such claim shall be valid unless so made.

Paragraph 15 provides:

(a) All disputes, other than those required to be handled under Section 44 of the General Conditions, arising under this contract or its interpretations, whether involving law or fact, or both, or extra work, and all claims for alleged breach of contract shall within 10 days of commencement of dispute be presented to the contracting officer for decision. A copy of the notice of the dispute shall be forwarded to the Field Office of the Public Housing Administration. Such notice need not detail the amount of the claim, but shall state the facts surrounding the claim in sufficient detail to identify the claim, together with its character and scope. In the meantime, the Contractor shall proceed with the work as directed. The parties agree that any claim not presented within the time limit specified within this subsection is waived, except that if the claim is of a continuing character and notice of the claim is not given within ten days of its commencement, the claim will be considered only for a period commencing ten days prior to the receipt by the Local Authority of written notice thereof.
(b) The Contractor shall submit, in detail, his claim and his proof thereof. The decision of the Contracting Officer shall be approved in writing by the Public Housing Administration prior to its issuance. Any decision not so approved shall be a nullity. Each decision by the Contracting Officer shall be in writing and shall be mailed to the Contractor by registered mail, return receipt requested.
(c) If the Contractor does not agree with any decisions of the Contracting Officer, he shall except from the final release the decision in question.
(d) Provided the Contractor has:
(1) Given notice of any dispute within the time limit stated in 15(a) above;
(2) Presented his dispute to the Contracting Officer;
(3) Taken exception in his release from the Contracting Officer’s decision ; and
(4) Brought suit within 120 days after receipt of final payment under this contract or within six months of a written request by the Local Authority that he submit a final voucher and release, whichever time is the lesser.
The Contracting Officer’s decision shall not be final and conclusive but the dispute shall be tried in court on its merits. In the event the above conditions precedent have not been met, the Contractor hereby agrees that his noncompliance with the conditions precedent constitutes a waiver of his right to assert said claim.

The completion date in the contract was March 18, 1963.

While the construction was progressing, Granite City initiated two changes in the specifications. In each case, after a year of negotiation, adjustments were agreed to and made. Plaintiff *543 completed the project on July 17, 1963, and a Certificate of Release was submitted to plaintiff for signature on October 24, 1963. The plaintiff returned executed copies of the Certificate of Release on October 30, 1963, but included in its request for final payment, sums due as a result of extra work performed by the plaintiff. Defendant did not accept this Certificate of Release.

On April 20, 1964, the plaintiff sent defendant a new Certificate of Release which included a demand for payment of the undisputed balance and the cost of various unauthorized extras. Accompanying the Certificate were letters describing in detail each extra and requesting payment.

On September 10,1964, defendant sent plaintiff a letter in which it agreed to seven extra items totalling $2,258.98 included in the Certificate of April 20, 1964. Between September 16 and October 6, 1964, the plaintiff received from defendant various letters accompanied by findings of fact denying all other requests for payment of extras. The findings of fact as to each extra not only denied the claims on the merits but also on the grounds of failure to comply with paragraphs 11(a) and 15 of the contract. Defendant claims that plaintiff received final payment on April 20, 1965, but this is denied by the plaintiff and no documentary evidence has been submitted by either side. Plaintiff filed suit on September 30, 1965, to recover all the individual claims which had been denied in September and October of 1964.

Paragraphs 11(a) and 15 of the contract provide the method of settling all disputes as to recovery for extra work. Plaintiff, however, contends that neither party complied with the provisions as to change orders upon which payment was made, and, therefore, the defendant has waived his right to demand compliance. Plaintiff did not plead waiver in his complaint but rather stated “Practical Construction Company at all times has fully performed pursuant to the contract, except when prevented from doing so by defendant’s numerous material breaches of said contract.” The courts have held such a variance between the pleadings and proof fatal and have refused to admit evidence as to waiver. Corbin, On Contracts § 765. While plaintiff should be permitted to amend his complaint to plead waiver, 2 plaintiff in his amended complaint continued to allege full performance. We do not think that the failure to plead waiver should be the only basis for the decision, but the last minute assertion of such an issue in an answer to a motion for summary judgment does not constitute the trial of such an issue by express or implied consent within the meaning of Rule 15(b) of the Federal Rules of Civil Procedure.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Manion v. Roadway Package System, Inc.
938 F. Supp. 512 (C.D. Illinois, 1996)
Taylor v. Western & Southern Life Insurance
966 F.2d 1188 (Seventh Circuit, 1992)
Southcenter View Condominium Owners' Ass'n v. Condominium Builders, Inc.
736 P.2d 1075 (Court of Appeals of Washington, 1986)
A.J. Tenwood Associates v. Orange Senior Citizens Housing Co.
491 A.2d 1280 (New Jersey Superior Court App Division, 1985)
American Continental Life Insurance v. Ranier Construction Co.
607 P.2d 372 (Arizona Supreme Court, 1980)
Nuest v. Westinghouse Air Brake Company
313 F. Supp. 1228 (S.D. Illinois, 1970)
Midway Oil Co. v. Cities Service Oil Co.
49 F.R.D. 273 (S.D. Illinois, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
416 F.2d 540, 1969 U.S. App. LEXIS 10871, Counsel Stack Legal Research, https://law.counselstack.com/opinion/practical-construction-company-a-corporation-v-granite-city-housing-ca7-1969.