Cracchiolo v. Carlucci

157 P.2d 352, 62 Ariz. 284, 1945 Ariz. LEXIS 188
CourtArizona Supreme Court
DecidedMarch 23, 1945
DocketCivil No. 4656.
StatusPublished
Cited by16 cases

This text of 157 P.2d 352 (Cracchiolo v. Carlucci) is published on Counsel Stack Legal Research, covering Arizona Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cracchiolo v. Carlucci, 157 P.2d 352, 62 Ariz. 284, 1945 Ariz. LEXIS 188 (Ark. 1945).

Opinion

LaPRADE, J.

The appellants, hereinafter called the owners, and the appellee, Joe Carlucci, hereinafter called the contractor, made a building contract on July 16,1941, for construction of a tourist court or “motel” near Tucson. The appellee, W. M. Killen, was surety on the contractor’s bond for faithful performance of the contract. The motel was to be completed in accordance with an architect’s plans and specifications on or before November 15, 1941, for a price of $39,875. *286 In December 1941, the contractor turned the motel over to the owner, who opened the motel for business.

The contractor claimed that there was due him more than $14,000 on the contract and extras, which the owners refused to pay, claiming nonperformance of the contract in accordance with the plans and specifications, and damages for failure to complete the work on time. The dispute was submitted to arbitration by written agreement on March 11,1942. The arbitrators made a written award on June 5, 1942, and a supplemental award on June 15,1942. The arbitrators found, among other things, that the contractor had failed to comply with his contract in six particulars, and required that the contractor remedy these defects by July 31, 1942. The owners were required to pay the contractor all sums owing over $5,000, which they did.

The contractor, during June, July, and August, 1942, attempted to comply with the arbitration award, and by the end of August did substantially complete all work on five of the six defects, but failed to comply with Item 15 of the award, the largest and most costly part of the work to be done.

Item 15 of the award, which the contractor failed to fulfill, concerns the regrading and repaving of the motel driveway. This driveway, paved in form of a horseshoe, with thirty-two cabins around the outer edge, contains approximately 1800 square yards of paving. The original plans and specifications required that the driveway paving be not less than twelve inches below the floors of the motel cabins and have a drainage slope of at least twelve inches from the back of the property to the highway so as to afford proper drainage. When the contractor finished with his original work in December 1941, the floors of several cabins were almost flush with the driveway pavement, and the driveway had a drainage slope of only four inches from back of the property to the highway. The arbitrators7 award required that this driveway be regraded and *287 repaved under competent engineering supervision, and “that in no case shall the finish paving grade at entrance to any cabin be less than six inches below finish floor of that cabin.”

Shortly after the award was rendered, the contractor employed two of the arbitrators, who were qualified engineers and architects, to draw plans for regrading and repaving the motel driveway in accordance with Item 15 of the award. After several delays, due chiefly to the contractor’s insistence that the plan for regrading and repaving should be as simple and as inexpensive as possible, “Plan F” was designed by the contractor’s two engineers, and approved by the contractor shortly before September 9,1942. The owners were asked to approve this plan, but took no action for about two weeks, and before they did approve the plan, the contractor told his engineers to “Forget it, we are going to court,” and proceeded with his lien foreclosure action.

In the trial of the case, the two engineers and architects, who had been the arbitrators, testified that it would cost more than $8,000 to comply with “Plan F.-” The contractor testified the cost of compliance with “Plan F” would be not more than $2,500. A paving contractor, Mr. F. H. Martin, testified that compliance with “Plan F,” with a drainage slope of between fifteen to eighteen inches, would cost $3,104.07. (“Plan F” specified a drainage slope of approximately thirty inches.) The court adopted the paving contractor’s cost figure, and entered judgment for failure to comply with the award as interpreted in “Plan F,” but with a drainage slope of fifteen to eighteen inches, at $3,104.07. There were also assessed damages for past, i.e., subsequent to July 31, 1942, and probable future loss of rentals estimated to accrue during the repaving process in the sum of $1,100. Subtracting the total of 'those two sums and two other incidentals, from the $5,000 retained by the owner under the arbitration *288 award, the court arrived at a balance due from the owners to the contractor of $744.93. This appeal is from the judgment of the court foreclosing the contractor’s lien for this amount, after motions to amend findings and judgment and for new trial had been overruled.

Appellants’ first three assignments of error challenge the conclusion of the court that by virtue of said arbitration agreement and award they were not entitled to any recovery for alleged damages in loss of rentals prior to July 31, 1942, and the rulings excluding proffered evidence to prove such losses.

The submission agreement was general rather than special. In this regard it recited that whereas

“ ... a dispute has arisen between the parties in connection with and arising out of their relation and the compensation to be paid the contractor, and the performance by the contractor of work thereon . . . the parties have agreed to submit all controversies and differences between them to arbitration, ...”

The agreement contains no specification or enumeration as to the various items in dispute. A submission agreement is a contract and must comply with the formal requisites of all agreements. 3 Am. Jur., Arbitration and Award, Section 38. (Cases cited.) Among other things it must contain a definite and sufficient statement of the matter to be referred to arbitration. (Id.) Eeference to arbitrators of “all matters in dispute” with reference to the subject-matter is sufficiently certain and comprehensive to support an award. King v. Cook, 1 T. U. P. Charlt., Ga., 286, 4 Am. Dec. 715; Shackelford v. Purket, 2 A. K. Marsh, Ky., 435, 12 Am. Dec. 422.

Where the submission is general, parol evidence is admissible in order to remove uncertainty as to what matters are actually in dispute. Davy’s Ex’rs. v. Faw, 7 Cranch 171, 3 L. Ed. 305; Shackelford v. *289 Purket, 2 A. K. Marsh, Ky., 435, 12 Am. Dec. 422. In the last case cited, the court said:

“ . . . Without the aid of parol evidence, it would be impossible to sustain a general submission of all matters in dispute. For as the submission contains no suggestion of the matters disputed, it must be inoperative, unless those matters can be ascertained by matters extraneous from the submission; ...”

It is not possible for us to tell from an examination of the submission agreement what matters were in dispute or what matters were submitted. Apparently the parties appeared before the arbitrators and submitted the matters in dispute. The arbitrators ’ award states that the award includes “such items of' dispute as were submitted ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Southwest v. Burns
Court of Appeals of Arizona, 2014
American Continental Life Insurance v. Ranier Construction Co.
607 P.2d 372 (Arizona Supreme Court, 1980)
Lane v. Bisceglia
488 P.2d 474 (Court of Appeals of Arizona, 1971)
Funk v. Funk
434 P.2d 529 (Court of Appeals of Arizona, 1967)
Allen D. Shadron, Inc. v. Cole
419 P.2d 520 (Arizona Supreme Court, 1966)
Caldwell v. Tilford
367 P.2d 239 (Arizona Supreme Court, 1961)
Jannis v. Ellis
308 P.2d 750 (California Court of Appeal, 1957)
Fineg v. Pickrell
305 P.2d 455 (Arizona Supreme Court, 1956)
Zelle v. Chicago & North Western Railway Co.
65 N.W.2d 583 (Supreme Court of Minnesota, 1954)
Haener v. Albro
249 P.2d 919 (Idaho Supreme Court, 1952)
Gillespie Land & Irrigation Co. v. Jones
164 P.2d 456 (Arizona Supreme Court, 1945)

Cite This Page — Counsel Stack

Bluebook (online)
157 P.2d 352, 62 Ariz. 284, 1945 Ariz. LEXIS 188, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cracchiolo-v-carlucci-ariz-1945.