Southwest v. Burns

CourtCourt of Appeals of Arizona
DecidedMarch 27, 2014
Docket1 CA-CV 12-0808
StatusUnpublished

This text of Southwest v. Burns (Southwest v. Burns) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southwest v. Burns, (Ark. Ct. App. 2014).

Opinion

NOTICE: NOT FOR PUBLICATION. UNDER ARIZ. R. SUP. CT. 111(c), THIS DECISION DOES NOT CREATE LEGAL PRECEDENT AND MAY NOT BE CITED EXCEPT AS AUTHORIZED.

IN THE ARIZONA COURT OF APPEALS DIVISION ONE

SOUTHWEST FARM SERVICES, LTD. PARTNERSHIP, an Arizona limited partnership Plaintiff/Appellee,

v.

ROBERT BURNS and JEANNE BURNS, husband and wife dba ROBERT BURNS ARCHITECTS, INC., Defendants/Appellants.

No. 1 CA-CV 12-0808 FILED 3-27-2014

Appeal from the Superior Court in Maricopa County No. CV2010-092562 The Honorable Emmet J. Ronan, Judge

AFFIRMED

COUNSEL

Grant & Vaughn, P.C., Phoenix By Kenneth B. Vaughn, Sharon R. Sprague Counsel for Plaintiff/Appellee

Jeffrey M. Zurbriggen, P.C., Phoenix By Jeffrey M. Zurbriggen Counsel for Defendants/Appellants SOUTHWEST v. BURNS Decision of the Court

MEMORANDUM DECISION

Judge Lawrence F. Winthrop delivered the decision of the Court, in which Presiding Judge Patricia A. Orozco and Judge Kenton D. Jones joined.

W I N T H R O P, Judge:

¶1 Robert and Jeanne Burns, doing business as Robert Burns Architects, Incorporated, appeal from a judgment and award of attorneys’ fees in favor of Southwest Farm Services, Limited Partnership on a breach of contract claim. For the reasons stated below, we affirm.

FACTUAL AND PROCEDURAL BACKGROUND

¶2 Southwest Farm Services, Limited Partnership (“Southwest”) is a hay brokering business. In August 2006, Southwest contracted with Robert Burns Architects, Incorporated, 1 for the development of a preliminary project site plan to develop property owned by Southwest and intended for business operations (the “Preliminary Site Plan Contract”). The price of services in the Preliminary Site Plan Contract was $5,600. In October 2006, Southwest contracted with Burns to provide more comprehensive architectural and engineering services related to the construction of buildings (the “Construction Design Contract”). In this contract, Southwest hired Burns to design and provide construction documents and engineering services for several buildings, a gate entry, and walls on the property. The price of services in the Construction Design Contract was $182,950, payable in six payments pursuant to a schedule set forth in the contract.

¶3 Southwest paid Burns $165,970.51 through June 2009. This included approximately $5,600 Southwest paid Burns on the Preliminary Site Plan Contract prior to signing the Construction Design Contract. Although Burns furnished preliminary site plans and later revised those

1 Robert Burns entered the contract doing business as Robert Burns Architects, Inc. Southwest later learned the corporation had been dissolved in 2002 and filed an amended complaint alleging that Robert Burns and the marital community were personally liable for the breach of contract. We refer to the defendants collectively as “Burns.”

2 SOUTHWEST v. BURNS Decision of the Court

site plans, Burns never delivered to Southwest final, signed, and sealed construction documents under the Construction Design Contract. Robert Burns testified that he would have delivered signed and sealed documents upon receipt of the final payment, which never occurred.

¶4 In October 2009, Southwest notified Burns that it considered Burns to be in material breach and demanded delivery of final construction documents in exchange for payment of the $10,959.49 balance due on the contract or a refund of the money Southwest paid Burns. Burns did not respond. Southwest made a second identical demand in March 2010, to which Burns also did not respond.

¶5 Southwest then filed a complaint for breach of contract. Burns answered and counterclaimed for breach of contract, bad faith, and unjust enrichment. At a one-day bench trial, the trial court received evidence of Burns’ invoices to Southwest and payment from Southwest to Burns. The court also heard testimony from Michael Perez, Southwest’s limited partner and manager, and Robert Burns. The trial court ruled that final payment to Burns on the Construction Design Contract was not due until there was “100% completion of the construction documents and submitt[al] to Maricopa County and approval of the building permit by Maricopa County.” The trial court found that no final, signed, and sealed plans had been submitted and there was no approved building permit. The trial court concluded that Southwest did not breach the Construction Design Contract because the final payment was not yet due. The court rejected Burns’ claim that its nonperformance was justified as well as Burns’ claim for unjust enrichment on the Construction Design Contract, finding that Southwest could no longer use the work performed by Burns. However, the trial court implicitly found that Burns had completed the Preliminary Site Plan Contract by reducing Southwest’s claimed damages by the value paid for services under that contract.

¶6 The court awarded Southwest a judgment of $160,330.85, $65,467.70 in prejudgment interest, and $48,431.90 in attorneys’ fees. Burns filed a timely notice of appeal. We have appellate jurisdiction pursuant to Arizona Revised Statutes (“A.R.S.”) section 12-2101(A)(1) (West 2014). 2

2 We cite the current Westlaw version of the applicable statutes and rules unless revisions material to this decision have since occurred.

3 SOUTHWEST v. BURNS Decision of the Court

DISCUSSION

I. Breach of Contract

¶7 Burns argues the trial court erred when it concluded that Burns breached the Construction Design Contract by failing to submit final plans to Maricopa County and by failing to obtain an approved building permit. 3 Interpretation of a contract is a question of law to be decided de novo. Polk v. Koerner, 111 Ariz. 493, 495, 533 P.2d 660, 662 (1975). On appeal, we view the evidence in the light most favorable to supporting the judgment and will accept the trial court’s findings of fact absent clear error. Id. at 494, 533 P.2d at 661.

¶8 Arizona courts strive to enforce contracts according to the parties’ intent. Taylor v. State Farm Mut. Auto. Ins. Co., 175 Ariz. 148, 152, 854 P.2d 1134, 1138 (1993). “In ascertaining the parties’ intent, the court will look to the plain meaning of the words as viewed in the context of the contract as a whole.” United Cal. Bank v. Prudential Ins. Co. of America, 140 Ariz. 238, 259, 681 P.2d 390, 411 (App. 1983).

¶9 Burns contends that the scope of work detailed in the Construction Design Contract did not require it to submit final plans to Maricopa County or obtain an approved building permit. The contract’s compensation and payment schedule, however, states that Southwest shall make its fifth payment “[u]pon 100% completion of the construction documents and Submittal to Maricopa County” and the final payment “[u]pon approval of the building permit by Maricopa County.” Burns contends that these provisions only triggered payments and did not require Burns to submit final plans or obtain a building permit. Our adoption of Burns’ interpretation of the scope of work language contained within the contract would render the language in the compensation and payment schedule meaningless. The payments are dependent upon Burns completing the items listed in the schedule. If Burns was not obligated to provide these services, this language would be superfluous.

¶10 Burns also argues it was not obligated to submit final plans or obtain a building permit because the parties had orally modified the Construction Design Contract and a valid novation occurred.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Northern Arizona Gas Service, Inc. v. Petrolane Transport, Inc.
702 P.2d 696 (Court of Appeals of Arizona, 1984)
Parks v. American Cas. Co. of Reading, Pa.
572 P.2d 801 (Arizona Supreme Court, 1977)
Polk v. Koerner
533 P.2d 660 (Arizona Supreme Court, 1975)
Darner Motor Sales, Inc. v. Universal Underwriters Insurance
682 P.2d 388 (Arizona Supreme Court, 1984)
United California Bank v. Prudential Insurance Co. of America
681 P.2d 390 (Court of Appeals of Arizona, 1983)
Fairway Builders, Inc. v. Malouf Towers Rental Co.
603 P.2d 513 (Court of Appeals of Arizona, 1979)
Taylor v. State Farm Mutual Automobile Insurance
854 P.2d 1134 (Arizona Supreme Court, 1993)
Berryhill v. Moore
881 P.2d 1182 (Court of Appeals of Arizona, 1994)
Adelman v. Christy
90 F. Supp. 2d 1034 (D. Arizona, 2000)
Englert v. Carondelet Health Network
13 P.3d 763 (Court of Appeals of Arizona, 2000)
Estate of Reinen v. Northern Arizona Orthopedics, Ltd.
9 P.3d 314 (Arizona Supreme Court, 2000)
Loiselle v. COSAS MANAGEMENT GROUP, LLC
228 P.3d 943 (Court of Appeals of Arizona, 2010)
Trustmark Insurance v. Bank One, Arizona, NA
48 P.3d 485 (Court of Appeals of Arizona, 2002)
Cracchiolo v. Carlucci
157 P.2d 352 (Arizona Supreme Court, 1945)

Cite This Page — Counsel Stack

Bluebook (online)
Southwest v. Burns, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southwest-v-burns-arizctapp-2014.