Diamos v. Hirsch

372 P.2d 76, 91 Ariz. 304, 1962 Ariz. LEXIS 292
Arizona Supreme Court·Decided June 6, 1962·No. 6633·Published·Cited by 26 cases

Opinion

STRUCKMEYER, Justice.

Plaintiff commenced this action to recover damages sustained as a result of an alleged breach of contract by anticipatory repudiation. Defendants filed a counterclaim alleging the breach was by the plaintiff. This is an appeal from a judgment entered on a directed verdict in favor of *305 defendants and from the judgment entered in favor of defendants on their counterclaim.

On November 20, 1956, plaintiff and defendants entered into an agreement the terms of which provided that plaintiff would construct a building on land owned by him and lease it to defendants for ten years. The rent clause of the agreement set forth a mathematical formula, the purpose of which was to establish the total amount of rent for the ten year period. 1 Within a day or two after signing the agreement, plaintiff’s agent contacted defendant Victor Hirsch and informed him that there had been a mistake in the rent provision in that the figure of $1,200 used in the formula should have been $12,000. Mr. Hirsch agreed that there had been an error and orally promised to give plaintiff a letter setting forth the monthly rent when the bids were in. Neither party contended that the $1,200 figure was correct and later, after suit was brought, the parties stipulated at the pre-trial conference that the figure $1,-200 be changed to read $12,000 in order to eliminate a count for reformation.

A satisfactory bid for the construction of the building was received on January 27, 1957. The following day Hirsch, one of the defendants, went to the plaintiff’s office and presented him with an addendum which he had prepared in lieu of the letter. The addendum set forth the monthly rent and also contained four additional items. 2 The first item setting forth the monthly rent *306 was agreeable to plaintiff, however a dispute arose over the four additional items. After discussing the matter for an hour and a half, the parties were unable to agree on all of the additional items. The conference between the parties ended with neither party having signed the addendum. All further discussion and correspondence on the matter was carried on by the parties’ attorneys.

During the next three weeks four letters were written and exchanged. The final letter written on February 18, 1957, by plaintiff’s attorney stated that plaintiff was willing and ready to carry out the terms of the agreement and that construction would start immediately if defendants would inform plaintiff in writing that the rent would be $200 per month for the first year and $250 per month for the last nine years of the lease. The defendants did not inform plaintiff in writing to this effect. There was no further discussion or correspondence on the matter.

On May 27, 1957, plaintiff commenced this action seeking to recover architectural expenses and attorney’s fees incurred by reason of defendants alleged breach of the agreement. Defendants filed a counterclaim alleging that plaintiff had breached the agreement by failing to construct the building. Thereafter plaintiff filed an amended complaint alleging that on or about January 28, 1957, defendants repudiated the agreement and refused to perform any of the conditions therein. On these issues the case was tried. At the conclusion of plaintiff’s case the trial court granted defendants’ motion for a directed verdict and allowed the trial to proceed on defendants’ counterclaim. The jury returned a verdict in favor of defendants on their counterclaim in the amount of $7,988.38. After a denial of plaintiff’s motion for a new trial, this appeal was perfected.

Plaintiff’s first assignment of error directs our attention to the question of whether the trial court erred in directing a verdict against plaintiff on his claim of repudiation and directing a verdict for defendants on their counterclaim for breach of the covenant to erect a building. It should be noted that the court did not direct a verdict on the counterclaim. The court did instruct the jury as a matter of law that plaintiff violated the terms of the agreement and left to the jury only the issue of damages. It is plaintiff’s position that the evidence established the elements of his claim and entitled him to have the jury decide the fact questions and render verdicts accordingly on the claim and counterclaim.

Plaintiff in his amended complaint alleged that defendants repudiated the agree *307 ment on January 28, 1957, when defendant Hirsch met with plaintiff and submitted the addendum. Plaintiff further contends, as he did below, that in any event the letter written by defendant’s attorney on February 13, 1957, constituted a repudiation of the agreement.

We have recognized that an action may be maintained for breach of contract based upon the anticipatory repudiation by one of the parties to the contract. Sarle v. School Dist. No. Twenty-Seven of Pima County, 32 Ariz. 96, 255 P. 994. It is well established that in order to constitute an anticipatory breach of contract there must be a positive and unequivocal manifestation on the part of the party allegedly repudiating that he will not render the promised performance when the time fixed for it in the contract arrives. Mobley v. New York Life Ins. Co., 295 U.S. 632, 55 S.Ct. 876, 79 L.Ed. 1621, 99 A.L.R. 1166; Salot v. Wershow, 157 Cal.App.2d 352, 320 P.2d 926; Atkinson v. District Bond Co., 5 Cal.App. 2d 738, 43 P.2d 867; Preston v. Love, 240 S.W.2d 486 (Tex.Civ.App.1951); 4 Corbin on Contracts § 973 (1951); 5 Williston on Contracts § 1324 (rev. ed. 1937); Restatement of the Law of Contracts § 318. And as succinctly pointed out in § 319 of the Restatement of the Law of Contracts, the effect of a repudiation is nullified:

“(a) Where statements constituting such a repudiation are withdrawn by information to that effect given by the repudiator to the injured party before he has brought an action on the breach or has otherwise materially changed his position in reliance on them;”

At the conclusion of plaintiff’s case the trial judge upon defendants’ motion for a directed verdict reviewed the evidence and concluded that there was insufficient evidence to support plaintiff’s contention that there had been a repudiation and that if defendants had repudiated, the repudiation had been nullified thereafter.

We have examined the evidence and are of the opinion that the trial court did not err in granting defendants’ motion. George Nick Diamos, son of plaintiff, was present at the January 28th conference and testified (plaintiff did not testify) that Hirsch implied that he wanted plaintiff to sign the addendum or defendants would not perform.

Free access — add to your briefcase to read the full text and ask questions with AI

Diamos v. Hirsch, 372 P.2d 76, 91 Ariz. 304, 1962 Ariz. LEXIS 292 (Ark. 1962).

372 P.2d 76 (Diamos v. Hirsch) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Chandler v. Roosevelt
Court of Appeals of Arizona, 2024
Le Canard v. Thorpe
Court of Appeals of Arizona, 2021
Spencer v. Asher
Court of Appeals of Arizona, 2019
Parus Holdings, Inc. v. Worldcom, Inc.
424 F. App'x 32 (Second Circuit, 2011)
Frank Lloyd Wright Foundation v. KROETER
697 F. Supp. 2d 1118 (D. Arizona, 2010)
Ratliff v. Hardison
199 P.3d 696 (Court of Appeals of Arizona, 2008)
Alvin S. Ratliff v. Daniel M. Hardison, Sr.
Court of Appeals of Arizona, 2008
In Re WorldCom, Inc.
368 B.R. 308 (S.D. New York, 2007)
Healey v. Coury
783 P.2d 795 (Court of Appeals of Arizona, 1989)
Holt v. Utica Mutual Insurance
759 P.2d 623 (Arizona Supreme Court, 1988)
Oldenburger v. Del E. Webb Development Co.
765 P.2d 531 (Court of Appeals of Arizona, 1988)
Snow v. Western Savings & Loan Ass'n
730 P.2d 204 (Arizona Supreme Court, 1987)
United California Bank v. Prudential Insurance Co. of America
681 P.2d 390 (Court of Appeals of Arizona, 1983)
Davis v. Tucson Arizona Boys Choir Society
669 P.2d 1005 (Court of Appeals of Arizona, 1983)
American Continental Life Insurance v. Ranier Construction Co.
607 P.2d 372 (Arizona Supreme Court, 1980)
Wippman v. Rowe
540 P.2d 141 (Court of Appeals of Arizona, 1975)
McMahon v. Fiberglass Fabricators, Inc.
496 P.2d 616 (Court of Appeals of Arizona, 1972)
Vinnell Corp. v. State ex rel. Skousen
490 P.2d 21 (Court of Appeals of Arizona, 1971)
Hurwitz v. DAVID K. RICHARDS & COMPANY
436 P.2d 794 (Utah Supreme Court, 1968)