Alterio v. Biltmore Construction Corp.

377 A.2d 237, 119 R.I. 307, 1977 R.I. LEXIS 1908
CourtSupreme Court of Rhode Island
DecidedAugust 30, 1977
Docket75-205-Appeal
StatusPublished
Cited by49 cases

This text of 377 A.2d 237 (Alterio v. Biltmore Construction Corp.) is published on Counsel Stack Legal Research, covering Supreme Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Alterio v. Biltmore Construction Corp., 377 A.2d 237, 119 R.I. 307, 1977 R.I. LEXIS 1908 (R.I. 1977).

Opinion

*309 Bevilaclqua, C.J.

This is an appeal from a judgment entered against both defendants in the amount of $3,069.88 after trial before a Superior Court justice sitting without a jury. The plaintiffs sought to recover damages for breach of a building contract on the grounds that defective materials were used and the construction was not done in a workmanlike manner.

The plaintiffs, William and Adi Alterio, are owners of a residence located at 55 Naples Avenue, Warwick, Rhode Island. The defendants are the Biltmore Construction Corp., a Rhode Island corporation, and Felix Carlone, president and treasurer of the corporation.

On April 6, 1970 plaintiffs entered into a written contract with Biltmore Construction Corp. to add a family room and garage to plaintiff’s residence for a price of $4,890. The contract was executed by plaintiffs and by defendant Felix Carlone as president and treasurer of the Biltmore Construction Corp. Work was commenced in the latter part of June 1970. During the construction of the additions, the parties orally agreed to enlarge a cement patio and construct a roof over the patio for an additional price of $500.00.

At trial plaintiff William Alterio testified that, with the exception of an Anderson Door and bow window selected *310 by plaintiffs, defendant Carlone had complete control over the selection of construction materials, and that the majority of work was performed by defendant Carlone’s son and a helper. In addition, he testified that on July 20, 1970 he noticed defects in the construction and notified defendant Carlone of these defects, but they were not corrected.

Construction was completed in August 1970. The plaintiffs made periodic payments to defendant Carlone from July 1970 through February 21, 1977, at which time plaintiffs refused to pay the $820 balance due because the defects were not rectified.

In October of 1971, at plaintiffs’ request, Albert DiDonato, a Providence contractor, inspected plaintiffs’ residence and submitted an estimate of repairs in the amount of $3,889.88. At trial DiDonato was unable to specify the cost of the labor and materials for each suggested repair, but he testified, over objection, that his estimate of $3,889.88 consisted of $3,075 for labor and materials, $461.25 for overhead (15 percent), and $353.63 for profit (10 percent). He stated that at the time he drew up the estimate he calculated the cost of labor and materials for each defect, but he no longer had all of these figures. He did testify as to the cost for correction of certain, but not all, of the defects, and the figures he was able to specify totaled approximately $900 for labor and materials. Although objected to, the 1971 written estimate in the amount of $3,889.88 was admitted into evidence.

The defendants’ expert witness, Frank DeFusco, a Providence contractor, testified that he had recently examined plaintiffs’ residence and had observed certain defects. He testified as to the cost at the present time for repairing each defect, and the prices he quoted totaled approximately $515.

The trial justice rejected the testimony of defendants’ expert because he did not find it credible. As a result, although he felt DiDonato’s estimate should have been more *311 specific, he adopted the $3,889.88 estimate as the fair and reasonable cost'of repairing the defects. From that amount he deducted the $820 withheld by plaintiffs, and awarded damages in the sum of $3,069.88 plus interest and costs against both defendants. The trial justice entered judgment against defendant Carlone as well as against Biltmore Construction Corp. because he was of the opinion that plaintiffs relied on Carlone’s personal promises and assurances and that they contracted with defendants “on the basis of a long personal, not corporate, relationship.” The defendants’ motion for a new trial was denied, and defendants appealed.

The issues raised by the instant appeal are: (1) whether the estimate of repairs prepared by plaintiffs’ expert was inadmissible and whether the amount of damages awarded was clearly wrong; and (2) whether the trial justice erred in entering judgment against Felix Carlone as an individual.

I

The defendants contend that there was no legally competent evidence to support the trial justice’s award of damages. This contention necessarily involved consideration of defendants’ argument that the trial justice erred in admitting into evidence the estimate of repairs prepared by plaintiffs’ expert and testimony concerning this item, since the trial justice’s award was based on his acceptance of this evidence.

It is settled law that a bill for repairs unsupported by testimony cannot prove itself and is therefore inadmissible to prove the existence of the alleged defects or the cost of repairing them. Krasnoff v. Flynn, 97 R.I. 129, 131, 196 A.2d 158, 160 (1963); Rossilli v. Iacovelli, 88 R.I. 456, 149 A.2d 709 (1959); Nock v. Lloyd, 32 R.I. 313, 79 A. 832 (1911). However, where an expert witness testifies as to the necessity for the repairs and the reasonableness of their cost, such evidence has been held to be admissible. Krasnoff v. Flynn, supra. In that case, the expert witness, in the course of his testimony "identified a repair bill on which were *312 itemized in detail the repairs to plaintiff’s car and the cost of each item,” and this court held that under the circumstances the bill was admissible. Id. at 131, 196 A.2d at 159-60 (emphasis added).

In the instant case, there was no dispute over the existence of the defects and the necessity of the repairs. The disagreement was over the cost of correcting the defects. The estimate at issue consisted of a listing of defects and a total figure of $3,889.88 as the cost of correction, with no itemization of the cost of repairing each defect. Furthermore, a review of the record discloses that plaintiffs’ expert was unable to itemize the costs; that is, he could not specify the cost of repairing some of the listed defects, nor could he state which portion of the total estimate was attributable to labor and which to materials except by guessing. 1 As a result, there is a discrepancy of almost $3,000 between DiDonato’s written estimate of $3,889.88 and his oral testimony as to the cost of repairing particular defects which totaled approximately $900. 2

In essence, DiDonato’s estimate constituted an expert’s opinion as to the total cost of correcting the defects. The issue before us is whether this opinion, unsupported by testimony as to the facts on which it was based, was competent evidence of damages, and, thus, whether it was admissible.

Unquestionably, an expert’s opinion must be predicated upon facts legally sufficient to form a basis for his conclusion. Nasco, Inc. v. Director of Pub. Works, 116 R.I. 712, 360 A.2d 871 (1976);

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Johnston Equities Associates, LP v. Town of Johnston
Supreme Court of Rhode Island, 2022
Louis Paolino v. Joseph Ferreira
153 A.3d 505 (Supreme Court of Rhode Island, 2017)
Devaney v. Kilmartin
88 F. Supp. 3d 34 (D. Rhode Island, 2015)
State v. Gaspar
982 A.2d 140 (Supreme Court of Rhode Island, 2009)
M.G.C. Remodeling v. Rhode Island Contr.
Superior Court of Rhode Island, 2009
Berganza v. Rhode Island Economic Dev., Pc
Superior Court of Rhode Island, 2009
Nunes v. Meadowbrook Development Co.
Superior Court of Rhode Island, 2008
Daley v. Falaye
Superior Court of Rhode Island, 2007
Walker v. Degnan (In re Degnan)
361 B.R. 650 (D. Rhode Island, 2007)
Dodson v. Ford Motor Company, 96-1331 (2006)
Superior Court of Rhode Island, 2006
Riley v. Stone
900 A.2d 1087 (Supreme Court of Rhode Island, 2006)
Petrarca v. Fidelity & Casualty Insurance
884 A.2d 406 (Supreme Court of Rhode Island, 2005)
State v. Hanes
783 A.2d 920 (Supreme Court of Rhode Island, 2001)
Raimbeault v. Takeuchi Manufacturing (U.S.), Ltd.
772 A.2d 1056 (Supreme Court of Rhode Island, 2001)
Insurance Co. of North America v. Kayser-Roth Corp.
770 A.2d 403 (Supreme Court of Rhode Island, 2001)
Doe v. Gelineau
732 A.2d 43 (Supreme Court of Rhode Island, 1999)
State v. Bettencourt
723 A.2d 1101 (Supreme Court of Rhode Island, 1999)
Gallucci v. Humbryd
709 A.2d 1059 (Supreme Court of Rhode Island, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
377 A.2d 237, 119 R.I. 307, 1977 R.I. LEXIS 1908, Counsel Stack Legal Research, https://law.counselstack.com/opinion/alterio-v-biltmore-construction-corp-ri-1977.