Iannuccillo v. Material Sand & Stone Corp.

713 A.2d 1234, 1998 R.I. LEXIS 168, 1998 WL 285513
CourtSupreme Court of Rhode Island
DecidedMay 15, 1998
Docket93-453-Appeal
StatusPublished
Cited by8 cases

This text of 713 A.2d 1234 (Iannuccillo v. Material Sand & Stone Corp.) is published on Counsel Stack Legal Research, covering Supreme Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Iannuccillo v. Material Sand & Stone Corp., 713 A.2d 1234, 1998 R.I. LEXIS 168, 1998 WL 285513 (R.I. 1998).

Opinion

OPINION

WEISBERGER, Chief Justice.

This case comes before us on cross-appeals from a judgment entered in Superior Court following a jury waived trial. The plaintiff, Louis A. Iannuccillo (Iannuccillo), sued, claiming money damages for the defendants’ alleged breach of contract and negligence arising out of excavation work the defendants performed on property owned by the plaintiff at the corner of Waterman Avenue and Donovan Court (the property or site) in the town of North Providence, Rhode Island. The defendants filed a counterclaim, alleging that Iannuccillo had breached the contract by failing to pay for certain blasting expenses. The facts and travel of the case insofar as are pertinent to our determination of the instant appeals are as follows.

In 1985 plaintiff entered into a written contract with defendant Material Sand and Stone Corporation (Material), whereby Material was to excavate the 127,000-square-foot lot from its then-existing sloped state to “grade from eurbline elevation to an elevation 2 feet higher at the rear of the property.” Leonard Pezza (Leonard), defendant C. Pezza & Son, Inc.’s (Pezza) principal, had a working relationship with plaintiff. Pezza was an excavation and on-site-preparation contractor. The defendant Robert Pezza is the son of Leonard and president of Material, an earth-processing company.

In 1985 Leonard and Iannuccillo met at the property to discuss the proposed excavation job. The essential terms of their agreement were thereafter reduced to a written agreement dated July 22, 1985. Although the written contract was entered into between Material (Robert Pezza’s signature appears on the writing) and Iannuccillo, the parties agreed, as the trial justice recognized, that Pezza would actually perform the excavation. The parties estimated that said excavation would entail the removal of approximately fifty to sixty-thousand cubic *1236 yards of gravel and “existing rock now exposed.” Under the terms of the contract Pezza was to deliver ten thousand cubic yards to another site owned by Iannuccillo (the 246A site), with the remainder of the excavated stone delivered to Material, which would process it and sell it. Testimony at trial established that at that time the fair market value for gravel was $1 per cubic yard. Iannuccillo’s expectation under the contract was that he would end up with a lot which would be suitable to build and defendant would benefit from the proceeds realized from the processing and sale of the gravel — expected to' amount to approximately forty to fifty-thousand cubic yards. The parties agreed that “[t]he cost of blasting [would] be shared by, Material Sand and Stone Corporation and Louis Iannuccillo at a price of $5,000 each”; this was to have been the only money to change hands under the terms of the written contract.

Located at the rear of the subject property, which prior to the excavation stood approximately 40 feet higher than curb elevation on Waterman Avenue, was a residential housing development. At the time the contract was entered into, plaintiff had no engineering plans for the excavation, but he testified that he intended to leave a “20-foot buffer” along the boundary bordering the residential development (eastern boundary). Leonard testified that Iannuccillo never instructed him specifically about a buffer. He testified that he intended to slope the resulting embankment to provide an appropriate buffer between the residential development and plaintiff’s excavated building site.

During the spring of 1986 residents along the eastern boundary complained to offiqials of the town, who in turn intervened, claiming that the excavation of Iannuceillo’s property was illegal. North Providence officials were concerned .with plaintiff’s plans, or lack thereof, in regard to the condition in which the embankment at the eastern boundary would be left after the excavation was completed. On May 9, 1986, the planning director for the town of North Providence sent plaintiff a letter, stating that he was in violation of a zoning ordinance for removing gravel from the site without the approval of the zoning board. Pezza was allowed to continue the excavation in reliance on plaintiff’s promise to provide the town with an appropriate plan documenting plaintiff’s intended result. When plaintiff failed to deliver a plan to the town, the planning director shut the project down on or about June 3, 1986. The town also installed a 500-foot fence along the eastern boundary of the property, the slope of which apparently was growing ever more precipitous with the removal of each shovel full of earth. The town billed Iannuccillo $6,920 for the cost of the fence.

While plaintiff and town officials were embroiled over plaintiffs lack of preparation for the excavation, further troubles were beginning to surface between Pezza and Iannuccil-lo. Pezza had brought in a blasting contractor to break up some of the larger exposed boulders as contemplated in the parties’ agreement. Upon completion of this blasting, approximately 10,000 cubic yards of ledge were discovered. The ledge was located in both the flat area of the site and the embankment or slope area. Iannuccillo instructed Pezza to work around .the newly exposed ledge but failed to forward his half of the accrued blasting costs to Pezza. Ian-nuccillo then shifted his position in respect to the ledge, asserting that defendant was obligated to remove the ledge as part of their contract. The defendant, of course, maintained that ledge removal was not part of the bargain, but plaintiff refused to negotiate any further.

With the job indefinitely on hold, Iannuc-cillo hired an engineering firm, R.F. Geisser & Assoc. Inc. (Geisser), to develop a final plan that would be satisfactory to the town. Geisser determined that the embankment along the eastern boundary was unstable and formulated a plan for remedial work to shore up the embankment. The plan for remedial work was completed and forwarded to Ian-nuccillo on or about October 29,1986.

In January 1989 plaintiff sued Pezza, Material, and Robert Pezza, claiming that defendants had breached the contract and negligently performed the excavation, which undermined the lateral support to the adjacent residential property, requiring the erection of the 500-foot fence and the reme *1237 dial engineering work pursuant to the Geis-ser plan. The defendants counterclaimed, seeking damages for Iannuccillo’s failure to pay his half of the blasting costs incurred by Pezza as agreed in the written contract.

The property lay untouched from June 1986 until 1993 when, while the instant suit was pending, Iannuccillo hired R. DiCenzo Trucking (DiCenzo) to blast the ledge, excavate it, and complete the site development by resloping the eastern boundary according to the Geisser plan. DiCenzo charged plaintiff a total of $80,000 of which DiCenzo paid $32,000 directly to a third-party blasting contractor. DiCenzo testified that 60 percent of the work he performed was the hauling away of the blasted ledge material and that after the ledge had been cleared, it was necessary for him to reslope approximately 60 percent of the embankment.

The case was tried without a jury in May 1996. 1 In rendering his decision from the bench, the trial justice found that the ledge was not contemplated when the parties originally bargained and that, therefore, defendants could not be held liable for its removal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tri-Town Construction Company, Inc. v. Commerce Park Associates 12, LLC
139 A.3d 467 (Supreme Court of Rhode Island, 2016)
Labelle v. Malry, Pc 04-4077 (r.I.super. 8-9-2007)
Superior Court of Rhode Island, 2007
Lopez v. Personnel Appeal Bd., 99-4151 (2002)
Superior Court of Rhode Island, 2002
ADP Marshall, Inc. v. Brown University
784 A.2d 309 (Supreme Court of Rhode Island, 2001)
Bradford Dyeing Assoc. v. J. Stog Tech GmbH
765 A.2d 1226 (Supreme Court of Rhode Island, 2001)
Women's Development Corp. v. City of Central Falls
764 A.2d 151 (Supreme Court of Rhode Island, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
713 A.2d 1234, 1998 R.I. LEXIS 168, 1998 WL 285513, Counsel Stack Legal Research, https://law.counselstack.com/opinion/iannuccillo-v-material-sand-stone-corp-ri-1998.