National Chain Co. v. Campbell

487 A.2d 132, 1985 R.I. LEXIS 435
CourtSupreme Court of Rhode Island
DecidedJanuary 30, 1985
Docket82-393-Appeal
StatusPublished
Cited by47 cases

This text of 487 A.2d 132 (National Chain Co. v. Campbell) is published on Counsel Stack Legal Research, covering Supreme Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Chain Co. v. Campbell, 487 A.2d 132, 1985 R.I. LEXIS 435 (R.I. 1985).

Opinion

OPINION

SHEA, Justice.

This is an appeal from judgments entered after a jury trial in Superior Court. The judgments awarded nominal damages of $1 to plaintiff, National Chain Company (National), and the sum of $400 on his counterclaim to the defendant, John J. Campbell (Campbell). National had sought to recover damages based on breach of contract and negligence, alleging that Campbell failed to perform in a workmanlike manner. Campbell had counterclaimed for the cost of services rendered. We reverse and remand for retrial on all issues.

National is a jewelry manufacturer with offices located in Warwick, Rhode Island. Campbell was hired to wallpaper the offices of National’s president with wallcov-ering that had been previously purchased by National. The terms of the agreement were that Campbell would be paid on a time-spent basis. Upon completion of the job, the evidence shows that the wallpaper had ragged edges, that there were gaps at the seams, that it was curled up at the edges, and that it had glue stains, contact cement, and staples on it. National refused to pay Campbell and brought suit for recovery of the amount it had paid for the wallpaper and for the costs incurred in removing it and repairing the wall surface damaged by Campbell. National’s complaint contained a second count based on negligence.

National’s expert, Kenneth Normandin, an experienced wallpaper hanger, testified at trial about the quality of Campbell’s work. It was his opinion that the gaps at the seams were caused by Campbell’s failure to permit the material to dry and shrink to its normal shape before the seams were cut. In his words, “[I]t was just [a] terrible looking job.” Normandin submitted an estimate for removing the wallpaper and preparing the walls for new wallpaper in the amount of $756, of which $300 was for stripping and preparing the walls. The balance was for installing new wallcovering for which National makes no claim.

National’s first claim of error arises out of the trial justice’s charge to the jurors that if they found for plaintiff, they could only award nominal damages in the amount of $1 because National had not produced any probative evidence of the original contract price. In his charge, he told the jury:

“There is no evidence in this case of what the cost would have been had Mr. Campbell properly completed his contract to paper the offices involved which National Chain contends he breached * * *.
“National Chain failed to prove the reasonable cost of properly performing that portion of the contract which National Chain says Mr. Campbell breached; and so, you cannot apply the formula for damages which the law places, and that is the cost of correction and completion less the cost of the plaintiff performing the job properly without your guessing or speculating * * *.
“I am instructing you that they failed in that duty to prove damages, and that you will not be allowed to bring back, even if you find a contract existed between National Chain and John J. Campbell, and even if you find that Mr. Campbell breached that contract by failing to perform it in a workmanlike fashion, you will — if that be your finding, then I instruct you to bring back a verdict in the amount of One Dollar in nominal damages for National Chain because National Chain failed in its burden of proof on damages.”

The amount of damages sustained from a breach of contract must be proven with a reasonable degree of certainty, and the plaintiff must establish reasonably precise figures and cannot rely upon specula-

*135 tion. Restatement, Contracts § 331(1) (1932). The burden of proof therefore is on plaintiff to prove, by competent evidence, the amount of damages that it suffered because of defendant’s failure to perform. Smith v. Zepp, 173 Mont. 358, 370, 567 P.2d 923, 930 (1977). However, “[plaintiffs will not be denied recovery merely because the damages * * * are difficult to ascertain, as long as they prove damages with reasonable certainty.” Id.

It is apparent from the instruction given that the trial justice failed to consider the testimony and evidence of National’s expert concerning what the cost of repairing the walls would be apart from the expenses involved in hanging new wall-covering. In addition, he gave no consideration to National’s evidence of the cost of the damaged wallpaper initially purchased by National in the amount of $1,981.14. 1 Furthermore, since National was seeking only the cost of the ruined wallcovering and the cost of repairing the damaged wall surface, this instruction was inappropriate. Since the instruction given has no relation to National’s claim for damages, it was error and will require a new trial.

The underlying rationale in breach-of-contract actions is to place the innocent party in the position in which he would have been if the contract had been fully performed. George v. George F. Berkander, Inc., 92 R.I. 426, 430, 169 A.2d 370, 372 (1961). A major consideration in determining the proper measure of damages is whether the contractor has substantially performed so that the purpose of the contract is accomplished. Plante v. Jacobs, 10 Wis.2d 567, 570, 103 N.W.2d 296, 298 (1960). This general principle gives rise to National’s second claim of error. The trial justice refused to instruct the jury that Campbell could not recover on his counterclaim unless he had substantially performed the contract in a workmanlike manner. The trial justice ruled that although the contractor could not recover on the contract, he could recover in quantum me-ruit or quasi-contract.

It is well settled that when a builder has substantially performed, he can recover the contract price less the amount needed by the owner to remedy the defect. Ferris v. Mann, 99 R.I. 630, 636, 210 A.2d 121, 124 (1965). The doctrine of substantial performance recognizes that it would be unreasonable to condition recovery upon strict performance where minor defects or omissions could be remedied by repair. This formula is inappropriate, however, in situations in which the contractor’s performance is worthless and the work has to be redone completely. In these situations, the contractor is liable for the cost to the owner of having the job redone. Scheppegrell v. Barth, 239 La. 42, 117 So.2d 903 (1960); Rosier v. Escue, 48 So.2d 687 (La.Ct.App.1950); 13 Am.Jur.2d Building and Construction Contracts § 78 (1964); Annot., 76 A.L.R.2d 827 (1961). To recover on an action in quantum meruit, it must be shown that the owner derived some benefit from the services and would be unjustly enriched without making compensation therefor. Montes v. Naismith and Trevino Construction Co., 459 S.W.2d 691, 694 (Tex.Civ.App.1970).

We adhere to the rule enunciated in DiMario v. Heeks, 116 R.I.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brown v. Newrez, LLC
D. Rhode Island, 2021
South County Post & Beam, Inc. v. Brian T. McMahon
116 A.3d 204 (Supreme Court of Rhode Island, 2015)
Process Engineers & Constructors, Inc. v. DiGregorio, Inc.
93 A.3d 1047 (Supreme Court of Rhode Island, 2014)
T.G. Plastics Trading Co. v. Toray Plastics Inc.
958 F. Supp. 2d 315 (D. Rhode Island, 2013)
Sophie F. Bronowiski Mulligan Irrevocable Trust v. Bridges
44 A.3d 116 (Supreme Court of Rhode Island, 2012)
Washburn v. Trombino's Folly
Superior Court of Rhode Island, 2011
ADP Marshall, Inc. v. NORESCO, LLC
710 F. Supp. 2d 197 (D. Rhode Island, 2010)
Kempen v. Town of Middletown
Superior Court of Rhode Island, 2010
M.G.C. Remodeling v. Rhode Island Contr.
Superior Court of Rhode Island, 2009
Robinson Design Inc. v. Connors
Superior Court of Rhode Island, 2009
Cavanaugh v. Contractors' Registration Board
Superior Court of Rhode Island, 2008
Nunes v. Meadowbrook Development Co.
Superior Court of Rhode Island, 2008
Labelle v. Malry, Pc 04-4077 (r.I.super. 8-9-2007)
Superior Court of Rhode Island, 2007
Walker v. Degnan (In re Degnan)
361 B.R. 650 (D. Rhode Island, 2007)
Independent Financial, Services, Inc. v. CCI Group, Inc.
459 F. Supp. 2d 138 (D. Rhode Island, 2006)
ROSADO-SOSTRE v. Turabo Testing, Inc.
364 F. Supp. 2d 144 (D. Puerto Rico, 2005)
Finnegan v. Verdone, 2003-1251 (2004)
Superior Court of Rhode Island, 2004
Desimone Electric Inc. v. Cmg, Inc., 01-6077 (2004)
Superior Court of Rhode Island, 2004

Cite This Page — Counsel Stack

Bluebook (online)
487 A.2d 132, 1985 R.I. LEXIS 435, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-chain-co-v-campbell-ri-1985.