Process Engineers & Constructors, Inc. v. DiGregorio, Inc.

93 A.3d 1047, 2014 WL 2957407, 2014 R.I. LEXIS 111
CourtSupreme Court of Rhode Island
DecidedJuly 1, 2014
Docket2013-87-Appeal
StatusPublished
Cited by11 cases

This text of 93 A.3d 1047 (Process Engineers & Constructors, Inc. v. DiGregorio, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Process Engineers & Constructors, Inc. v. DiGregorio, Inc., 93 A.3d 1047, 2014 WL 2957407, 2014 R.I. LEXIS 111 (R.I. 2014).

Opinion

OPINION

Justice GOLDBERG, for the Court.

This case came before the Supreme Court on February 6, 2014, pursuant to an order directing the parties to appear and show cause why the issues raised in this appeal should not summarily be decided. The defendant, DiGregorio, Inc. (defendant or DiGregorio), appeals from a Superior Court judgment in favor of the plaintiff, Process Engineers & Constructors, Inc. (plaintiff or Process), granting the plaintiff’s claim for quantum meruit. After considering the written and oral arguments advanced by counsel, we are satisfied that cause has not been shown and that this appeal may be decided at this time. For the reasons set forth below, we affirm the judgment of the Superior Court.

Facts and Travel

A series of contracts and subcontracts set the stage for this dispute. On November 28, 2005, Brown University (Brown) contracted with Bond Brothers, Inc. (Bond Brothers) for the replacement of high-temperature, high-pressure water pipes, designed to provide heat and hot water to buildings on the Brown campus. Brown preselected a ready-made, pre-insulated piping system manufactured by Perma Pipe, Inc. (Perma Pipe). On April 24, 2006, Bond Brothers entered into a subcontract with DiGregorio, whereby DiGre-gorio agreed to furnish labor, materials, equipment, and services for the project. On the same day, DiGregorio entered into a sub-subcontract with Process, in which Process agreed to install the pipe. The sub-subcontract required that change orders must be in writing and signed by the owner, contractor, and architect.

Process installed the pipe. In the fall of 2006, however, the parties discovered that the insulation surrounding the interior of the pipe had become wet. 1 Process then replaced the damaged pipe and finished the work necessary to complete its portion of the project. In February 2008, Process filed this action against DiGregorio, alleging that DiGregorio failed to pay for some *1050 of the work that Process performed on the project. Process asserted breach of contract and quantum meruit claims against DiGregorio. 2

On April 30, 2012, trial commenced before a justice of the Superior Court sitting without a jury. Three witnesses testified on that day. Robert Silvia (Silvia), the owner and president of Process, testified that Process was a subcontractor to Di-Gregorio on the project and that Process was to install “prefabricated conduit piping systems.” Silvia testified that there was a provision in the sub-subcontract regarding additional work or changes to the contract. Although Process never received any formal change orders, Silvia testified that Process was asked to and did perform work without a formal change order. Silvia discussed a number of invoices, which included change orders and relevant settlements and releases of holdback funds; ultimately, he testified that Process was still owed $316,000. On cross-examination, Silvia acknowledged that he had no proof that the change orders noted in the invoices actually were approved. Additionally, when asked what Process was not paid for, Silvia responded, “I have no idea because we’d get checks and joint checks that weren’t even made out to us. There was never any documentation to show what was paid and what wasn’t paid.” According to Silvia, three invoices from Process were termed “back charges” — the invoice for an additional performance bond premium, an invoice for the disposal of pipe fabrication that had been removed from Hope Street, and an invoice for the replacement of pipe sections that were reinstalled at Meehan Loop.

The plaintiff called Enrico DiGregorio, the president of DiGregorio, who testified as an adverse witness. He testified that DiGregorio withheld $148,694.51 from Process because it believed that Process was at fault for the water damage to the pipe. The witness, however, did admit that Process performed all of the work under the contract and that, at some point, the billing should have caught up and Process should have been paid.

Charles Barbanti (Barbanti), who was employed by Bond Brothers and was the project manager, testified during defendant’s case. Barbanti testified that Bond Brothers made the final determination of who would be paid and that Process was paid for its work on the project, including “legitimate change orders.” Regarding the wet pipe insulation, according to Bar-banti, in addition to receiving it, welding it, and installing it, Process also was required to protect it and test it. Barbanti testified that, in his opinion, Process could have provided better protection to the pipe. Specifically, he stated that Process was “using like Saran wrap, which is like something you’d wrap a sandwich with,” and instead, he “felt they should be using six or eight mil poly” — a heavier grade plastic. According to Barbanti, Process should have duct-taped the end of the pipe when Process received it. On cross-examination, Barbanti admitted that the manufacturer shipped the pipes in the “Saran wrap” material and that the “six or eight mil poly” may have exceeded the manufacturer’s specifications. Barbanti also admitted that Process was not responsible for dewatering the trench, and that Process was entitled to rely on someone else to keep the trenches dry. He also stated *1051 that dewatering was included in DiGrego-rio’s scope of work.

The trial justice issued a written decision on July 13, 2012. 3 Addressing the breach of contract claim first, the trial justice found that the provision of the sub-subcontract between Process and DiGrego-rio relating to the requirement of written and signed change orders was clear and unambiguous. The trial justice concluded that Process had “failed to satisfy its burden to show that the conditions precedent [with respect to the change orders] have occurred and thus the [defendant has not breached its subcontract by nonperformance.” 4

The trial justice next addressed plaintiffs quantum meruit claim as applied to three items: the change orders, the additional bond premium, and the pipe replacement necessitated by wet insulation. Regarding the change orders and noting the inconsistency of Silvia’s testimony, the trial justice found that plaintiff had failed to meet its burden of showing that plaintiff conferred a benefit on defendant and that defendant accepted the benefit. Next, the trial justice found that “[plaintiff could recover the additional bond premium in the amount of $12,929.40, required by the [b]ond company, based on an increase of the initial subcontract amount and not originally covered under the subcontract.” Finally, regarding the wet pipe, the trial justice was “satisfied that Process has satisfied its burden to show that its loss was due to something [other] than its own actions,” because it was not Process’s responsibility to dewater the trenches. Accordingly, the court concluded that Process “was able to show that the additional costs in replacing the damaged pipe were not attributed to [plaintiffs own inefficiencies or job preparation.”

The trial justice granted recovery as to two invoices in his written decision: the increase on the bond premium ($12,929.40) and the replacement of the damaged wet pipe ($72,857.96).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. E.R.R.
35 F.4th 405 (Fifth Circuit, 2022)
City of Woonsocket v. RISE Prep Mayoral Academy
Supreme Court of Rhode Island, 2021
In re Gen. Motors LLC
339 F. Supp. 3d 262 (S.D. Illinois, 2018)
Lauren Daley Ainsworth v. John Ainsworth
186 A.3d 1074 (Supreme Court of Rhode Island, 2018)
Mathew M. Cote v. John Aiello
148 A.3d 537 (Supreme Court of Rhode Island, 2016)
South County Post & Beam, Inc. v. Brian T. McMahon
116 A.3d 204 (Supreme Court of Rhode Island, 2015)
Timothy Raiche d/b/a T. Raiche Builders v. Timothy W. Scott
101 A.3d 1244 (Supreme Court of Rhode Island, 2014)
In re Estate of Ann Marie Picillo
99 A.3d 975 (Supreme Court of Rhode Island, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
93 A.3d 1047, 2014 WL 2957407, 2014 R.I. LEXIS 111, Counsel Stack Legal Research, https://law.counselstack.com/opinion/process-engineers-constructors-inc-v-digregorio-inc-ri-2014.