Edward R. Marden Corp. v. S. & R. CONSTRUCTION CO., INC.

309 A.2d 675, 112 R.I. 332, 1973 R.I. LEXIS 988
CourtSupreme Court of Rhode Island
DecidedOctober 2, 1973
Docket1847-Appeal
StatusPublished
Cited by7 cases

This text of 309 A.2d 675 (Edward R. Marden Corp. v. S. & R. CONSTRUCTION CO., INC.) is published on Counsel Stack Legal Research, covering Supreme Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Edward R. Marden Corp. v. S. & R. CONSTRUCTION CO., INC., 309 A.2d 675, 112 R.I. 332, 1973 R.I. LEXIS 988 (R.I. 1973).

Opinion

*333 Doris, J.

This is a- civil action wherein the plaintiff seeks damages for the breach of a building contract by the defendant. The defendant in its answer filed a claim for damages against the plaintiff.

Trial was held to a Superior Court justice sitting without a jury. Decision was rendered for plaintiff in the amount of $30,626.21. Judgment was thereafter entered for plaintiff in the amount of $30,626.21, plus interest of $9,409.36, plus costs of $41.45, for a total of $40,077.02. It is from that judgment that defendant has appealed to this court.

The plaintiff, Edward R. Marden Corp., hereinafter sometimes refererred to as “Marden,” entered into a contract with the United States Navy on or about March 9, 1965, for the construction of a mess hall and dormitory at the naval base at Newport, Rhode Island. In furtherance of said contract Marden, on or about April 7, 1965, entered into a subcontract with defendant, S. & R. Construe *334 tion Co., Inc., hereinafter sometimes referred to as “S. & R.,” for the building and site-earthwork at a contract price of $49,000. S. & R. commenced work as agreed and had completed a substantial part of the work required under the contract at the time of the alleged breach. According to the testimony, difficulties arose between Marden and S. & R., and between S. & R. and the Navy. The disputes involved the type of stone required by the Navy for back-fill, the method of backfilling required by the Navy, the number of workers employed by S. & R., and the length of time S. & R. used in doing its work. The defendant complained that Marden failed to make work available and that other subcontractors of Marden were interfering with and delaying the equipment and employees of defendant. Most of this testimony is in dispute.

It is undisputed, however, that on September 24, 1965, S. & R. left the job and did not return. As a result of the withdrawal from the job by defendant, Marden sent to S. & R. a letter of termination. Included in the notice of termination was a statement that S. & R. would be held liable by Marden for any amounts above the contract price required to complete the work which S. & R. had not completed. At that time, plaintiff had paid defendant under the terms of the contract $33,892.30 and had billed defendant $4,019.94 for work performed by it for defendant. Thereafter, Marden rented equipment, purchased supplies,, and, using its own employees, completed the work remaining to be done under the subcontract with S. & R.

I

The defendant first contends that the judgment is against the law and against the evidence and the weight thereof.

The defendant argues that it was justified in leaving the job prior to completion and that if such withdrawal was justified there was no breach by defendant. The contention by defendant is in accordance with the rule that to one *335 who is sued for nonperformance of his promise, it is a defense if he can prove that his performance was prevented or substantially hindered by the plaintiff. 4 Corbin Contracts §947 at 813 (1951).

The defendant contends that it was justified in leaving the job and argues that testimony and evidence were sufficient to show that defendant was ready and able to perform, but plaintiff at the time did not have work available for defendant. The defendant also contends that plaintiff allowed equipment and material from other subcontractors to be strewn about the work area, thereby blocking the employees and the equipment of defendant. The defendant testified that it had been delayed in its performance of the work under the contract by bad and inclement weather, and argued that delay was therefore excusable.

The testimony as to these contentions by defendant is in conflict. The trial justice in his decision commented on the testimony of witnesses Karl Muse and George Millman that there was plenty of work available for defendant, and on testimony of defendant’s witness, Joseph Pennacchia, that lack of work existed for only a few days. He also commented on the testimony that defendant was dissatisfied with the type of stone required by the Navy for back-filling and also with the type of compacting demanded by the Navy inspector. He consequently found specifically that there was plenty of work available for defendant. The trial justice further found that the bad weather was something that was foreseeable and should have been anticipated by defendant when it submitted its bid, and therefore was not an excuse for nonperformance. 13 Am. Jur.2d Building & Construction Contracts §54 (1964). Based on these findings the trial justice concluded that abandonment by defendant was not as a result of delay or interference on the part of plaintiff.

*336 The defendant contends that in making such findings the trial justice misconceived the evidence. A reading of the transcript persuades us that there was sufficient evidence on which the trial justice could base these findings and that he had neither misconceived nor overlooked any material evidence and was therefore not clearly wrong.

Where the findings of a trial justice are supported by the evidence, the rule is that they will not be disturbed unless shown to be clearly wrong or unless the trial justice has overlooked or misconceived material evidence. Pucci v. Algiere, 106 R. I. 411, 261 A.2d 1 (1970); Mateer v. Mateer, 105 R. I. 735, 254 A.2d 417 (1969). The rule is well settled that on review this court neither weighs the evidence nor passes on the credibility of witnesses, but sustains the findings of the trial justice if it finds on the record competent evidence which if accepted as truthful will support those findings, and that the burden is on the appellant to show that the trial justice was clearly wrong in his decision in that he overlooked or misconceived relevant and material evidence. Pucci v. Algiere, supra. The defendant has failed to persuade us that the trial justice was clearly wrong in that he either overlooked or misconceived the evidence or misapplied the law. We will not, consequently, disturb the findings of the trial justice that defendant abandoned the project, that plaintiff was not responsible for said abandonment and that consequently defendant had breached his contract with plaintiff.

The defendant next argues that the trial justice erred in assessing the damages as a result of the breach of contract by defendant. The defendant in its brief agrees that the rule for assessing damages is that where there has been a failure to complete performance of a contract according to its terms, the measure of damages ordinarily is the reasonable cost of completing the work. 13 Am. Jur.2d Building & Construction Contracts §78 at 77 (1964); 25 *337 C.J.S. Damages §75 at 855 (1966).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Conti v. Geffroy
486 A.2d 579 (Supreme Court of Rhode Island, 1985)
Pawtucket Institution for Savings v. Gagnon
475 A.2d 1028 (Supreme Court of Rhode Island, 1984)
MBT Construction Corp. v. Kelhen Corp.
432 A.2d 670 (Supreme Court of Rhode Island, 1981)
Picerne v. DiPrete
428 A.2d 1074 (Supreme Court of Rhode Island, 1981)
LaPorte v. Ramac Associates, Inc.
395 A.2d 719 (Supreme Court of Rhode Island, 1978)
Sladen v. Rowse
347 A.2d 409 (Supreme Court of Rhode Island, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
309 A.2d 675, 112 R.I. 332, 1973 R.I. LEXIS 988, Counsel Stack Legal Research, https://law.counselstack.com/opinion/edward-r-marden-corp-v-s-r-construction-co-inc-ri-1973.