Eric Soby, D/B/A Soby Painting Co., and United States Fidelity and Guaranty Company v. Lloyd W. Johnson and Max J. Kuney, D/B/A Kuney Johnson Company

270 F.2d 193, 1959 U.S. App. LEXIS 5267
CourtCourt of Appeals for the Ninth Circuit
DecidedSeptember 8, 1959
Docket15823
StatusPublished
Cited by8 cases

This text of 270 F.2d 193 (Eric Soby, D/B/A Soby Painting Co., and United States Fidelity and Guaranty Company v. Lloyd W. Johnson and Max J. Kuney, D/B/A Kuney Johnson Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eric Soby, D/B/A Soby Painting Co., and United States Fidelity and Guaranty Company v. Lloyd W. Johnson and Max J. Kuney, D/B/A Kuney Johnson Company, 270 F.2d 193, 1959 U.S. App. LEXIS 5267 (9th Cir. 1959).

Opinion

HAMLIN, Circuit Judge.

In October and November, 1952, ap-pellees entered into construction contracts with the United States whereby appellees contracted to build certain buildings for the United States military. The contracts were for buildings at two locations, one at Ladd Air Force Base and the other at Eielson Air Force Base, both in Alaska. Appellees, as prime contractors, subcontracted with appellant Soby whereby Soby undertook to do the painting and other work incidental to painting on both projects. Appellant United States Fidelity and Guaranty Company (herein called Surety) was surety for Soby under both contracts.

Soby brought an action against appel-lees in the Third Division of the District Court for the Territory of Alaska under the so-called Miller Act, 40 U.S.C.A. § 270a et seq., seeking recovery for his work on the projects upon a theory of quantum meruit. He alleged appellees had used faulty material on the Ladd project, which made his work more difficult and costly and obliged him to repaint units already completed, whereby he was damaged. Appellees cross-complained, seeking damages for alleged breaches of contract by Soby on both the Ladd and Eielson projects.

Appellant Soby’s action was dismissed, and judgment was granted appellees on both their cross-complaints. Except for an incidental matter, appellants appeal only with respect to the cross-complaint respecting the Eielson project, for which appellees received judgment of $53,955.43.

The facts giving rise to the dispute are these. Soby commenced performance under his two subcontracts in the spring *195 of 1953, but for reasons not relevant here, abandoned work on both jobs at the direction of Surety on December 19, 1953. Four days later a representative of Surety wrote a letter to appellees in which he said:

“ * * * this leaves you free and without prejudice to complete the contracts and to tender to us the claim of the cost of the completion over and above the contract prices involved.”

Accordingly, with the express approval of Surety, Larsen (or Larson) Brothers Painting Company was engaged to complete the painting under the subcontracts. Under this arrangement, Larsen was to be compensated for actual costs, plus 10% of the labor only. The percentage was not computed on the cost of materials, and no overhead or profit (other than 10% on labor) was charged.

In connection with the Eielson painting subcontract, appellees spent or incurred obligations totalling $132,292.33, and earned $78,336.90. Appellees were awarded the difference, $53,995.43, which sum the trial court found reasonable. Appellants claim this award was excessive.

Other than intimations of “outrageous padding, feather-bedding and profiteering,” and of “collusion of the general contractor and his hand-picked substitute subcontractor,” for which we find no support in the record, appellants’ claim of error is based solely on a “percentage of completion estimate” filed by appellees with the Contracting Officer for the United States. This estimate was made after Soby’s termination but before Larsen commenced work, and was filed for the purpose of securing payment, prior to completion, for work performed. Ap-pellees were paid on the basis of the estimate, which showed the project 97.85% complete. A progress estimate discloses the “Interior Finish” (which included painting) was 91.18% complete. The gist of appellants’ argument is that an award of almost $54,000 to complete 8.82% of a $78,000 job is excessive and unwarranted. Though the point has a surface plausibility, we think the trial court’s finding of reasonableness of the award, far from being “clearly erroneous,” is supported by substantial and convincing evidence.

First, one of the appellees testified without contradiction that it is understood in the business that percentage of completion estimates, though they may serve as a general guide, do not necessarily fairly reflect what portion of the work has actually been done, and in fact, less than 97.85% of the work had been completed at the time the estimate was prepared.

Secondly, the “Interior Finish” item, which was listed as 91.18% complete, included considerable work other than painting. The prime contract allotted $346,402.46 to Interior Finish, and the painting subcontract, included therein, accounted for only $78,336.90. Even if we assume that 91.18% of the $346,402.-46 Interior Finish work was complete, there remained over $30,000 of Interior Finish work to be completed, and, as appellants concede, the remainder of the work was “substantially all painting.” This figure bears a close relation to that portion of appellees’ total judgment attributable to the Larsen payroll, which, including taxes and 10% fee, was $33,-251.06. This sum was amply supported by payroll records, invoices, government inspectors’ reports and other evidence. In addition, weekly invoices were sent to both appellants as expenditures were made, and the record indicates appellants had other knowledge of the progress of the work. Officials of both Larsen and appellees testified all expenditures were reasonable and the trial court so found.

In United States v. Behan, 1884, 110 U.S. 338, 4 S.Ct. 81, 83, 28 L.Ed. 168, the Supreme Court said:

“Unless there is some artificial rule of law which has taken the place of natural justice in relation to the measure of damages, it would seem to be quite clear that the claimant ought at least to be made whole for his losses and expenditures. So far as appears, they were incurred *196 in the fair endeavor to perform the contract which he assumed. If they were foolishly or unreasonably incurred, the [appellant], should have proven this fact. It will not be presumed. * * *
“The prima facie measure of damages for the breach of a contract is the amount of the loss which the injured party has sustained thereby. * * * It does not lie, however, in the mouth of the party, who has voluntarily and wrongfully put an end to the contract, to say that the party injured has not been damaged at least to the amount of what he has been induced fairly and in good faith to lay out and expend, (including his own services) after making allowance for the value of materials on hand; at least it does not lie in the mouth of the party in fault to say this, unless he can show that the expenses of the party injured have been extravagant, and unnecessary for the purpose of carrying out the contract.”

Appellants rely solely on the percentage of completion estimate and the prog-ess estimate. They offered no evidence to rebut the documented proofs of expenditure submitted by appellees. American Can Co. v. Garnett, 9 Cir., 1922, 279 F. 722; Elias v. Wright, 2 Cir., 1921, 276 F. 908.

We hold there was substantial evidence to support the judgment of the District Court on this issue.

When Soby abandoned the projects, he left various materials, equipment and supplies on the job sites. These were used by Larsen in completing the work. When the job was completed, the items were sold to another contractor. A set-off of $3,000 for these items was granted by the trial court.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Smith v. Coyne
Maine Superior, 2004
Edward R. Marden Corp. v. S. & R. CONSTRUCTION CO., INC.
309 A.2d 675 (Supreme Court of Rhode Island, 1973)
MacRi v. United States
353 F.2d 804 (Ninth Circuit, 1965)
Danzas, Ltd. v. National Bank of Alaska
226 F. Supp. 928 (D. Alaska, 1964)
Autrey v. Williams & Dunlap
210 F. Supp. 491 (W.D. Louisiana, 1962)
Heddendorf v. Goldfine
186 F. Supp. 412 (D. Massachusetts, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
270 F.2d 193, 1959 U.S. App. LEXIS 5267, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eric-soby-dba-soby-painting-co-and-united-states-fidelity-and-guaranty-ca9-1959.