Myer Feinstein Co. v. De Vincent

30 A.2d 221, 151 Pa. Super. 254, 1943 Pa. Super. LEXIS 277
Superior Court of Pennsylvania·Decided October 6, 1942·No. Appeal, 196·Published·Cited by 11 cases

Opinion

Opinion by

Baldrige, J.,

In this action upon a contractor’s performance bond, an appeal has been taken by Alfonso De Vincent, defendant-obligor, from the action of the court below in refusing his motions for judgment n.o.v. and a new trial and entering judgment in the sum of $735 upon a finding in favor of Edward Gr. Holloway, Inc., the use plaintiff, for whom the work in question was to have been performed.

The material facts may be thus summarized: On October 11, 1940, the defendant, a bricklaying contractor, entered into a written contract with the use plaintiff in which he agreed to perform all the bricklaying required in connection with the contemplated construction of “thirty-two two-story dwellings with garages.” On the same date the defendant executed the bond, upon which this suit is based, in the sum of $10,400, conditioned upon the faithful pérformance of his contract. The obligee therein was the legal plaintiff, Myer Feinstein Co., which had agreed to assist the use plaintiff in securing the necessary funds to finance its building operation and gave the defendant its written guarantee covering payment of the sum to become due from the building corporation in connection with the brick work upon the first unit of twenty houses.

Pursuant to a warrant of attorney authorizing confession of judgment contained in the bond, the use plaintiff had judgment entered thereon and subsequently marked to its use as third party beneficiary. Damages *256 were assessed at $735, upon the filing of an averment of default, with a copy of the contract attached, alleging defendant had failed to perform any of the work agreed upon, as a result of which the use plaintiff had been required to expend the additional sum of $350 for the brick work in the twenty house unit and would be compelled to pay $385 in excess of the contract price on the balance of the houses “which said sums were just, reasonable and the market prices of same at the time in question.”

The defendant thereafter filed a petition alleging that the contract had been cancelled by mutual consent after the use plaintiff refused to secure a guarantee from Myer Feinstein Co. covering payment for the brick work on all thirty-two houses, as demanded by defendant. Attached to the petition as an exhibit was a copy of a letter dated November 7, 1940, addressed to defendant by Myer Feinstein Co., asserting its guarantee was void since it had received from Mr. Holloway, president of the use plaintiff, a release signed by defendant “releasing Mr. Holloway” from the contract. (Italics supplied) The court granted a rule to show cause why the judgment should not be opened and a defense be permitted. After an answer was filed and argument had the rule was made absolute.

The case was then transferred to the Municipal Court for trial where it was heard by Bonniwell, J., without a jury, who, at the suggestion of defendant’s counsel, unopposed by the attorney for the use plaintiff, permitted the averment of default to be considered as the statement of claim and the petition to open the judgment as the affidavit of defense.

The real question in this case was whether the contract had been cancelled by mutual agreement. The court below held it was not and found upon sufficient competent evidence in favor of the use plaintiff in the sum of $735,

*257 Counsel for defendant insists that the use plaintiff’s proofs were fatally defective on the question of damages in that a bald statement as to the amount expended without showing that it was the fair, reasonable and market cost of completing the work, furnished an insufficient basis for the verdict. It is true that the use-plaintiff’s testimony contained nothing directly estáblishing the reasonableness of the price paid Bennis & McGough who actually performed the work in question. Edward G. Holloway, president of the use plaintiff, testified without objection that his corporation had to pay to have the work done $1315 in excess of the contract price agreed to in writing by the appellant.

Counsel for defendant did not attempt by cross-examination of the witness or otherwise to impeach the reasonableness of these figures. Under our decision in Huskey Mfg. Co. v. Friel-McLeister Co., 84 Pa. Superior Ct. 328 a verdict for even $1315 might have been sustainable. We there said, page 333: “Where the subject of a contract relates to building or construction, the measure of damages is the reasonable cost to the owner of completing the contract, and where there is no other evidence on the subject the actual .cost to the owner is some evidence of the reasonable cost of completion. In Michigan Lubrication Co. v. Ontario Cartridge Co., 275 Fed. 902, the court sustained the admission of evidence as to the cost of a substituted article because it tended to establish the measure of damages. In City of New York v. Second Avenue R. Co., 102 N. Y. 572, where the defendant was bound to make repairs in a city street and neglected so to do and the city proceeded to make the repairs and purchased the necessary materials, where it appeared that the work had been done in the usual manner by agencies usually employed in the prosecution of such work, it was held that proof of the cost of the repairs was prima facie evidence in the absence of any evidence of fraud or impeachment of *258 the reasonableness of the charge.” (Italics supplied.)

Free access — add to your briefcase to read the full text and ask questions with AI

Myer Feinstein Co. v. De Vincent, 30 A.2d 221, 151 Pa. Super. 254, 1943 Pa. Super. LEXIS 277 (Pa. Ct. App. 1942).

30 A.2d 221 (Myer Feinstein Co. v. De Vincent) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Spang & Co. v. United States Steel Corp.
518 A.2d 273 (Superior Court of Pennsylvania, 1986)
Duquesne Light Co. v. Rippel
478 A.2d 472 (Supreme Court of Pennsylvania, 1984)
Delahanty v. First Pennsylvania Bank, N.A.
464 A.2d 1243 (Supreme Court of Pennsylvania, 1984)
Mancini v. Morrow
458 A.2d 580 (Superior Court of Pennsylvania, 1983)
Golomb v. Korus
396 A.2d 430 (Superior Court of Pennsylvania, 1978)
Edward R. Marden Corp. v. S. & R. CONSTRUCTION CO., INC.
309 A.2d 675 (Supreme Court of Rhode Island, 1973)
Magar v. Lifetime, Inc.
144 A.2d 747 (Superior Court of Pennsylvania, 1958)
Briskman v. Greenhill Farms of Lower Merion, Inc.
142 A.2d 504 (Superior Court of Pennsylvania, 1958)
Goldsman v. Litman
68 Pa. D. & C. 313 (Philadelphia County Municipal Court, 1948)