R.J. Wheeler Company, Inc. v. F. Petty Sons, Inc., 86-5182 (1994)

CourtSuperior Court of Rhode Island
DecidedAugust 25, 1994
DocketC.A. No. 86-5182
StatusUnpublished

This text of R.J. Wheeler Company, Inc. v. F. Petty Sons, Inc., 86-5182 (1994) (R.J. Wheeler Company, Inc. v. F. Petty Sons, Inc., 86-5182 (1994)) is published on Counsel Stack Legal Research, covering Superior Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
R.J. Wheeler Company, Inc. v. F. Petty Sons, Inc., 86-5182 (1994), (R.I. Ct. App. 1994).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]

DECISION
This action is before the court sitting without a jury and a decision is here rendered in accordance with R.C.P. 52. The case was heard before this court on June 1-2, 1994. The plaintiff seeks damages for breach of contract. The defendant counterclaims for damages resulting from breach of contract and tortious interference with contract. Jurisdiction in this court is pursuant to G.L. 1956 (1985 Reenactment) § 8-2-14 (Supp. 1993).

Facts
The evidence adduced at trial established the following facts. Plaintiff, R.J. Wheeler Company, Inc. ("R.J. Wheeler"), is a Rhode Island corporation duly incorporated under Rhode Island law. The defendant, F. Petty Sons, Inc. ("F. Petty Sons") was also a duly incorporated Rhode Island corporation at the time this cause of action accrued. The subject dispute arises out of a contract for the erection of a 32,000 square foot pre-engineered steel building in the Town of Lincoln for the Vistawall Company ("Vistawall").1

In the Spring of 1986, R.J. Wheeler negotiated with the Vistawall Company to build the pre-engineered structure to serve as a warehouse on the Vistawall site. R.J. Wheeler, as general contractor, subcontracted the erection of the structure to F. Petty Sons. The parties entered into the subcontracting agreement on April 24, 1986. (Exhibit 2). The agreement provided for a contract price of $59,300. Additionally, the agreement provides for the incorporation of the terms of the general contract between R.J. Wheeler and Vistawall ("general contract"), in particular, the requirement that change orders for extras be in writing. The evidence indicates that the general contract was not, in fact, entered into by R.J. Wheeler and Vistawall until August 13, 1986. (Exhibit 13).

F. Petty Sons was scheduled to begin work on the job site on May 12, 1986. The daily job reports compiled by Thomas Calcagne, the project foreman and R.J. Wheeler employee, indicate that the site was not ready for erection on that date. (Exhibit 3). Frank Petty, the President of F. Petty Sons, testified that the company incurred expenses due to that delay. Mr. Petty testified that additional expenses were incurred due to defects in the parts of the pre-engineered structure.

On June 4, 1986, F. Petty Sons billed R.J. Wheeler for $26,415. (Exhibit 9). The invoice indicates that $22,000 was due for construction of the red iron, the outer shell of the building. The remaining $4415 was due to extra expenses incurred as a result of the delay at the work site and defects in the parts. R.J. Wheeler tendered payment for $22,000.

Work continued on the project through June and July. Joseph Tassone, Vice President of R.J. Wheeler, testified that the company was not satisfied with the staffing provided by F. Petty Sons on the project. Additionally, Mr. Tassone testified that defendant's workers had failed to clean up their debris from the site in violation of the terms of the subcontract. On July 8, 1986, R.J. Wheeler notified F. Petty Sons, in writing, that it would charge clean-up costs if the problem continued. (Exhibit 4).

The work on the site continued into August but on August 14, 1986 R.J. Wheeler notified F. Petty Sons that it would terminate employment in forty-eight hours due to F. Petty Sons' failure to properly staff the project in violation of the subcontract. On the same day, defendant notified R.J. Wheeler, by mailgram, that it would cease work on the project unless payment was made for the work completed. (Exhibit 12). Subsequently, R.J. Wheeler hired Gansett Steel Erectors ("GSE") to finish the project.

On December 3, 1986 the plaintiff filed a complaint with this court alleging a breach of contract. Plaintiff alleges that defendant did not perform its part of the contract in that it installed the structure in an unskilled and negligent manner and that it did not properly staff the project as required by the contract. Further, plaintiff maintains that it sustained damages as a result of defendant's actions.

In response, defendant filed a counterclaim alleging breach of contract and tortious interference with contract.2 Defendant alleges that plaintiff breached its contract in that it interfered with defendant's access to the job site, provided a faulty foundation on which to build, and failed to pay the defendant for completed work. Further, defendant argues that the plaintiff tortiously interfered with a subcontract defendant had with Providence Steel and Iron Company ("PSI") on the same work site. Finally, defendant asserts that it has a mechanic's lien against Vistawall.

There are several issues before the court. Initially, this court must determine whether a valid contract exists between the parties and if so, what are the terms of such a contract. Further, this Court must review the merits of plaintiff's claim and, if it is meritorious, provide an appropriate remedy. Finally, the court must review the defendant's counterclaims.

The defendant argues that the general contract, which contains the requirement that extras be approved in writing, was not properly incorporated into the subcontract, and is, therefore, not part of the agreement of the parties. The defendant attaches great significance to the fact that the general contract was not signed until August 13, 1986, more than three months after the parties entered into the subcontract. Although this contention is appealing, it lacks merit in this case.

Generally, a subcontract may incorporate by a clearly stated general reference all of the terms of the general contract.Chicopee Concrete Service, Inc. v. Hart Engineering,498 N.E.2d 121, 122 (Ma. 1986). Although it is necessary that the matter referred to be in existence it is not necessary that it be in writing. See 17A Am.Jur.2d § 400. In the case at bar, it is clear that Vistawall and R.J. Wheeler had entered into a legally enforceable agreement long before they memorialized it into the August 13, 1986 writing. Mr. Tassone testified that he negotiated with Vistawall to build the warehouse. Subsequently, he engaged several subcontractors, including the defendant, to do work on the site. Further, the work began in May and was substantially completed by August of 1986. These actions indicate that R.J. Wheeler and Vistawall were working under a legally enforceable oral agreement which was eventually memorialized in writing. The fact that they did not memorialize this agreement into written form until August 13, 1986 is of no consequence to this case.

A party who signs a contract generally manifests assent to its terms. F.D. McKendall Lumber Co. v. Kalian, 425 A.2d 515, 518 (R.I. 1981). Mr. Petty's testimony that he did not know that the general contract required extras to be in writing is not only incredible but also immaterial. The general contract is a standard form contract distributed by the Associated General Contractors of America. The terms of said contract clearly require that change orders be obtained in writing before commencing extra work. Accordingly, this court finds that the terms of the general contract were incorporated into the subcontract and became part of the agreement of the parties.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

George v. George F. Berkander, Inc.
169 A.2d 370 (Supreme Court of Rhode Island, 1961)
F. D. McKendall Lumber Co. v. Kalian
425 A.2d 515 (Supreme Court of Rhode Island, 1981)
DiBiasio v. Brown & Sharpe Manufacturing Co.
525 A.2d 489 (Supreme Court of Rhode Island, 1987)
Chicopee Concrete Service, Inc. v. Hart Engineering Co.
498 N.E.2d 121 (Massachusetts Supreme Judicial Court, 1986)
Edward R. Marden Corp. v. S. & R. CONSTRUCTION CO., INC.
309 A.2d 675 (Supreme Court of Rhode Island, 1973)
C.N.C. Chemical Corp. v. Pennwalt Corp.
690 F. Supp. 139 (D. Rhode Island, 1988)
National Chain Co. v. Campbell
487 A.2d 132 (Supreme Court of Rhode Island, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
R.J. Wheeler Company, Inc. v. F. Petty Sons, Inc., 86-5182 (1994), Counsel Stack Legal Research, https://law.counselstack.com/opinion/rj-wheeler-company-inc-v-f-petty-sons-inc-86-5182-1994-risuperct-1994.