Jalex Builders, Inc. v. Monaghan, 98-0130 (2002)

CourtSuperior Court of Rhode Island
DecidedSeptember 19, 2002
DocketC. A. No. NM 98-0130
StatusPublished

This text of Jalex Builders, Inc. v. Monaghan, 98-0130 (2002) (Jalex Builders, Inc. v. Monaghan, 98-0130 (2002)) is published on Counsel Stack Legal Research, covering Superior Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jalex Builders, Inc. v. Monaghan, 98-0130 (2002), (R.I. Ct. App. 2002).

Opinion

DECISION
This dispute arises from a contract to construct a single-family home at 60 America Way, Jamestown, Rhode Island, entered into by Jalex Builders, Inc. (Plaintiff) and Janet Monaghan (Defendant). Plaintiff was to construct a single-family dwelling for Defendant. Defendant was to pay Plaintiff the sum of $155,503 plus the cost of any extra work as provided in a written contract. Defendant failed to make the final payments due under the contract and Plaintiff thereafter filed this action. Defendant counterclaimed for defective workmanship.

The two basic issues presented to the Court for resolution are: 1) whether Plaintiff proved Defendant was responsible for monies owed under the contract, including extra work performed by Plaintiff, and 2) whether Defendant proved that certain work was performed in an unworkmanlike fashion thereby warranting an award of compensatory damages.

FINDING OF FACT AND CONCLUSIONS OF LAW WITH RESPECT TO PLAINTIFF'S COMPLAINT
Prior to entering into a contract, the parties met on a couple of occasions. In addition, Plaintiff was provided with a set of plans that Defendant had obtained from an out-of-state company or architect. The testimony of Plaintiff is persuasive that these plans could not be used for the construction of a single-family dwelling in Rhode Island without modification.

After the contract was signed, Plaintiff had revisions prepared to the plans that were provided to him by Defendant. These plans, in conjunction with the plans for the truss roof systems, were submitted to the Jamestown Building Official to obtain a building permit. These plans were approved by the Building Official and used for the construction of the house. The Court found that these plans were provided to Plaintiff by Defendant. Defendant's plans were not the plans used to obtain a building permit or to construct the home.

After the building permit was obtained, construction started on the house. Prior to the actual work commencing, there was an issue with respect to the relocation of the house. Apparently, the survey provided to Plaintiff by Defendant was inaccurate and required that the house be relocated. Because of the change in the location of the house, the length of the driveway increased.

During the course of the construction, there were many changes made to the scope and extent of the work. Some of these changes were reflected in a change order. Others changes were not.

In late October or early November, the Certificate of Occupancy was obtained from the Jamestown Building Official. Pursuant to the terms of the contract, Plaintiff was to receive a payment in the amount of $27,503 at that time. Payment was not made by Defendant. Instead, Defendant made a direct payment to Arnold Lumber for $13,285.17, leaving a balance due under the base contract price of $14,217.83. In addition to this amount, Plaintiff is also seeking $24,349.25 for extra work and changes to the scope of the work.

There are many small extras that were added to the project during the course of the job. Plaintiff contends that all of these items were requested by Defendant and were not in the contract. There are also a number of larger items that were added to the project, such as the additional costs to construct the driveway, changes relating to the kitchen cabinet allowance, for the hardware floors, for the painting of the house, for the installation of underground utilities, and for the air-conditioning system.

According to the testimony of Plaintiff, it is not uncommon for verbal changes to be made during the course of any construction job. Plaintiff testified that when jobs are moving so fast, it is impractical and impossible to obtain written change orders prior to the actual completion of the work.

The Rhode Island Supreme Court in MBT Construction Corp. v. KelhenCorp., 432 A.2d 670 (R.I. 1981), addressed the question of the effect of parties to a contract failing to abide by the contractual terms requiring a written modification. In that case plaintiff was seeking additional compensation for construction work it performed that was not approved in writing by the defendant. In reviewing this issue, the Court stated in part as follows:

"Generally, parties to a contract may modify the written terms by a subsequent oral agreement. Assuming both parties assent to a modification rising to the level of a separate agreement, the modification will not lack enforceability simply because the parties failed to employ the particular method of modification called for in the contract. In such a situation the parties will be bound by the modification if the trial court finds that the parties waived their contractual rights regarding the procedure for modification." Id. at 674-75.

After carefully considering the testimony of both parties, this Court finds that the requirement in the construction contract for written change orders were waived by the parties as evidence by their conduct and actions. In this case, the parties engaged in a course of conduct whereby extra items would be requested or additional work authorized without there being a formal written change order. Defendant testified that she never objected to the extra work being provided by Plaintiff, and, further, she never instructed Plaintiff to stop providing the extra items and extra work. Defendant also testified that for most, if not all, of these items she actually requested that they be included in the scope of the work.

It would be fundamentally unfair and inequitable to now allow Defendant to insist upon the formality of a written change order prior to Defendant being obligated to make payment for the items when the course of conduct between the parties is persuasive that the Defendant in fact either requested, agreed to, or acquiesced to such work as the project progressed.

The Court finds that Plaintiff believes that it has established, by a fair preponderance of the evidence, that it is entitled to the principal sum of $38,567.08, said sum representing the balance of $14,217.83 which Plaintiff is due under the contract as adjusted for Defendant's payment to Arnold Lumber, plus $24,349.25 which the Court has found the Plaintiff is entitled to recover for extra work to which the Defendant assented orally or knowingly acquiesced to as the work progressed. Specifically, the Court finds Plaintiff's testimony and exhibits to be credible with respect to the value of said extra work performed by Plaintiff.

FINDINGS OF FACT AND CONCLUSIONS OF LAW WITH RESPECT TO DEFENDANT'S COUNTERLCIAM
Defendant filed a counterclaim against Plaintiff for breach of contract due to the house not being built in a workmanlike manner. The basis of the counterclaim was set forth by Gary Johnson of G. Johnson Builders (Johnson), who testified on Defendant's behalf as a qualified expert in the area of home construction. Johnson prepared a five-page proposal that set forth what was not built in a workmanlike manner, why it was not built accordingly, and the cost of repair. At the trial, Johnson further testified to what was defective concerning the workmanship provided in the construction of the home, why it was defective, and the costs of correction and repair.

Johnson stated that he performed two inspections of the house and then prepared the proposal itemizing numerous problems with the workmanship. The proposal further included labor and materials. Johnson testified that he had priced and performed all the work set forth in the proposal many times.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

MBT Construction Corp. v. Kelhen Corp.
432 A.2d 670 (Supreme Court of Rhode Island, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
Jalex Builders, Inc. v. Monaghan, 98-0130 (2002), Counsel Stack Legal Research, https://law.counselstack.com/opinion/jalex-builders-inc-v-monaghan-98-0130-2002-risuperct-2002.