Menard & Co. Masonry Building Contractors v. Marshall Building Systems, Inc.

539 A.2d 523, 1988 R.I. LEXIS 45, 1988 WL 26371
CourtSupreme Court of Rhode Island
DecidedMarch 31, 1988
Docket86-24-Appeal
StatusPublished
Cited by49 cases

This text of 539 A.2d 523 (Menard & Co. Masonry Building Contractors v. Marshall Building Systems, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Menard & Co. Masonry Building Contractors v. Marshall Building Systems, Inc., 539 A.2d 523, 1988 R.I. LEXIS 45, 1988 WL 26371 (R.I. 1988).

Opinion

OPINION

MURRAY, Justice.

This is an appeal by the plaintiff, Menard & Co. Masonry Building Contractors (Me-nard), from a judgment of the trial court. That court granted a motion for a directed verdict by the defendant, Marshall Building Systems, Inc. (Marshall). Thereafter, the trial justice granted Marshall’s subsequent conditional motion for a new trial, following upon a jury verdict for Menard. We hold that the trial justice misapplied the proper standard in directing a verdict for Marshall. We further hold that the trial justice misconceived material evidence on a relevant issue of fact in improperly granting the defendant’s conditional motion for a new trial. Thus we reverse.

The facts, as they relate to the instant appeal, are set forth below. Con-Sul, Inc. (Con-Sul), a foreign corporation, acted as general contractor in the erection of a building in Warwick, Rhode Island. 1 It subcontracted most of the work on the project to Marshall, which, in turn, entered into a subcontract with Menard to perform certain required masonry work. The subcontract between Marshall and Menard contained a provision which required that change orders be in writing. Thomas Cop-ithorne (Copithorne) represented Marshall in its negotiations with Menard and executed the subcontract for Marshall.

During its course of performance on the project, Menard was called to a meeting at the site of the construction project on January 14, 1978 by Copithorne, who served as Marshall’s project manager. Con-Sul was represented by its project manager, James Pickett (Pickett). Marshall was represented by Copithorne and its job supervisor, Charles Stone (Stone). Menard was represented by its project manager, Romeo Cilli-no (Cillino). During the meeting Pickett insisted that Menard perform overtime work to complete the construction of a wall needed to support some equipment which was to be delivered to the site the following Monday. Cillino stated that overtime was unnecessary for the timely completion of the wall. He further advised that overtime was not part of the subcontract between Menard and Marshall and that his workers *525 must be paid at overtime rates. Although Cillino testified that Pickett of Con-Sul authorized the overtime work, we find it significant that Copithorne, the party with whom Menard had entered into the subcontract, stated “Don’t worry about it, you’ll be paid for it.” Cillino testified that he understood Copithorne to mean that Marshall would pay Menard and Menard accordingly submitted its invoices for the overtime work it performed to Marshall, the party with whom it contracted. He offered unrebutted testimony with regard to situations where the subcontractor’s subcontractor performs work for the general contractor. He stated that it is customary within the construction industry for the subcontractor of a subcontractor to be paid by the party with whom it contracted, not by the general contractor. Menard was never paid for the overtime work and brought suit to recover its loss.

During the trial de novo Marshall moved for a directed verdict at the close of Me-nard’s case, which was denied. At the close of its own case Marshall again moved for a directed verdict. The trial justice reserved decision and allowed the case to go to the jury. The jury returned a verdict for Menard. Thereafter, the trial justice granted Marshall’s motion for a directed verdict and its later conditional motion for a new trial. In granting the motion for a new trial the trial justice stated that he had a “recollection that the jury was informed in some fashion that Con-Sul was now out of business.” He opined that the jury was thereby prejudiced against Marshall.

I

This court has often articulated the standard for review where the trial justice has granted a motion for a directed verdict. Like the trial justice, we are required to examine all the evidence in the light most favorable to the nonmovant, giving no consideration to the weight of the evidence or the credibility of the witnesses, and to draw from that evidence only those reasonable inferences which support the nonmov-ant’s position. The motion should be denied if our examination reveals evidence upon which reasonable minds could differ. In such a situation the jury should be left to determine the facts of the case. D’Arezzo v. Bowden, 512 A.2d 843 (R.I.1986). “However, no recovery can be predicated on positive evidence that contains inherent improbabilities or contradictions that alone or in connection with other circumstances in evidence destroy the declarant’s credibility.” Id. at 846-47. Applying the aforesaid standard to the matter on appeal, we conclude that the trial justice erred in directing a verdict for Marshall.

A

The trial justice predicated his decision to direct a verdict for Marshall upon his conclusion that “there is no evidence in this case from which the jury can conclude that, being the project manager, [Copit-horne] had authority to say ‘Don’t worry about it, Marshall will pay you.’ ” We note that the trial justice specifically found the testimony of Cillino to be credible. Thus he necessarily found that Cillino’s testimony was not to be disregarded as containing inherent improbabilities or contradictions. D'Arezzo, supra. Indeed; in considering the motion, the trial justice should have culled from the evidence only those reasonable inferences which supported Menard’s position.

Our own independent examination of the unrebutted evidence offered by Cillino reveals no inherent improbabilities or contradictions that destroy his credibility. Thus we must examine whether Menard has offered evidence upon which reasonable minds can differ, sufficient, if believed, to sustain a finding that Copithorne had authority to bind Marshall to a contract with Menard and, further, that such an implied contract, founded upon agency principles, came into existence.

B

Applying the standard of review appropriate where the trial justice has granted a motion for a directed verdict, we find that Menard has offered evidence sufficient to show that Copithorne had the ap *526 parent authority and did in fact bind Marshall to a contract with plaintiff.

Marshall has cited an old case, not binding upon this court, for the proposition that with regard to construction contracts, “[pjersons who rely upon the authority of an agent to modify by parol a written contract entered into by his principal, do so at the risk of being bound by the contract as it was made.” Ferro Concrete Const. Co. v. United States for Use and Benefit of Luchini, 112 F.2d 488, 491 (1st Cir. 1940) (citing Dudley v. Perkins, 235 N.Y. 448, 139 N.E. 570 (1923)). In Ferro the agent, a superintendent of construction who neither negotiated nor signed the contract was found to be without authority to modify said contract. Marshall asserts that its agent, Copithorne, was without authority to modify its contract with Menard by impliedly agreeing to compensate Menard for overtime, a term not contained in the contract. Thus, it argues, it is not bound to pay for such overtime.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Johnston Equities Associates, LP v. Town of Johnston
Supreme Court of Rhode Island, 2022
Fergus v. Ross
79 N.E.3d 421 (Massachusetts Supreme Judicial Court, 2017)
Haviland v. Simmons
45 A.3d 1246 (Supreme Court of Rhode Island, 2012)
Almonte v. KURL
46 A.3d 1 (Supreme Court of Rhode Island, 2012)
Manning v. Bellafiore, 2000-63 (r.I.super. 2005)
Superior Court of Rhode Island, 2005
Promac v. Vulcan Asso., 99-16 (r.I.super. 2005)
Superior Court of Rhode Island, 2005
Cin-Doo v. 7-Eleven
2005 DNH 058 (D. New Hampshire, 2005)
Carlsten v. Widecom Group, 97-1425 (2004)
Superior Court of Rhode Island, 2004
Sheldon v. Damle, 2001-0072 (2004)
Superior Court of Rhode Island, 2004
Fraioli v. Lemcke
328 F. Supp. 2d 250 (D. Rhode Island, 2004)
Carlsten v. the Widecom Group, Inc., 97-1425 (2003)
Superior Court of Rhode Island, 2003
Isaiah 61:1, Inc. v. City of Bridgeport
809 A.2d 551 (Connecticut Superior Court, 2002)
731 Airport Associates, LP v. H & M Realty Associates, LLC
799 A.2d 279 (Supreme Court of Rhode Island, 2002)
Bradford Foundation v. Town of Avon, No. Cv 99 0496299s (Oct. 3, 2001)
2001 Conn. Super. Ct. 13648 (Connecticut Superior Court, 2001)
Fanny J. Crosby Memorial v. Bridgeport, No. Cv97 0344840s (Aug. 20, 2001) Ct Page 11258
2001 Conn. Super. Ct. 11257 (Connecticut Superior Court, 2001)
Butler v. McDonald's Corp.
110 F. Supp. 2d 62 (D. Rhode Island, 2000)
Montella v. Nissan Motor Acceptance Corp.
741 A.2d 282 (Supreme Court of Rhode Island, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
539 A.2d 523, 1988 R.I. LEXIS 45, 1988 WL 26371, Counsel Stack Legal Research, https://law.counselstack.com/opinion/menard-co-masonry-building-contractors-v-marshall-building-systems-ri-1988.