Ferro Concrete Const. Co. v. United States

112 F.2d 488, 1940 U.S. App. LEXIS 4941
CourtCourt of Appeals for the First Circuit
DecidedJune 4, 1940
Docket3500
StatusPublished
Cited by20 cases

This text of 112 F.2d 488 (Ferro Concrete Const. Co. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ferro Concrete Const. Co. v. United States, 112 F.2d 488, 1940 U.S. App. LEXIS 4941 (1st Cir. 1940).

Opinion

PETERS, District Judge.

This appeal is from a judgment of the United States District Court in Rhode Island entered after a jury verdict.

It appears from the evidence that in January, 1933, Ferro Concrete Construction Company, appellant, made a contract with the United States for the construction of a public building at Newport, Rhode Island, and gave the bond required by the Hurd Act. U.S.C.Tit. 40, Section 270, 40 U.S.C.A. § 270. L. Luchini & Son, appellees, as sub-contractors, agreed with the Ferro Company to furnish the stone for the building for the specified sum of $30,000. The stone called for by the sub-contract was furnished after some-delay due to financial embarrassment of the Luchinis. During the progress of the work Ferro Company made various payments to the Luchinis and on their account aggregating $3,892.73 more than the contract price. Proceedings under the Hurd Act were brought by other sub-contractors and Luchini & Son came in as intervenors claiming under an abrogation or modification of the contract a larger sum due them than they had received; and, after a trial by jury lasting several days, they recovered a verdict for $27,-282.07 which represented the difference between $56,082.08, the amount of their claim, and the total amount they had been paid.

Objections were made by the Ferro Company to the admission and exclusion of evidence, to some parts of the judge’s charge to the jury, and to the denial of motions for a directed verdict.

It will not be necessary to consider the objections to the other rulings at the trial, as we think that the motion for a directed verdict should have been granted.

It may be convenient to refer to the partnership of the Luchinis as “Luchini”, or the plaintiff, and to the Ferro Company as “Ferro” or the defendant For the *490 purposes of the trial they occupied substantially that relationship.

No question was made that the parties deliberately entered into an agreement, evidenced by a written contract in duplicate, dated March 25, 1933, to the effect that Luchini was to furnish and deliver at the building site, finished and ready to set, the granite necessary to complete the building in accordance with the general plans and specifications, and that in return Ferro was to pay Luchini $30,000, payable in instalments, at certain stages of the work. Luchini claimed that after the execution and delivery of this written contract it was modified or rescinded with respect to the sum of $30,000 to be paid for the work, and that in lieu of the contract price Ferro agreed to pay him “what it was worth to do the job”. Denial by Ferro raised the issue of fact which was decided adversely to- Ferro by the jury.

Counsel for Ferro claim that there was before the jury no credible or substantial evidence of any modification of the contract in respect of the price, and also that there was no evidence that the person alleged to have made the modification of the contract in behalf of Ferro had any authority, express or implied, to do so.

As we agree with the defendant’s position on the question of the authority of the alleged agent to modify the written contract, and as a decision on that point is decisive of the case, we will not consider the other points raised.

The only evidence befor.e the jury of any agreement with the defendant, or anyone in its behalf, by which the plaintiff could be considered released from his obligation to furnish the stone for the contract price, is the testimony of the younger Luchini as to a conversation some time in the summer of 1933 with Starr, the superintendent of construction. Luchini was uncertain as to when the conversation occurred, but finally fixed it as “a couple of weeks, I would say, from memory” after August 8, 1933, the date of a letter written by Luchini to Ferro authorizing the latter to place' an additional man on the job to expedite the progress of the work at the quarry. The recital by Luchini of his conversation with Starr is as follows:

“I told him that I was having too great difficulty carrying on under the conditions as they existed and told him that he knew I couldn’t get any money or raise any money and that I couldn’t go on with an arrangement like that. And he asked me what I wanted. Well, we discussed the thing and I said ‘You know that I am supposed to double this plant and I am supposed to — I am supposed to double the men at the plant and increase the plant machinery itself. You want me to do all this and I can’t move a leg without going through you. So I don’t see how I can carry on. I just can’t go on and do what you want me to do. You can’t speed up this thing unless you buy more machinery or rent it and put on more men, find more men in other locations, other granite areas, and maybe we might have to increase the stationary plant * * * the stationary plant, the machines at the plant. And I am working for you for nothing and my father is, and my brother, and you are getting the use of everything we have got and I still don’t get any money for it. Now, I can’t go on unless you come with me and help to get this equipment and pay me what it is worth to do the job, and pay me and my father’s time and my brother’s time.
“Q. 212. What did he say to that? A. Why that — well, he said, ‘We can’t change now and you go ahead. You do all you can and I will come with you and, if necessary, we will go together to these equipment places, and I will tell them that we will see that they get paid.’
“Q. 213. And what did he say about payment to you? A. He said, ‘I will see that you get paid for your trouble and pay you what it is worth to do the job.’
“Mr. Edwards: Well, which is it?
“Q. 214. Now he asks you which it was. What do you say to us? A. Pay what it was worth to do the job.”

Assuming that the conversation above quoted was had between the individuals, as stated by the witness Luchini, and that it was sufficient, if authorized, to bind the Ferro Company to “change the contract price from payment of a flat sum of thirty thousand dollars to a payment upon a quantum meruit basis”, as plaintiff’s counsel puts it, it is necessary to determine the extent of the authority vested in Starr to make such a change in the contract and whether, in the absence of actual authority, Ferro was bound by his action under the circumstances of the case.

In considering evidence as to the authority of Starr to make the alleged new contract with Luchini the rule as to *491 the burden of proof is important. It was thus stated in the case of Owens Bottle-Machine Co. v. Kanawha, B. & T. Co., 4 Cir., 259 F. 838, 842:

“It is of course an elementary rule of law that a person dealing with an alleged agent is bound to ascertain his authority, and that, when suit is brought against the principal in respect of an act of such agent, the burden is upon the plaintiff to establish, not only the fact of agency, but that the act upon which he relies was within the agent’s authority.”
“A party who seeks to charge a principal for the contracts made by his agent must prove that agent’s authority; and it is not for the principal to disprove it.” Schutz v. Jordan, 141 U.S. 213

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gardi v. Jana Partners LLC (In Re Dreier LLP)
450 B.R. 452 (S.D. New York, 2011)
Tri-State Hospital Supply Corp. v. United States
142 F. Supp. 2d 93 (District of Columbia, 2001)
New England Acceptance Corp. v. American Manufacturers Mutual Insurance
368 N.E.2d 1385 (Massachusetts Supreme Judicial Court, 1977)
Eberhardy v. General Motors Corporation
404 F. Supp. 826 (M.D. Florida, 1975)
Neely v. Martin K. Eby Construction Co., Inc.
386 U.S. 317 (Supreme Court, 1967)
Cohen v. Goldman
132 A.2d 414 (Supreme Court of Rhode Island, 1957)
Amen v. Black
234 F.2d 12 (Tenth Circuit, 1956)
Johnson v. Mosley
179 F.2d 573 (Eighth Circuit, 1950)
Burke v. Mesta MacH. Co.
79 F. Supp. 588 (W.D. Pennsylvania, 1948)
Resnick v. Wolf & Cohen, Inc.
49 A.2d 809 (District of Columbia Court of Appeals, 1946)
Metallizing Engineering Co. v. B. Simon, Inc.
64 F. Supp. 848 (W.D. New York, 1945)
United States v. Bennett
57 F. Supp. 670 (E.D. Washington, 1944)
Montgomery Ward & Co. v. Duncan
311 U.S. 243 (Supreme Court, 1940)

Cite This Page — Counsel Stack

Bluebook (online)
112 F.2d 488, 1940 U.S. App. LEXIS 4941, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ferro-concrete-const-co-v-united-states-ca1-1940.