Fanning & Doorley Construction Co. v. Geigy Chemical Corp.

305 F. Supp. 650, 1969 U.S. Dist. LEXIS 9414
CourtDistrict Court, D. Rhode Island
DecidedOctober 28, 1969
DocketCiv. A. 3152
StatusPublished
Cited by5 cases

This text of 305 F. Supp. 650 (Fanning & Doorley Construction Co. v. Geigy Chemical Corp.) is published on Counsel Stack Legal Research, covering District Court, D. Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fanning & Doorley Construction Co. v. Geigy Chemical Corp., 305 F. Supp. 650, 1969 U.S. Dist. LEXIS 9414 (D.R.I. 1969).

Opinion

OPINION

PETTINE, District Judge.

This is a claim for payment of a balance due under a contract for the construction of a system of underground piping with a counterclaim by the defendant owner seeking liquidated and other damages. The American Insurance Company, defendant to the counterclaim, is the surety on the plaintiff’s performance bond.

Findings of Fact

Fanning & Doorley Construction Co., Inc. (hereinafter referred to as “Fanning & Doorley”), the plaintiff in this action, is a Rhode Island corporation engaged in the construction business. Defendant, Geigy Chemical Corporation (hereinafter referred to as “Geigy”), is a Delaware corporation with its main offices in Ardsley, New York. Geigy has a plant in Cranston, Rhode Island, called the Alrose Division, which is engaged in the manufacture of chemicals.

During the year 1958, Geigy decided to have constructed a new system of underground piping at its Alrose Plant and engaged Metcalf & Eddy, a Boston, Massachusetts firm of consulting engineers as advisors. They were retained to draw plans, specifications and prepare a eon-tract. In addition, they were to let the contract for the construction of the system and supervise its execution. ' As a result, they prepared the “Book”, so-called, which contained, among other things, information for bidders, form of bid, contractor’s bond and specifications for the work to be done.

The work under this proposed contract consisted of the construction of cast-iron water piping, concrete storm drains, a vitrified clay sanitary sewer system, an industrial waste sewer system, and a booster pumping station and appurtenant work. Metcalf & Eddy, after investigation by one of its engineers, John Podger, recommended (and it was specified in the Book) that the industrial waste system be constructed of chemical stone ware bell and spigot pipe and that said pipe be joined by using a material called Causplit; a mortar produced by blending a resin and powder which is resistant to the corrosive effects of acids, alkalis and alcohols of the type that are discharged from the Alrose Plant.

In July, 1959, the Book was circulated to several contractors, including Fanning & Doorley, and bids were invited using the form of proposal contained therein. In the portion of the Book entitled “Information For Bidders,” prospective bidders were warned to satisfy themselves by examination as to the actual conditions and requirements of the work and that the information furnished was not guaranteed to be accurate. In addition, bidders were advised to satisfy themselves regarding the character, quantities and conditions of the various materials which would be used. 1

*662 Fanning & Doorley, on or about July 31,1959, submitted its bid on a unit price basis using the form set forth in the Book. In this form of bid, units and quantities of work of different kinds were estimated and a price submitted for each. Fanning & Doorley’s bid on the units estimated in the Book totaled $204,-147.50. The prescribed contract was executed on August 28, 1959, by the appropriate officers of Fanning & Doorley and Geigy. At the same time a “Supplemental Agreement” was also signed and made part of the Book, which provided, among other things, that Fanning & Doorley would be paid on the basis of its cost plus 15%, but that the total amount payable would not exceed the total amount computed by using the prices stipulated in the proposal. In other words, this was a cost plus contract with a top or upset limit. Also, on August 28, 1959, a performance bond was executed by Fanning & Doorley, as principal, and The American Insurance Company, as surety, the latter being a defendant to Geigy’s counterclaim in this action.

Following the signing of the contract, the work was scheduled to commence on September 21, 1959 and be completed by *663 February 24,1960, the end of the 180-day specified contract period.

The specifications for the chemical stoneware pipe provided in pertinent part as follows:

“Except as hereinafter specified, the pipe shall be jointed with asbestos-rope calking and Causplit Mortar made by Pennsalt Chemicals Corp., Philadelphia, Pa. The Contractor’s attention is directed to the fact that Causplit is a phenol-formaldehyde type resin and that some persons are allergic to such materials. Causplit shall at all times be handled and joints shall be made in accordance with the recommendations of the manufacturer and extreme care shall be taken in its use to avoid any possible damage.
“Expansion joints shall be made, as indicated on the drawings, with asbestos-rope calking and a plasticized epoxy similar to Coroline E manufactured by the Ceilcote Co., Cleveland, Ohio.
“After the pipe has been laid and jointed but before the concrete cradle is placed, all areas of the pipe that would otherwise be in contact with the concrete shall be covered with a bituminous impregnated felt to ensure that no bond will exist between the pipe and the cradle.” (See fn. 1 — Sec. 16.4)

In addition, there was a provision that the sewers and manholes had to meet certain leakage test requirements and that:

“Portions of sewers which fail to meet tests shall be repaired and retested as necessary without additional compensation until test requirements are met.” (See fn. 1 — Sec. 15.8)

The supervision of the execution of the contract was vested in the Engineer (Metcalf & Eddy), and it provided in Article III that the Engineer would in all cases determine the amount, quality, acceptability, and fitness of the work, and further that in the event that a determination or decision of the Engineer was questioned by the Contractor, the decision of the Engineer would be a condition precedent to the Contractor’s right to receive any money for the work to which the question or difference in opinion related. Article II provided that the Contractor would do all the work and everything necessary for performance and completion as required by the contract in the manner and within the time specified, and that the entire work be completed to the satisfaction of the Engineer. In Article XXIV it was further provided:

“If the work or any part thereof shall be found defective at any time before the final acceptance of the whole work, the Contractor shall forthwith make good such defect in a manner satisfactory to the Engineer * * * ”

Fanning & Doorley started work under the contract in the latter part of September, 1959. During the time that followed, Metcalf & Eddy, on the authority of Ceigy, issued twelve (12) written supplemental agreements, so-called, which provided in some cases for extra work or a redesign of work, and in other cases for a deletion of work. The defendant contends that the major item not completed by July 1960 was the chemical stoneware system and argued this item was crucial and it was apparent that Fanning & Doorley did not complete and was not going to complete this requirement. (On post trial arguments, counsel for defendant. did not deem it significant to consider manhole leakage. As a consequence, this court will not concern itself with the leakage failures of the same).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Havens Steel Co. v. Randolph Engineering Co.
613 F. Supp. 514 (W.D. Missouri, 1985)
United States Fid. & Guar. Co. v. Jacksonville
357 So. 2d 952 (Supreme Court of Alabama, 1978)
L. M. White Contracting Co. v. St. Joseph Structural Steel Co.
488 P.2d 196 (Court of Appeals of Arizona, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
305 F. Supp. 650, 1969 U.S. Dist. LEXIS 9414, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fanning-doorley-construction-co-v-geigy-chemical-corp-rid-1969.