Blue Bell, Inc. v. Cassidy
Opinion
This is an action to recover damages resulting from the collapse of a portion of a building on February 15, 1958, near Tupelo, Mississippi. Plaintiff, Blue Bell, Incorporated, bottomed its claim on the alleged negligence of defendant, John Cassidy, doing business as John Cassidy Construction Company, in failing to adequately protect his work. The case was tried to the Court without a jury and is now for disposition on briefs.
The building about which this controversy arose is an industrial type building with tilted concrete walls, concrete floors and a light concrete roof which was constructed by defendant under a contract with the plaintiff. This contract consists of the Standard A. I. A. Form A-l issued by the American Institute of Architects, printed “General Conditions” published by the American Institute of Architects, and the plans and specifications prepared by architects employed by plaintiff and by engineers employed by the architects with the approval of plaintiff. Defendant contractor was to supply all materials and labor necessary for the completed building with the exception of the structural steel work, certain electrical work, painting, conveyor systems, well and water tank, and balcony grating, which were to be provided by other contractors or by plaintiff. For this he was to receive a fixed contract price.
The architects had general supervision and direction of the work and were required to furnish with reasonable promptness any additional instructions that were necessary for the proper execution of the work. It was also the responsibility of the architects to make decisions on all matters relating to the execution and progress of the work. Defendant was relieved of responsibility for damages to the work due to causes beyond his control or without fault or negligence on his part.
No extra work could be done or change made, except in an emergency endangering life or property, unless in pursuance of a written order from the owner signed or countersigned by the architects or a written order from the architects stating that the owner had authorized the extra work or change.
The foundations for this building were to be piles of the bored pedestal type with belled bottoms and changes in depth of piles or sizes of bells could be ordered by the architects if a revision of the foundation was required because of soil conditions encountered. When work on foundations began, one of the engineers was present and soil conditions were encountered which required a change in the design of the piles. Under the direction of the architects and engineers, friction-type piles were substituted.
In the latter part of 1957, defendant’s superintendent noticed some bowing in the structural steel and reported this [445] fact to the engineers, but nothing was done about this by the engineers or architects. ■
Work continued until January 7, 1958, at which time there remained only the finishing work to be done. On that day it was discovered by defendant that certain columns supporting the structural steel beams had settled or sunk into the ground which caused excessive water to pond or stand on the roof. The architects and engineers were notified and the following day one of the architects and one of the engineers visited the job site for the purpose of making an inspection. They were accompanied on this inspection by defendant’s superintendent.
There was a sharp conflict in the evidence concerning instructions given to defendant’s superintendent on the job on this occasion. Plaintiff claims that the superintendent was instructed to shore up two of the columns. Defendant’s evidence, which is more persuasive, is to the contrary. He contends that the superintendent was instructed at this time to take readings as to the settlement of all columns and it is undisputed that readings were taken shortly after the meeting on January 8, which showed that five columns had settled more than 2% inches. The two columns about which the controversy exists had settled more than the others. However, this dispute is inconsequential since these two columns were shored up on the night of January 15 and the eventual collapse of a portion of the roof was in no wise caused by these columns being shored on January 15 rather than on January 8.
Plaintiff also strongly contends that at the January 8 meeting the engineer directed the superintendent on the job to shore up any column that settled more than 2% inches. This is sharply contradicted by defendant’s witnesses, and their version is supported by other circumstances as will be seen. The evidence is in conflict as to the amount of settling of columns after January 8, but the first reading taken on January 8 showed that at least five columns had settled more than 2% inches, and plaintiff does not claim that the superintendent was expressly instructed on January 8, or at any other time, to shore up all five of these columns. Additionally, it is significant to note that on January 14, one of plaintiff’s engineers and one of plaintiff’s architects visited this job site with the Dean of the School of Engineering of the University of Mississippi to obtain his advice about what should be done. During this visit defendant was directed to make a load test on one or two of the columns, and, there is no evidence that any comment was offered or complaint made at this time by the architect or the engineer with respect to the absence of shoring. It is also significant to note that the testimony of the engineer, who was present at the job on January 8, negatives the issuance of the aforementioned positive general directions. Referring to what transpired then, he said:
“Mr.-Footnotes
200 F. Supp. 443 (Blue Bell, Inc. v. Cassidy) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.