Evergreen Amusement Corp. v. Milstead

112 A.2d 901, 206 Md. 610
CourtCourt of Appeals of Maryland
DecidedOctober 1, 1998
Docket[No. 98, October Term, 1954.]
StatusPublished
Cited by80 cases

This text of 112 A.2d 901 (Evergreen Amusement Corp. v. Milstead) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Evergreen Amusement Corp. v. Milstead, 112 A.2d 901, 206 Md. 610 (Md. 1998).

Opinion

Hammond, J.,

delivered the opinion of the Court.

The Evergreen Amusement Corporation, the appellant, operator of a drive-in movie theater, was held liable by the court, sitting without a jury, to Harold D. Milstead, the appellee, a contractor, for the balance due on a writ *614 ten contract for the clearing and grading of the site of' the theater and certain extras, less the cost of completing a part of the work and damages for delay in completion, based on rental value of the theater property during the period of delay and out-of-pocket costs for that time.

The appellant, by counter-claim, sought recovery of lost profits for the period of delay. The court held the amount claimed to have been so lost to be too uncertain and speculative, and refused evidence proffered to support appellant’s theory. The appellant makes four contentions: that the damage ruling was error; that it should have been allowed to prove a contemporaneous oral agreement as to time of performance; that the appellee was entitled to no compensation for fill dirt supplied by him to bring the property up to grade; and, finally, that the appellee should not be permitted to recover at all because he did not fully perform.

Under the terms of the contract, appellee agreed to supply necessary materials and perform the work needed to clear the theater site of timber, stumps and waste material, to “grade the site as indicated on the plans” and construct a drainage ditch on the north side of the property and install two hundred feet of pipe. It then provided: “At this contract price, no additional fill material will be substituted for unsuitable material found on the site.”

The trial court found that both sides assumed when they contracted and the work began, that the site could be graded merely by moving the earth from certain parts of it to other parts, and that no additional dirt from the outside would be needed to reach the desired grade. Preliminary engineering studies on both sides, such as they were, relied on a contour map showing the topography of the ground, based on a survey made by a man who did not testify. Doubt was cast on the accuracy of the map by an engineer, who explained that the piles of debris, stumps and tree trunks.oh the property when the map presumably was prépáredy would have made, it difficult accurately to' prepare it. The court *615 found that the only accurate method would have béen to make a complete cross-section of the property at reasonable intervals. It found the calculations of both sides to have been in error, as the fact that after some eight thousand cubic yards of dirt were hauled in the grading was still not finished as desired, bears persuasive witness. Indeed, the parties agreed that the north side of the site should be left slightly below the planned grade so that additional dirt would not have to be brought in. In any event, it was soon discovered that the cuts and fills would not balance and that a large amount of borrow would be required. At a meeting of the parties, it was agreed that such fill dirt as was needed to bring the site up to grade would be brought in, except at the north side, and that the appellee would be paid for this borrowed dirt at sixty-eight cents a yard. This agreement is denied by the appellant but the trial court found as a fact that it was made. Two writings support the finding. One is the daily log kept by the president of the appellant, who was on the site as the work went on. It repeatedly recorded the amount of borrow brought into the job, in terms of pan-loads. The other is the bill of the appellee, which included the cost of this borrowed dirt; it was approved in writing by the president of the appellant. The appellant says that even if it did agree to pay for the extra dirt, there was no consideration for its agreement, because, under the contract, the appellee was required to furnish all materials needed. The contractor counters by pointing to the clause in the contract that at the price offered “no additional material will be substituted for unsuitable material on the site.” We think the agreement to pay for the additional dirt was binding on either of two theories—that of unforeseen difficulty or that of interpretation of the contract from the conduct of the parties.

It is undenied that the owner and contractor both thought it to be a solid fact that the cuts and fills would balance. Certainly the discovery that outside fill dirt to the value of thousands of dollars—more than the whole *616 of thé original contract cost—would be needed to reach grade, was not only evidence of mutual mistake but of revelation of unforeseen difficulty. In Lange v. United States, 4th Cir., 120 F. 2d 886, Judge Dobie, for the Court, pointed out that the general rule is that doing something one is under legal obligation to do, is not consideration which will support a promise to pay additional compensation therefor, and said: “But to this rule the Court of Appeals of Maryland admits an exception, an exception criticized by Williston on Contracts, Sec. 130 (a), but seemingly recognized in the Restatement in Sec. 76, Illustration 8.” Judge Dobie observed that “* * * both parties were taken by a surprise which might have been avoided had either party taken the necessary precautions. We, therefore, are of the opinion that the pending case falls within the principle and spirit of the exception set out in Linz v. Schuck; and we are confirmed in this view by the disposition of the Court of Appeals of Maryland, manifested in later cases, to give a liberal application to the exception of unforeseen difficulties. See Dickinson & Tweeddale v. Fowler, 1911, 114 Md. 344, 79 A. 519; People’s Banking Co. v. Fidelity & Deposit Co., 165 Md. 657, 170 A. 544, 171 A. 345.”

■ On the other theory, either the contract clearly meant what the contractor said it meant, in which case the agreement to pay for extra dirt certainly was binding and to have been expected, or, at least, was ambiguous. If the latter, determination of its real meaning can be aided by the construction the parties put upon it, as revealed by their actions. Among the officers of appellant, who agreed to pay for the outside fill, were experienced business men and drive-in theater builders. Records were kept of the amount brought in. Bills for the cost of that amount in excess of the original contract price were approved in writing by appellant. Only when shortness of funds sharpened its critical eye did it seek to repudiate the effect of its earlier actions. In Saul v. McIntyre, 190 Md. 31, 36, the Court said the conduct of the parties to a written contract may amount not only *617 to a construction of ambiguous provisions but may even evidence a subsequent modification of its terms. In Eastern Woodworks, Inc. v. Vance, 206 Md. 419, again it was held that the construction placed on the contract by the parties themselves may be relevant. See also B. & O. R. R. v. State, 45 Md. 596; Mattingly Lumber Co. v. Equitable Bldg. & Savings Assn., 176 Md. 403, 408; National Union Mtge. Corp. v. Potomac Consol. Debenture Corp., 178 Md. 658; McKeever v. Washington Heights Realty Corp., 183 Md. 216.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

CR-RSC Tower I, LLC v. RSC Tower I, LLC
56 A.3d 170 (Court of Appeals of Maryland, 2012)
Arthur E. Selnick Associates, Inc. v. Howard County Maryland
51 A.3d 76 (Court of Special Appeals of Maryland, 2012)
U.K. Construction & Management, LLC v. Gore
20 A.3d 163 (Court of Special Appeals of Maryland, 2011)
(2002)
87 Op. Att'y Gen. 3 (Maryland Attorney General Reports, 2002)
Sharick v. Southeastern University of Health Sciences, Inc.
780 So. 2d 142 (District Court of Appeal of Florida, 2001)
Lerner v. Lerner Corp.
750 A.2d 709 (Court of Special Appeals of Maryland, 2000)
National School Studios, Inc. v. Mealey
126 A.2d 588 (Court of Appeals of Maryland, 1999)
Beverly Hills Concepts, Inc. v. Schatz & Schatz, Ribicoff & Kotkin
717 A.2d 724 (Supreme Court of Connecticut, 1998)
Goldman, Skeen & Wadler, P.A. v. Cooper, Beckman & Tuerk, L.L.P.
712 A.2d 1 (Court of Special Appeals of Maryland, 1998)
Stewart Title Guaranty Co. v. West
676 A.2d 953 (Court of Special Appeals of Maryland, 1996)
Waller v. Maryland National Bank
620 A.2d 381 (Court of Special Appeals of Maryland, 1993)
Edwards Family Ltd. Partnership v. Barlow
915 F.2d 1564 (Fourth Circuit, 1990)
Usemco, Inc. v. Marbro Co.
483 A.2d 88 (Court of Special Appeals of Maryland, 1984)
Chlan v. KDI Sylvan Pools, Inc.
452 A.2d 1259 (Court of Special Appeals of Maryland, 1982)
Design & Funding, Inc. v. Betz Garage, Inc.
438 A.2d 1316 (Court of Appeals of Maryland, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
112 A.2d 901, 206 Md. 610, Counsel Stack Legal Research, https://law.counselstack.com/opinion/evergreen-amusement-corp-v-milstead-md-1998.