Usemco, Inc. v. Marbro Co.

483 A.2d 88, 60 Md. App. 351, 39 U.C.C. Rep. Serv. (West) 1600, 1984 Md. App. LEXIS 426
CourtCourt of Special Appeals of Maryland
DecidedNovember 8, 1984
Docket26, September Term, 1984
StatusPublished
Cited by11 cases

This text of 483 A.2d 88 (Usemco, Inc. v. Marbro Co.) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Usemco, Inc. v. Marbro Co., 483 A.2d 88, 60 Md. App. 351, 39 U.C.C. Rep. Serv. (West) 1600, 1984 Md. App. LEXIS 426 (Md. Ct. App. 1984).

Opinion

BLOOM, Judge.

Appellant, USEMCO, Inc., sued appellee, Marbro Company, Inc., in the Circuit Court for Prince George’s County, for money allegedly due as final payment for an automatic pumping station Marbro purchased from USEMCO for inclusion in a sewage treatment facility Marbro built for Anne Arundel County. Marbro pleaded a “set off and counterclaim” in which it acknowledged that it withheld the final payment but asserted that USEMCO was responsible for delays in completion of the facility that caused Marbro to be assessed liquidated damages by Anne Arundel County in a total amount greater than the $23,500 due USEMCO. *354 The case was removed to the Circuit Court for Anne Arundel County where, after a nonjury trial, USEMCO was determined to be liable for a substantial part of the liquidated damages sustained by Marbro. Appealing from a judgment in its favor for just $1750, USEMCO raises the following issues:

1) Did the lower court err in not accepting as controlling the Standard Terms and Conditions as part and parcel of this contract?
2) Did the lower court err in finding a breach of this contract, resulting from the alleged delay on the part of the appellant?
3) Did the lower court err in assessing damages against the appellant in this matter by using the liquidated damage clause of the contract between appellee and Anne Arundel County?
4) Did the lower court err in its analysis of the facts, and was the error instrumental in the court finding the way it did, thereby resulting in reversible error?

Our answer to each of those questions is “No,” although with respect to the first three of them we take a somewhat different route than the trial court followed to reach the same destination.

Facts

USEMCO is a manufacturer of pumping stations. Through its Maryland agent, Flow Industries, Inc. (Flow), USEMCO learned that Anne Arundel County was soliciting bids for the construction of sewage systems. Flow obtained for USEMCO a set of the county’s plans and specifications, on the basis of which USEMCO prepared a proposal for Flow to transmit to Marbro and other general contractors interested in submitting bids to the county. As prepared by USEMCO, the pertinent portions of the document read as follows:

USEMCO proposes to offer for sale the equipment described below, subject to the Standard Terms and Condi *355 tions of Sale contained in USEMCO’s Order Acknowledgement Form.
USEMCO factory built automatic pumping station with a nominal initial design capacity [followed by detailed specifications and dimensions not necessary to repeat here]. The principal components shall include:
PUMPS: 2 rated at 2000 gpm. The pumps proposed are 8 inch, model 8 x 8 x 17, manufactured by Allis Chalmers. Motors shall be supplied at 30 Hp, 860 rpm, to operate on 3 phase, 460 volts power.
CONTROL: NEMA I, Type Bubbler Flowmatcher. PIPING: Suction 12 inch, Discharge 12 inch.
[Auxiliary equipment and specially required equipment were also listed.]
Price: _F.O.B. factory, freight allowed.
Delivery: 24-28 weeks estimated, after receipt of approved drawings.

Flow was instructed to price the proposal and send copies to Marbro and other interested contractors.

Based on USEMCO’s proposal, Marbro submitted a bid to Anne Arundel County and sent to Flow, on Marbro’s stationery, an order in the following form:

2 pump station (200 GPM &
200 GPM
as per plans to specs)
1 Magnetometer &
Recorder
as per plans & Specs
[This order is contingent upon award, and equipment subject to approval by Anne Arundel County.]
Total 72,500.00

According to testimony adduced by it at trial and not contradicted by Marbro, USEMCO then sent to Marbro by mail an Order Acknowledgment form together with a three page document entitled “Standard Terms and Conditions of Sale.”

*356 USEMCO’s Order Acknowledgment form thanked the customer for the order, acknowledged its receipt and advised that the order had been accepted and was “subject to our Standard Terms and Conditions, which are attached to our Order Acknowledgement.” Included among the provisions printed on the Standard Terms and Conditions form were the following:

1. This proposal is based upon a design prepared by USEMCO which is similar to the quantities and/or specifications shown by the job plans. This proposal does not guarantee that the product described herein is in exact accord with the job plans.
******
3. USEMCO shall schedule delivery at the earliest possible date; all delivery schedules are estimates only, based on the best information available.
* j¡c sic * *
9. USEMCO shall not be liable for any losses, damages, or delays due to or caused by transportation difficulties, fire, labor shortages, strike or other labor disputes, civil or military authority insurrection, riot, war, accident, shortage of labor or material, failure of USEMCO to receive brand name parts or other materials necessary for the construction of this equipment, flood, storm, flotation of equipment, or any other cause or circumstance, whether like or unlike the foregoing, beyond USEMCO’s reasonable control or for any delays due to failure of buyer to furnish and/or approve technical data, drawings, etc. Acceptance of equipment on delivery shall constitute a waiver of any claims for losses or damages due to delay, whether or not excused by the foregoing, and a waiver of the right to revoke such acceptance for any reason. Further, under no circumstances shall USEMCO be liable for any liquidated, special or consequential damages or for any penalties, whether direct or indirect.

The county’s plans and specifications called for “built-together” pumps with wound rotor motors. Contending that *357 no company in the United States made wound rotor motor “built-together” pumps and relying upon an “equal or better” clause in the county’s plans and specifications, USEMCO proposed to substitute what is known in the trade as “flex-coupled” pumps, which USEMCO insists are superior in performance to “built-together” pumps.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Paccar Inc. v. Elliot Wilson Capitol Trucks LLC
923 F. Supp. 2d 745 (D. Maryland, 2013)
Prison Health Services, Inc. v. Baltimore County
912 A.2d 56 (Court of Special Appeals of Maryland, 2006)
Stewart Title Guaranty Co. v. West
676 A.2d 953 (Court of Special Appeals of Maryland, 1996)
Lenkin-N Ltd. Partnership v. Nace
568 A.2d 474 (District of Columbia Court of Appeals, 1990)
Brown MacHine, Division of John Brown, Inc. v. Hercules, Inc.
770 S.W.2d 416 (Missouri Court of Appeals, 1989)
Kline Iron & Steel Co. v. Gray Communications Consultants, Inc.
715 F. Supp. 135 (D. South Carolina, 1989)
Maurice Electrical Supply Co. v. Anderson Safeway Guard Rail Corp.
632 F. Supp. 1082 (District of Columbia, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
483 A.2d 88, 60 Md. App. 351, 39 U.C.C. Rep. Serv. (West) 1600, 1984 Md. App. LEXIS 426, Counsel Stack Legal Research, https://law.counselstack.com/opinion/usemco-inc-v-marbro-co-mdctspecapp-1984.