Lange v. United States

120 F.2d 886, 1941 U.S. App. LEXIS 3579
CourtCourt of Appeals for the Fourth Circuit
DecidedJune 10, 1941
Docket4744
StatusPublished
Cited by18 cases

This text of 120 F.2d 886 (Lange v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lange v. United States, 120 F.2d 886, 1941 U.S. App. LEXIS 3579 (4th Cir. 1941).

Opinion

DOBIE, Circuit Judge.

This is an appeal from a judgment of the District Court rendered in a suit on a contract brought pursuant to the provisions of the Act of August 24, 1935, Chapter 642, §§ 1-4, 49 Stat. 793, 794, 40 U.S.C.A. §§ 270a-270d. See United States -v. Lange, D.C.D.Md.1940, 35 F. Supp. 17.

On November 23, 1938, a contract was awarded to Lange Brothers (hereinafter called appellants) for the construction of a laundry building for the United States at the Naval Academy, Annapolis, Maryland. Prior to the submission of their total bid as general contractors, appellants had obtained estimates from subcontractors on the cost of sundry different items intended to be let out to these subcontractors by the general contractors. One of these items was the construction and installation in this building of a laundry or clothes chute. On November 11, 1938, C. M. Wilkinson, doing business as C. M. Wilkinson & Company (hereinafter called appellee) had made a written offer to construct this chute for the price of $347. The appellee's *887 offer ivas finally reduced to $325 and, after tlie Government liad accepted appellants’ bid of over $168,000 for the entire work, .appellee’s reduced offer for the chute war, embodied in a formal contract of the parties, bearing the date of March 1, 1939. The entire work on the chute, undertaken by the appellee, was to be in strict accordance with the plans and specifications of the Government architect, and was subject to the approval and acceptance of both the appellants and the Government.

Subsequent to the signing of the contract of March 1, 1939, appellants mailed to appellee page 26 of the General Government Specification which read:

“8-08. Clothes Chute shall be made of corrosion-resisting steel sheets not less than 0. 110 inch thick and conforming to grade 1, class 4 of specification No. 47S20a. The chute shall be of welded construction and all interior welding beads shall be ground down to a smooth, polished, continuous surface with no burns or protusions that might injure wet clothing. The chute shall be securely braced externally to withstand the stresses imposed by a 500-pound load passing through at one time. Supports shall be braced securely and anchored rigidly to the floor structure.”

Appellee, despite his long experience in the sheet metal business, had never heard of the symbol No. 47S20a; and, in fixing the total amount of his original estimate, appellee had figured that the metal required was “corrosion-resisting steel sheets” of copper bearing metal, a material which cost only five cents a pound. This symbol, No. 47S20a, however, though not ordinarily used in general lines of manufacture and fabrication, was yet quite commonly used for marine work; and, unknown to appellee, the symbol definitely called for the use of “stainless steel,” a material which cost about forty-six cents a pound. It was not until June, 1939, seven months after appellee’s original bid and about three months after the signing of the first contract, that appellee learned the true significance of this symbol.

After the signing of the first contract, appellants had sent appellee the one page, quoted above, of the General Specifications. Appellants did not, however, forward to appellee the separate pamphlet or bulletin which is known by the designated symbol No. 47S20a. Although this bulletin was in appellants’ possession, appellants evidently did not think it necessary to bring its precise contents specifically to the attention of appellee. Thus, appellee did not become aware of the meaning of the symbol until the Naval Academy authorities, in correcting the drawings submitted by appellee, referred to “Grade 1, Class 4 of Navy Department Specification No. 47S20a.”

On discovering the nature of the material required by No. 47S20a, appellee sent a letter to appellants under date of June 27, 1939, explaining the mistake made by appellee in fixing the price of the chute. This letter included the following words:

“ * * * We have no desire to force our design in this case where the officials have likely been impressed by something special on which they may insist by demanding that any other concern live up to the specifications to the letter and that we cannot do at the price we have given you for standard chute.”

Appellants’ letter of July 8, 1939, the next item in the correspondence found in the record, seemed to ignore appellee’s letter of June 27th; but this letter of appellants did state that shop drawings had not yet been submitted in proper form for approval, that the building had been ready to receive the installation of the chute, that there was no reason for “any further stalling” by appellee, that unless drawings were resubmitted for approval not later than July 13th, in accordance with the requirements of the plans and specifications, appellants would find it necessary to have the work performed by others.

One of the most vital links in the whole chain of negotiations was the telephone conversation between the parties on July 14, 1939. Unfortunately, the record gives us little specific information about this conversation. It is mentioned, however, in a letter written to appellants by appellee’s representative under date of July 14, 1939: “Confirming our phone message wish to say that our president has gone into the matter personally and advises us that he is willing to eliminate profit in an attempt to meet the situation which he realizes is awkward for all concerned and makes the rock bottom price of $1,071.00 and supply the chute of the metal specified in government specifications.”

Appellee had arrived at an adjusted figure of $1,271. But in the course of the negotiations (evidently during the telephone conversation), appellee agreed to *888 deduct anything pertaining to overhead or profit, thereby deducting an amount equivalent to $200. The final figure, as thus determined, was, accordingly, $1,071.

It was brought out in the oral testimony that after appellants had been informed that appellee would not continue under the contract of March 1st, and after appellants had written the stem letter of July 8th, appellants had proceeded “to get some other prices” on the diute. One of the appellants testified that the prices in three bids thus submitted were all greater than appellee’s revised price.

On July 24, 1939, appellants wrote to appellee enclosing a draft of the new contract and urging that the chute be erected not later than the week of August 14, 1939. The second formal contract embodied practically all the 'terms of the first and, except for the higher price and certain minor, we think, adjustments, the second contract is practically identical with the first contract. The date set for the completion of the chute was naturally advanced — the new date being September 12, 1939; the old, May 15, 1939. Again, in the first contract, it is provided that appellee shall submit, not later than ten days after the date of the contract, copies of all shop drawings and also the names of materials and appliances called for by the specifications. In the second contract, the time for submitting drawings, etc., is cut in half and, in addition, specific mention is again made for a complete set of drawings to be furnished by appellee.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fort v. Kudeviz (In re Genesis Press, Inc.)
559 B.R. 445 (D. South Carolina, 2016)
Sumerel v. Goodyear Tire & Rubber Co.
232 P.3d 128 (Colorado Court of Appeals, 2009)
Evergreen Amusement Corp. v. Milstead
112 A.2d 901 (Court of Appeals of Maryland, 1998)
Lowey v. Watt
684 F.2d 957 (D.C. Circuit, 1982)
Canaras v. Lift Truck Services, Inc.
322 A.2d 866 (Court of Appeals of Maryland, 1974)
United States v. Gilman
360 F. Supp. 828 (D. Maryland, 1973)
Dowling v. Bruffey
291 A.2d 471 (Court of Appeals of Maryland, 1972)
Limestone Realty Co. v. Town & Country Fine Furniture & Carpeting, Inc.
256 A.2d 676 (Court of Chancery of Delaware, 1969)
Hester v. New Amsterdam Casualty Company
268 F. Supp. 623 (D. South Carolina, 1967)
Merit Music Service, Inc. v. Sonneborn
225 A.2d 470 (Court of Appeals of Maryland, 1967)
Binder v. Benson
171 A.2d 248 (Court of Appeals of Maryland, 1961)
Brown v. Woodring
174 F. Supp. 640 (M.D. Pennsylvania, 1959)
Orsini v. Lathrop Co.
12 Alaska 641 (D. Alaska, 1950)
United States v. Jones
176 F.2d 278 (Ninth Circuit, 1949)
Pet Milk Co. v. Boland
175 F.2d 151 (Eighth Circuit, 1949)
Schiavi v. Mayor of Baltimore
40 F. Supp. 184 (D. Maryland, 1941)

Cite This Page — Counsel Stack

Bluebook (online)
120 F.2d 886, 1941 U.S. App. LEXIS 3579, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lange-v-united-states-ca4-1941.