Pet Milk Co. v. Boland

175 F.2d 151, 1949 U.S. App. LEXIS 2348
Court of Appeals for the Eighth Circuit·Decided May 24, 1949·No. No. 13815·Published·Cited by 8 cases

Opinions

COLLET, Circuit Judge.

This action is to recover on quantum meruit for a balance alleged to be due ap-pellee [plaintiff] for the construction of a sewer line for appellant [defendant] at the latter’s Siloam Springs, Arkansas, plant. The controversy in the trial court and about which this appeal is concerned revolves around the question of whether a certain written “Purchase Order” submitted to plaintiff and signed by his representative, his son, represented the agreement between the parties or whether an oral agreement, varying in one important respect from the written purchase order, constituted the contract. There was -a jury verdict for the plaintiff for $30,023.78 and interest for which judgment was given. After unsuccessful motions for judgment for defendant notwithstanding the verdict or for a new trial, this appeal followed. Generalizing the defendant’s contentions, it asserts that (a) the written purchase order constituted the contract between the parties and that parol evidence of conversations and understandings had prior to and contemporaneously with its execution, which were admitted as evidence, violated the parol evidence rule, (b) that the parol agreement asserted by plaintiff constituted a modification of the alleged written contract for which modification there was no consideration, and (c) that the court’s charge was erroneous. The facts necessary to an understanding of these issues follow.

Plaintiff, a contractor, was engaged in the performance of another contract for defendant at Siloam Springs, Arkansas, in the fall and winter of 1943. Early in January, 1944, defendant’s construction superintendent at Siloam Springs suggested to' plaintiff that he bid on the construction of a fifteen-inch sewer line which was to constitute a part of defendant’s Siloam Springs plant. Under date of January 18, 1944, [153] plaintiff submitted a written proposal to defendant to construct the sewer line and a water line. In that proposal plaintiff offered to perform the necessary earth trench excavation at $1.75 per cu. yard and the rock excavation at $20 per cu. yard. The above-mentioned invitation and proposal led to further negotiations in which defendant’s construction superintendent furnished plaintiff’s son with a profile of the sewer project. Plaintiff made a further written proposal, dated February 16, 1944, in which he offered to perform the earth excavation, characterized as “machine excavation,” at $2.25 per cu. yard and the rock excavation, designated as “excavation, blasted,” at $15 per cu. yard. The estimated yardage of earth excavation was stated in the February 16 proposal. No estimate of the amount of rock excavation was given. At that time the approximate amount of rock to be encountered was unknown by either party. These proposals naturally included other details incident to a construction project of that nature, but since the present controversy involves only these items, brevity suggests the exclusion of the non-controverted items from present consideration. On February 16, 1944, plaintiff’s son (who at all times represented plaintiff) met defendant’s purchasing agent and engineer at defendant’s office in St. L^uis. Plaintiff’s evidence is that at the February 16 meeting defendant’s purchasing agent was contending that the trench need not be more than 24 inches in width, while plaintiff’s son was insisting that it should be wider because 24 inches was too narrow for safety and that the machine with which the work was to be done cut a trench 42 inches in width. His evidence was to the effect that a compromise was reached on a 33-inch trench, but with no specific agreement as to the method of calculating the necessary amount of earth to be removed and compensated for in the construction of a trench of that width and the depth required (at some places as deep as sixteen feet). Because of the urgency of the need for the sewer by defendant, it was agreed that plaintiff would commence work immediately and the details of the contract be worked out later. It was also agreed that the work could and would be completed within 45 days or by April 15, 1944. Plaintiff did commence the work on February 22, 1944. Shortly thereafter defendant mailed to plaintiff a written purchase order in which the proposed unit prices, as submitted by plaintiff, were fixed at $2.25 per cu. yard for machine excavation and $15 per cu. yard for blasted excavation. With respect to the method of computing the amount of material excavated for which compensation should be made, the purchase order provided that:

“The cubic yards of all excavation for the 15-inch tile sewer line is to be figured on the basis of a trench 33 inches wide multiplied by the average depth and by the length of the trench through the cut.”

Free access — add to your briefcase to read the full text and ask questions with AI

Pet Milk Co. v. Boland, 175 F.2d 151, 1949 U.S. App. LEXIS 2348 (8th Cir. 1949).

175 F.2d 151 (Pet Milk Co. v. Boland) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Home Instead, Inc. v. David Florance
721 F.3d 494 (Eighth Circuit, 2013)
Mercantile Bank of Sikeston v. Moore
792 S.W.2d 653 (Missouri Court of Appeals, 1990)
McKeeman v. Commercial Credit Equipment Corp.
320 F. Supp. 938 (D. Nebraska, 1970)
Bommarito v. Southern Canning Co.
208 F.2d 56 (Eighth Circuit, 1953)
Pet Milk Co. v. Boland
185 F.2d 298 (Eighth Circuit, 1950)
Layne-Minnesota Co. v. City of Beresford
175 F.2d 161 (Eighth Circuit, 1949)