United States ex rel. Wilkinson v. Lange

35 F. Supp. 17, 1940 U.S. Dist. LEXIS 2454
CourtDistrict Court, D. Maryland
DecidedSeptember 28, 1940
DocketCiv. No. 773
StatusPublished
Cited by5 cases

This text of 35 F. Supp. 17 (United States ex rel. Wilkinson v. Lange) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States ex rel. Wilkinson v. Lange, 35 F. Supp. 17, 1940 U.S. Dist. LEXIS 2454 (D. Md. 1940).

Opinion

WILLIAM C. COLEMAN, District Judge.

This is a suit on a contract brought pursuant to the provisions of the Act of August 24, 1935, Chapter 642, Secs. 1-4, 49 Stat. 793, 794, 40 U.S.C.A. §§ 270a to 270d, inclusive, enacted to protect those furnishing materials or labor for construction of public buildings or works of the United States, as well as to secure the Government in connection with such construction.

The material facts, -briefly stated, are that in connection with the construction of a laundry building at the United States Naval Academy, Annapolis, Maryland, the use plaintiff, C. M. Wilkinson Company, with principal place of business in Cleveland, Ohio, hereinafter referred to as Wilkinson, contracted as a sub-contractor of the defendants, Lange Brothers, with principal place of business in Audubon, New Jersey (the other defendant, the Aetna Casualty & Surety Company, of Hartford, Connecticut, being surety on the bond of Lange Brothers), to construct and install in this building a laundry or clothes chute.

On November 11, 1938, Wilkinson made a written offer to do the work for $347, which was reduced to $325 and embodied in a formal contract entered into by the parties bearing date of March 1, 1939, by the terms of which the entire work was to be done in strict accordance with the plans and specifications of the Government architect, subject to the approval and acceptance of both Lange Brothers and the Government, and Wilkinson was to have the material completely fabricated and ready for delivery not later than May 15, 1939. It appears that Wilkinson was quite dilatory in examining the Government specifications which were made a part of the contract, and in submitting the requisite shop drawings, etc., to Lange Brothers; and that after the specifications had been fully understood, Wilkinson claimed that to comply strictly with the Government specifications, stainless steel would have to be supplied in the construction of the chute, instead of a copper-bearing metal upon which Wilkinson had' based his original estimate and entered into the contract of March 1st, and that therefore this change would greatly increase the cost.

Protracted correspondence ensued and Wilkinson remained in default with respect to performance within the time specified in the contract. Although there was [19]*19no admission on the part of Lange Brothers that Wilkinson could not reasonably have foreseen the increased cost if he had been diligent and thorough in his examination of the specifications, Lange Brothers, nevertheless, entered into a second formal agreement under date of July 24, 1939, that is, more than two months after the time when Wilkinson had obligated himself under the contract of March 1st to be ready to make delivery of the fabricated material. No delivery had been made or tendered under this first contract; nor had any payments been made thereunder.

This second contract was accepted by Wilkinson on August 18th, and in it the price agreed to be paid to Wilkinson was increased to $1,106 and time for delivery was extended to September 12th. This later contract is otherwise identical with the contract of March 1, 1939, except in a few respects which will be hereinafter referred to. No mention is made in the later contract of the earlier one. This later contract was submitted to Wilkinson by Lange Brothers under date of July 24th with a letter which, likewise, makes no mention of the earlier contract. The same printed form, supplied by Lange Brothers, was made use of in both cases.

For a number of weeks thereafter Lange Brothers continued to complain, through correspondence, of the alleged unwarranted delay on the part of Wilkinson in completing the work. Dispute arose as to precisely what was required by the Government specifications with respect to certain features of the construction. It was not until September 9th that the fabricated material left Wilkinson’s plant. At about the same time, Wilkinson billed Lange Brothers for $940 representing 85% of the second contract price. Although the contract of July 24th, as well as the contract of March 1st, provided that payments should be “on the basis of monthly payments of 90% of the value of the work performed during the preceding month, payable on or before the 20th of the month, final payment to be made thirty days after the completion and acceptance of the work, based on payments rec’d by contr. from owners”, no installment payments were made, nor do they appear to have been demanded by Wilkinson. On November 22nd, Lange Brothers wrote Wilkinson that they had so far been unable to get written approval of the work from the Government but that they expected same before the end of the month “which should enable us to dispose of same. In the meantime, we are forwarding you our check in the amount of $230.00 on account.” This payment was accepted by Wilkinson on November 27th with a voucher showing the balance still due, and with an expression of disappointment at not receiving a larger remittance and of expectation of “a further substantial payment at an early date.” On December 20th Lange Brothers wrote Wilkinson “that the building is now fully completed and expect the acceptance of same by the Government in the near future, and as soon as this is done we will dispose of the balance of our account with you.” Lange Brothers concluded by thanking Wilkinson for his “patience and cooperation.” Wilkinson continued to press Lange Brothers for payment, and on January 13, 1940, Lange Brothers sent him a check for $29.-11, stating that this was the “final payment” after taking into account the previous payment of $230 and certain minor charges in acordance with specified invoices and “the additional cost to us to complete your original contract with us dated March 1, 1939.” This last communication was acknowledged by Wilkinson by letter dated January 18th in which the remittance of $29.11 was not accepted as final payment (the check for same being held pending receipt of the balance still claimed to be due, and has never been cashed), and demand was made for the balance still claimed to be due under the second contract, namely, the price named in that contract, $1106, less the payment of $230 made on November 22nd. Lange Brothers’ refusal to pay the balance continued and the present suit was filed July 17th, last.

Plaintiff now claims $810.11, admitting a credit deduction of $65.89 on account of transportation charges in addition to the payment of $230.

The Court finds that judgment must be for the plaintiff for the sum claimed, namely, $810.11. No interest will be allowed, counsel for plaintiff having waived any claim thereto.

Both of the contracts in suit were made in Maryland because not completed until defendants had signed them in Baltimore after the plaintiff’s signature had been obtained. Therefore, Maryland law governs.

The rule in Maryland, which is the law generally, is that a promise to do, [20]*20or actually doing, no more than that which a party to a contract is already under legal obligation to do, is not a valid consideration to support the promise of the other party to the contract to pay additional compensation for such performance. In other words, a promise by one party to a subsisting contract to the opposite party to prevent a breach of the contract is without consideration. Or, stated in still another way, where the promise of the one is no more than a repetition of a subsisting legal promise, there can be no consideration for the promise of the other party and there is no warrant for inferring that the parties have voluntarily rescinded or modified their contract. Linz v. Schuck, 106 Md. 220, 67 A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fort v. Kudeviz (In re Genesis Press, Inc.)
559 B.R. 445 (D. South Carolina, 2016)
United States v. Gilman
360 F. Supp. 828 (D. Maryland, 1973)
Rabon v. State Finance Corporation
26 S.E.2d 501 (Supreme Court of South Carolina, 1943)
Schiavi v. Mayor of Baltimore
40 F. Supp. 184 (D. Maryland, 1941)
Lange v. United States
120 F.2d 886 (Fourth Circuit, 1941)

Cite This Page — Counsel Stack

Bluebook (online)
35 F. Supp. 17, 1940 U.S. Dist. LEXIS 2454, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-wilkinson-v-lange-mdd-1940.