Iron Clad Manufacturing Co. v. Stanfield

76 A. 854, 112 Md. 360, 1910 Md. LEXIS 126
CourtCourt of Appeals of Maryland
DecidedJanuary 12, 1910
StatusPublished
Cited by17 cases

This text of 76 A. 854 (Iron Clad Manufacturing Co. v. Stanfield) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Iron Clad Manufacturing Co. v. Stanfield, 76 A. 854, 112 Md. 360, 1910 Md. LEXIS 126 (Md. 1910).

Opinion

Schmucker, J.,

delivered the opinion of the Oourt.

The, appeal in this case is from a judgment of the Superior Court of Baltimore City in an action of assumpsit on a building contract. The declaration contains the common counts together with a special one on the contract. The case was tried, on an issue joined on the general issue pleas, before a *381 jury which, rendered a verdict for the plaintiff. From the judgment entered on that verdict the appeal was taken.

It appears from the record that on April 20th, 1905, the appellees, Stansfield & Son, who were builders and contractors of long' experience in Baltimore City, entered into a contract with the Iron Clad Manufacturing Company, a New York Corporation, for the erection in Baltimore of a one-story factory building 58 feet wide by 105 feet deep to be used in the manufacture of galvanized or enameled ware. The contract was not drawn in formal style but was entered into by means of written proposals and acceptances simultaneously made by the respective parties. No formal plans or specifications accompanied the contract but the several written documents of which it was composed contained a variety of provisions which taken together may be regarded as tanfamount to a set of specifications.

These specifications called for a brick building, of the dimensions1 mentioned, with a slag roof to be guaranteed against leakage and wooden floor to be constructed according to the specifications, the material to be of the best quality, of its specified kinds and the work to be done in the best workmanlike manner. The building was to be completed, in two weeks from the time of starting work on it, and was required to be satisfactory to the company for which it was erected and meet the approval of its master mechanic. The contract price for the complete building was fixed at $2,900.

After the building had been commenced the company, having acquired more land adjacent to the lot on which it was being erected, desired to have a larger factory. A supplemental contract was accordingly made between the parties, on May 9th, 1905, by written proposal and acceptance for constructing the proposed building of substantially the character originally intended but of the dimensions of 276 feet by 105 feet at an additional cost of $7,200 with the option to the company of having a cement floor at the further cost of $2,800. The company having elected to have the cement floor, the total contract price became $12,900.

*382 ■ The supplemental contract was in reality made with the Iron Clad Company of Maine which had in the meantime been formed by the persons interested in the New York corporation, but no complication results from that circumstance as both corporations admitted in open Court their joint liability for whatever was justly due under the contract.

The building was erected and taken possession of by the companies and used for the manufacture of their wares, and payments were made by them on account of its construction.. The suit was brought for an alleged balance of $5,100 of the contract price.

There is evidence in the record tending to prove that the plaintiffs had complied with all of the provisions of the several contracts on their part and also evidence of a contrary tenor. The defendant companies sought during the trial below to recoup from the contract price for alleged defects in the work and deviations from the contracts.

At the close of the case below the plaintiffs offered six prayers and the defendants offered seven. They will be set out in the report of the case by the Reporter.

The Court granted the plaintiffs’ third, fourth and fifth prayers in the form in which they were offered and their first and second prayers, after modifying them in certain respects, and rejected their sixth prayer.

The defendants’ first and seventh prayers were refused and their second, third, fourth and sixth prayers were granted as offered and their fifth prayer was granted as modified by the Court.

The appellants’ criticism of the plaintiffs’ first- prayer as granted is that it was misleading and calculated to create the impression upon the minds of the jury that a substantial compliance with the contract by the plaintiffs would entitle them to the full contract price. We do not think that the prayer is fairly open to that objection. It instructs the jury that if they find from the evidence that the plaintiffs constructed the building in substantial accordance with the terms of the contracts and that the defendants had occupied and used it *383 as a galvanizing factory and that it was reasonably satisfactory and acceptable to them and that there was a balance due on account of its construction then their verdict should be for the plaintiffs, the defendants having waived in open Court the requisite of approval of the building by their master mechanic. The prayer does not base the plaintiffs’ right of recovery upon the single ground of an erection of the build ing in substantial accordance with the terms of the contract but required the jury also to find that the defendants had accepted and used it for the purpose for which it was erected and had found it reasonably satisfactory and acceptable. The prayer does not say that the jury should allow the plaintiffs the full contract'price if they found the facts upon which it is predicated. • It goes simply to the plaintiffs’ right of recovery. It and the second prayer together make full and just provision for. proper reductions in arriving at a verdict from the contract price, for any defects in the building which the jury might find to exist.

The question of the measure of damages is dealt with in the second prayers of the plaintiffs and defendants, which in effect state the same rule upon the subject although their statements of it differ slightly in form. Both of the prayers provide for the finding by the jury of the existence of defects in the building caused by lack of workmanship or inferior material'used, or deviations from the plans and specifications not acquiesced in by the defendants. The plaintiffs’ prayer directs the jury, in arriving at their verdict, to deduct from the unpaid balance of the contract price, a sum equal to the extent to which any such defects and imperfections “have made said building less valuable to the defendants.” The defendants’ prayer directs the jury to deduct from the balance of the contract price remaining unpaid “such sum as they may find that the value of the building was lessened by reason of such defects or imperfections.” Both the plaintiffs and defendants, in these prayers stating the measure of damages, adopt the contract price as the standard and direct that the defendants be comqtensated for defects or imperfections *384 in the building by deducting from the unpaid balance of the contract price the amount that the value of the building was lessened by the defects or imperfections.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mayor of Baltimore v. Theiss
729 A.2d 965 (Court of Appeals of Maryland, 1999)
Evergreen Amusement Corp. v. Milstead
112 A.2d 901 (Court of Appeals of Maryland, 1998)
Gilbert Construction Co. v. Gross
129 A.2d 518 (Court of Appeals of Maryland, 1973)
Schneider v. Saul
168 A.2d 375 (Court of Appeals of Maryland, 1961)
Laurel Realty Co. v. Himelfarb
72 A.2d 23 (Court of Appeals of Maryland, 1950)
Takoma Park Bank v. Abbott
19 A.2d 169 (Court of Appeals of Maryland, 1941)
Mannella v. Pittsburgh
6 A.2d 70 (Supreme Court of Pennsylvania, 1939)
Parker v. Tilghman v. Morgan, Inc.
183 A. 224 (Court of Appeals of Maryland, 1936)
McClees v. Cohen
148 A. 124 (Court of Appeals of Maryland, 1930)
Murphy v. Kassis
228 N.W. 449 (North Dakota Supreme Court, 1930)
Hammaker v. Schleigh
147 A. 790 (Court of Appeals of Maryland, 1929)
Cronin v. Kimble
144 A. 698 (Court of Appeals of Maryland, 1929)
Helmer v. Geis
131 A. 34 (Court of Appeals of Maryland, 1925)
Lohmuller Building Co. v. Barrett
127 A. 482 (Court of Appeals of Maryland, 1925)
McEvoy v. Willard E. Harn Co.
98 A. 522 (Court of Appeals of Maryland, 1916)
Martin v. City of Rome
83 S.E. 872 (Court of Appeals of Georgia, 1914)

Cite This Page — Counsel Stack

Bluebook (online)
76 A. 854, 112 Md. 360, 1910 Md. LEXIS 126, Counsel Stack Legal Research, https://law.counselstack.com/opinion/iron-clad-manufacturing-co-v-stanfield-md-1910.