Schneider v. Saul

168 A.2d 375, 224 Md. 454, 1961 Md. LEXIS 514
CourtCourt of Appeals of Maryland
DecidedMarch 14, 1961
Docket[No. 172, September Term, 1960.]
StatusPublished
Cited by6 cases

This text of 168 A.2d 375 (Schneider v. Saul) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Schneider v. Saul, 168 A.2d 375, 224 Md. 454, 1961 Md. LEXIS 514 (Md. 1961).

Opinion

Horney, J.,

delivered the opinion of the Court.

When the Circuit Court for Montgomery County found for the defendant-seller (Helen McG. Saul) and entered a judgment for costs in her favor against the plaintiff-buyer (John E. Schneider) in the action brought by the buyer against the seller for damages arising out of an alleged breach of contract, the buyer appealed.

The buyer contends that the guarantee by the seller that a building permit to erect a filling station could be secured placed the responsibility for the delays in the issuance of the permit on the seller for which the buyer was entitled to damages.

The case has been submitted to us, pursuant to Maryland Rule 826 g, on a statement of the case in lieu of the pleadings and evidence (including by adoption the undisputed facts set forth in the memorandum opinion of the trial court), reading in pertinent part as follows:

“The parties * * * hereby stipulate and agree to the following statement of the case in lieu of the pleadings and evidence:
*456 1. To facilitate reference to the opinion of the court, counsel have taken the liberty of numbering consecutively the paragraphs thereof. Paragraphs 1 through 8 of the opinion state undisputed facts * * [We insert at this point a brief summary of such undisputed facts in chronological order.]
([1] On May 16, 1956, the buyer contracted with the seller to purchase a parcel of land located in Prince George’s County, on Riggs Road, near Sligo Creek Parkway, at a price of $29,950 payable in cash within thirty days. The contract contained other provisions to the effect that the buyer was to assume the obligations of performing under a lease to the Texas Company (Texaco); that the seller guaranteed that a building permit could be secured to erect a filling station on the property; that the seller was to remove the “Mack Snac” shack from the premises within thirty days after date of settlement; that the seller guaranteed that she would obtain a first deed of trust on the lot to be improved by the filling station in the amount of $42,000; that the buyer was guaranteed “reconfirmation of the lease” from Texaco; and that the seller would turn over to the buyer the contract of a builder (Mortenson) to erect a filling station in accordance with the plans of Texaco for $32,813. [2] On July 18, 1956, the application for a special exception to the zoning ordinance was granted by the County Commissioners, and “at that time a building permit could have been obtained by either the owner or the contract purchaser,” but settlement was delayed until December 17, 1956. Upon the payment of the purchase price a deed was executed and recorded together with a deed of trust from the buyer to secure the Riggs National Bank for a loan of $42,000 to be used in erecting the filling station. [3] Shortly thereafter the buyer entered into a contract with another builder (Kettler) to construct the filling station at a substantial increase in *457 cost over the prior contract, and on January 2, 1957, the substituted builder applied for a building permit, but it was refused when, on February 8, 1957, the County Commissioners, on their own motion revoked the special exception previously granted. [4] When the buyer learned that the special exception had been revoked he employed an attorney to try to secure its reinstatement and the seller did likewise. [5] On June 11, 1957, mainly through the efforts of the buyer’s attorney, the special exception was reinstated, the effect of which was to restore the right of the buyer to erect the filling station upon obtaining a building permit. [6] On June 28, 1957, the buyer entered into a new contract with the builder for the construction of the filling station at another increase in price over the previous contract, but before a building permit was obtained, the owner of the adjoining Esso station sued the County Commissioners, the building inspector, the seller and the buyer on a bill for an injunction to enjoin the issuance of the building permit and the erection of the filling station for the reason that the granting of the special exception was illegal in that it violated a set-back regulation. On a motion by the buyer for a summary judgment, the suit was dismissed on October 1, 1957. [7] However, when the application for a building permit was renewed, the State Roads Commission, on October 24, 1957, disapproved the issuance of the permit and the building plans on account of the layout of the entrances and exits. The negotiations with the Commission, which were begun promptly, continued until February 5, 1958, at which time, after modifications of the entrance and exit layouts, the erection of the filling station was approved by the Commission. [8] On April 8, 1958, the building permit was finally issued. Prior thereto the buyer had renegotiated a new lease with Texaco at an increased rental and had executed a final con *458 tract with the builder. Construction of the filling station was begun on July 10, 1958, and was completed on January 1, 1959. In the meantime the loan from the Bank had been increased to $55,000. Within a short time after the building was completed, the plaintiff sold the property.)
“The opinion sets forth how the questions raised at [the] trial arose and the court’s decision thereon. The principal question raised is stated by the court in paragraph 11 as follows:
‘While the plaintiff alleges numerous breaches of the agreement, his principal complaint is that he was “to be guaranteed by the seller that a building permit can be secured for erecting a Texaco gasoline station,” and that although the contract had been signed on May 15, 1956, he was unable to obtain the building permit until April 8, 1958, and then only through the efforts of his attorney.’
“In paragraph 16 of the opinion, the court rendered its decision of this question adverse to the plaintiff, and it is this adverse decision which is the basis of plaintiff’s appeal.”
“2. The following testimony hereinafter summarized was admitted into evidence at [the] trial:
“The [buyer], in testifying as to the occurrences at the time the contract was signed, testified to those matters set forth by the court in paragraphs 10 and 11 of the opinion—[to the effect that when he entered into the agreement he was induced to do so because he understood that the purchase of the property was a ‘package deal’ to secure a building permit immediately and a loan to erect the filling station already under contract to be occupied by Texaco under its lease of the premises, that is, that he thought he was ‘all ready to go’; and that the delays which arose whereby the filling station was not completed until January 1, 1959, constituted a substantial breach of the contract by the seller, and as *459

Free access — add to your briefcase to read the full text and ask questions with AI

Related

AirFacts, Inc. v. Diego De Amezaga
30 F.4th 359 (Fourth Circuit, 2022)
U.K. Construction & Management, LLC v. Gore
20 A.3d 163 (Court of Special Appeals of Maryland, 2011)
(1996)
81 Op. Att'y Gen. 219 (Maryland Attorney General Reports, 1996)
C. W. Blomquist & Co. v. Capital Area Realty Investors Corp.
311 A.2d 787 (Court of Appeals of Maryland, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
168 A.2d 375, 224 Md. 454, 1961 Md. LEXIS 514, Counsel Stack Legal Research, https://law.counselstack.com/opinion/schneider-v-saul-md-1961.