U.K. Construction & Management, LLC v. Gore

20 A.3d 163, 199 Md. App. 81, 2011 Md. App. LEXIS 65
CourtCourt of Special Appeals of Maryland
DecidedMay 26, 2011
Docket2824, September Term 2009
StatusPublished
Cited by3 cases

This text of 20 A.3d 163 (U.K. Construction & Management, LLC v. Gore) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
U.K. Construction & Management, LLC v. Gore, 20 A.3d 163, 199 Md. App. 81, 2011 Md. App. LEXIS 65 (Md. Ct. App. 2011).

Opinion

WRIGHT, J.

Appellant, U.K. Construction & Management, LLC (“U.K. Construction”), entered into a home improvement contract (“Contract”) with appellee, Patricia Gore, on August 10, 2007, for the renovation of a property owned by Gore at 2200 Brookfield Road, Baltimore, Maryland. Gore refused to pay U.K. Construction the final installment payment, alleging that several items on the punch list still needed attention. In late 2008, after court-ordered arbitration, the arbitrator found in favor of U.K. Construction.

On September 1, 2009, Gore filed a petition to compel arbitration in the Circuit Court for Baltimore City, again alleging defective work by U.K. Construction. U.K. Construction maintained that the issues had already been addressed in the prior arbitration, that the arbitration award constituted a final judgment, and that it was contrary to the principles of res judicata to re-litigate matters already covered. The court issued an order on November 25, 2009, denying Gore’s petition and granting U.K. Construction’s motion for sanctions. On December 4, 2009, Gore filed a motion for reconsideration. The court scheduled a motions hearing and subsequently reversed the November 25th ruling, instead granting Gore’s petition to compel arbitration.

U.K. Construction noted a timely appeal to this Court, asking us to determine whether the circuit court erred in granting Gore’s petition. 1 For the reasons that follow, we reverse the court’s judgment.

*84 Statement of Facts

On August 10, 2007, the parties entered into a contract for the renovation of a property owned by Gore at 2200 Brookfield Road, Baltimore, Maryland. U.K. Construction is a general contractor licensed in the State of Maryland to perform home improvement work. Gore obtained a renovation loan in connection with the Contract from SunTrust Bank, after Sun-Trust Bank had approved U.K. Construction as the general contractor.

The Contract stipulated that U.K. Construction was to be paid a total sum of $202,800.00 in installment payments according to a draw schedule. There were five scheduled draws. The Contract provided for certain guarantees of materials and workmanship, including that provided by subcontractors, and included a warranty for one year from the date of final acceptance of the work. The job proceeded without incident and four of the five scheduled draws were submitted and paid. Gore refused to pay the final installment totaling $40,720.00, claiming that several punch list items were deficient. Before U.K. Construction was given the opportunity to take action on the items, Gore locked them out and hired other contractors. Gore then obtained a certificate of occupancy from the city of Baltimore to certify that the work had been completed, refinanced the property with another mortgage lender, and paid off SunTrust Bank. Gore never paid U.K. Construction the final installment.

Paragraph 12 of the Contract required that any and all disputes be settled via binding arbitration and stated that the *85 decision of the arbitrator would be final and binding on the parties. 2 On March 27, 2008, U.K. Construction filed a petition to compel arbitration and to appoint an arbitrator, in the circuit court. The court granted U.K. Construction’s request, and on August 18, 2008, it ordered that Robert L. Ferguson, Jr. Esq. be “appointed to adjudicate the substantive issues” in this matter (“prior arbitration”).

On October 22, 2008, the parties attended the arbitration hearing, which lasted approximately eight hours. 3 After hearing all the evidence and arguments from both attorneys, Ferguson ruled in favor of U.K. Construction and issued a detailed opinion, dated November 25, 2008, and a supplemental opinion dated December 12, 2008. The arbitrator considered all outstanding rights and obligations under the Contract and found in favor of U.K. Construction, as follows:

I regard [Gore’s] conduct, changing the lock, not cooperating with Plaintiff for a final inspection of the Property by the City, obtaining an occupancy permit on her own and obtaining a mortgage loan to pay off the construction loan without paying Plaintiff, as a repudiation of the contract.

The arbitrator also found that despite Gore having introduced evidence that she incurred expenses in excess of $85,000 while trying to fix U.K. Construction’s work, 4 those repairs “should have been pursued as warranty work.”

Following the arbitration award, Gore did not exercise her right to vacate or modify the award. 5 On December 29, 2008, *86 after Gore failed to make any payments under the award, U.K. Construction filed a petition to confirm arbitration award as a *87 judgment with the circuit court. 6 On February 2, 2009, the court dismissed the petition with prejudice. Gore subsequently entered into a promissory note with U.K. Construction to pay off all monies due under the arbitration award via installment payments.

On February 13, 2009, approximately two months after receiving an unfavorable result in the prior arbitration, Gore filed a complaint against U.K. Construction with the Maryland Home Improvement Commission (“MHIC”), alleging the same defective workmanship that had been heard during the arbitration. U.K. Construction informed MHIC that the matter had already been adjudicated via arbitration. MHIC took no action.

On September 1, 2009, Gore filed a petition to compel arbitration in the circuit court, alleging that “much of the work performed by [U.K. Construction] on the property was done in an unworkmanlike manner and is in breach of the express and implied warranties of the [Contract]” 7 . On September 24, 2009, U.K. Construction filed a response in opposition to appellee’s petition to compel arbitration, arguing that the issues raised in Gore’s petition had already been addressed in the prior arbitration and it was therefore contrary to the *88 principle of res judicata to re-litigate those issues. As such, U.K. Construction concluded that “Ms. Gore’s Petition to Compel Arbitration is [merely] an attempt to claw back some of the money she was ordered to pay [U.K. Construction] at the earlier arbitration hearing. Ms. Gore’s actions are in bad faith, a waste of this court’s time and resources, as well as incurring unnecessary legal fees to [U.K. Construction].”

On September 24, 2009, U.K. Construction also filed a motion for sanctions, reiterating its position that Gore’s petition was filed “in bad faith and without substantial justification.”

On November 25, 2009, the court denied Gore’s petition and granted U.K. Construction’s motion for sanctions. On December 4, 2009, Gore filed a motion for reconsideration and requested a hearing.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

FutureCare NorthPoint, LLC v. Peeler
143 A.3d 191 (Court of Special Appeals of Maryland, 2016)
FutureCare Northpoint v. Peeler
Court of Special Appeals of Maryland, 2016

Cite This Page — Counsel Stack

Bluebook (online)
20 A.3d 163, 199 Md. App. 81, 2011 Md. App. LEXIS 65, Counsel Stack Legal Research, https://law.counselstack.com/opinion/uk-construction-management-llc-v-gore-mdctspecapp-2011.