Mannella v. Pittsburgh

6 A.2d 70, 334 Pa. 396, 1939 Pa. LEXIS 649
CourtSupreme Court of Pennsylvania
DecidedMarch 29, 1939
DocketAppeal, 80
StatusPublished
Cited by22 cases

This text of 6 A.2d 70 (Mannella v. Pittsburgh) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mannella v. Pittsburgh, 6 A.2d 70, 334 Pa. 396, 1939 Pa. LEXIS 649 (Pa. 1939).

Opinion

Opinion by

Mr. Justice Stern,

Mike Mannella, plaintiff, entered into a written contract with the City of Pittsburgh, defendant, to lay a 36-inch waterpipe servicing the South Side district. To the extent of about 800 feet the line was to rest in a trench at the bottom of, and crossing, the Monongahela River. The work proceeded satisfactorily until the laying of the pipe under the river had been finished. In order to permit of an inspection the pipe was then partially drained by a siphoning operation, during the course of which it floated, buckled at the flanges, and broke. This made necessary a repairing and relaying job, at an expense to plaintiff, as alleged by him, of $28,098.61, to recover which (together with a small item for other work not here involved) the present action was brought. The jury returned a verdict in favor of plaintiff in the amount of his claim, and judgment was entered thereon.

The principal issue at the trial was whether plaintiff or defendant was the party legally responsible for the cost of repairing and relaying the damaged pipe. This depended partly upon a factual controversy, which was resolved by the verdict of the jury, and partly upon the proper interpretation to be given to certain clauses of the agreement.

*398 Originally the contract provided that after the pipe had been laid and connected it should be weighted by placing concrete around it, but during the course of the work plaintiff suggested to defendant the elimination of this requirement and the allowance in return of a credit on the contract price, to which defendant agreed. In his letter making the offer plaintiff wrote: “I propose to backfill the trench over the pipe before pumping out the line for inspection and will re-excavate if necessary to repair any leaks that the final test may reveal. It is understood that this omission, if allowed, will in no way affect my responsibility for the line nor my obligation to pump same out for inspection.”

It was stipulated in the contract that each “laying length” of the pipe, before being placed, should be tested with water to a certain specified pressure, and a water-pressure test should again be made after the pipe had been laid and the field joints made; if excessive leakage appeared defendant reserved the right to require that the pipe should be given an air-pressure test. The water-pressure tests were made, including one after the laying of the pipe had been completed; they showed no appreciable leakage and the city engineers were satisfied with the results. Some air tests were' also made during the progress of the work, and it was demonstrated that the pipe was water-tight. In accordance with a provision of the contract a cofferdam was constructed at the north end where the pipe emerged from the river and from where it was to rise at a vertical angle for connection with the city water system.

When this point in the work was reached certain conversations occurred between the parties which gave rise to the present controversy. Since a jury has placed its stamp of approval upon plaintiff’s version, although it was vigorously contradicted by defendant’s witnesses, the facts as claimed by plaintiff must here be accepted as true. Plaintiff says that he was told by the inspector on the job “to pump the line,” to which he replied, “If *399 you do that the line will float.” Subsequently he was instructed by the managing engineer of the Bureau of Water that he should “go ahead and take 14 to 16 inches of water out of that line because we got it all calculated to do it all right”; plaintiff answered that he did not “think it was a good move to make,” that he considered it dangerous, and that “if I pumped that line out, she will float.” One of the city engineers who had charge of the construction work said to him: “You take 14 inches of water out of that line. You are safe. We got him all calculated. Go, take it out.” Later, another of the field engineers gave orders, in the absence of plaintiff, to plaintiff’s construction superintendent, either to pump the line out or not proceed any further with the work, to which the superintendent strongly demurred, but he referred the matter to plaintiff, who told him that if they insisted on it he should “go ahead.” It is reasonably clear from the testimony that this order for draining the pipe to the extent of 14 inches was ill-advised, and that the direct result of its execution was the floating and breaking of the pipe.

We have here, then, a situation comprising the following circumstances: a contractor is ordered by duly authorized representatives of the owner — in this case the City of Pittsburgh — to do a certain act in . connection with the work under construction; the propriety of the order is a matter of expert judgment; the contractor believes that it involves danger but he is overridden by the city’s technical engineers; although he has an opinion on the subject he has no absolute knowledge that the operation ordered will prove disastrous; he bows to force majéure in the shape of peremptory orders given by the city; by the terms of the contract he is required to comply with the orders he receives, there being a provision that “the orders of the Director shall be obeyed by the party of the second part [the contractor] and by all persons employed on the work,” the “Director” being defined as “the Director of the Department of Public Works of the City of Pittsburgh, *400 Pa. or his Managing Engineer, Assistants and Inspectors, limited by the special duties entrusted to them.” It is established that ordinarily a contractor is not responsible for defects caused by acts or orders of the owner during the progress of the work: Hogg v. Jackson & Sharp Co., (Md.) 26 A. 869; Iron Clad Mfg. Co. v. Thomas B. Stanfield & Son, 112 Md. 360, 76 A. 854; Siebert v. Leonard, 17 Minn. 433; Murphy v. Kassis, 59 N. Dak. 35, 39, 228 N. W. 449, 450; Bryant v. Stilwell, 24 Pa. 314, 319; Rohrman v. Steese, 9 Phila. Rep. 185. 1

The present controversy thus resolves itself into the question whether there is in this particular contract any assumption of liability by plaintiff which takes the case out of the general rule. Defendant contends that it had the right to demand the dewatering of the pipe when it did, and that plaintiff was bound to repair any resulting defects, and in support of this position points out a clause in the contract which provided that “the cofferdam shall be made reasonably tight and the contractor shall keep the water pumped out from same so that the pipe can be laid, joined, tested and inspected in the dry,” another clause that, “before emptying the pipe or making an air test, the contractor shall make such further provisions as he deems necessary against damage from flotation or any other cause during the test; the con *401

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hammel v. Christian
610 A.2d 979 (Superior Court of Pennsylvania, 1992)
Thomas M. Durkin & Sons, Inc. v. Nether Providence Township School Authority
460 A.2d 800 (Superior Court of Pennsylvania, 1983)
Mayor of Columbus v. Clark-Dietz & Associates-Engineers, Inc.
550 F. Supp. 610 (N.D. Mississippi, 1982)
Rochester MacHine Corp. v. Mulach Steel Corp.
449 A.2d 1366 (Supreme Court of Pennsylvania, 1982)
Rochester MacHine Corp. v. Mulach Steel Corp.
430 A.2d 280 (Superior Court of Pennsylvania, 1981)
Environmental Utilities Corp. v. Lancaster Area Sewer Authority
453 F. Supp. 1260 (E.D. Pennsylvania, 1978)
Appel Media, Inc. v. Clarion State College
327 A.2d 420 (Commonwealth Court of Pennsylvania, 1974)
Brown Estate
63 Pa. D. & C.2d 524 (Montgomery County Court of Common Pleas, 1973)
Sandmann v. Old Delancey Building & Loan Ass'n
135 A.2d 819 (Superior Court of Pennsylvania, 1957)
Turkish State Railways Administration v. Vulcan Iron Works
153 F. Supp. 616 (M.D. Pennsylvania, 1957)
Byson v. City of Los Angeles
308 P.2d 765 (California Court of Appeal, 1957)
Jones v. STEINBERG
115 A.2d 803 (Superior Court of Pennsylvania, 1955)
Philadelphia Housing Authority v. Turner Construction Co.
23 A.2d 426 (Supreme Court of Pennsylvania, 1941)
Sandy Hites Co. v. State Highway Commission
149 S.W.2d 828 (Supreme Court of Missouri, 1941)
Massiah v. Hood
10 A.2d 79 (Superior Court of Pennsylvania, 1939)

Cite This Page — Counsel Stack

Bluebook (online)
6 A.2d 70, 334 Pa. 396, 1939 Pa. LEXIS 649, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mannella-v-pittsburgh-pa-1939.