Tate-Jones & Co. v. Union Electric Steel Co.

126 A. 813, 281 Pa. 448, 1924 Pa. LEXIS 641
CourtSupreme Court of Pennsylvania
DecidedOctober 13, 1924
DocketAppeal, 80
StatusPublished
Cited by16 cases

This text of 126 A. 813 (Tate-Jones & Co. v. Union Electric Steel Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tate-Jones & Co. v. Union Electric Steel Co., 126 A. 813, 281 Pa. 448, 1924 Pa. LEXIS 641 (Pa. 1924).

Opinion

Opinion by

Mr. Justice Sadler,

On February 28,1920, Tate-Jones & Co., Inc., plaintiff, proposed to sell to defendant, for a stipulated price, six furnaces to be used for heating and annealing steel, and its offer was accepted. The seller guaranteed the equipment “to perform the work for which it was intended,” *452 and that the plant would “maintain uniform and controllable temperatures in working chamber from 1800 to 2300 degrees Fahr., for efficiently heating billets and ingots for forging, of sizes adaptable to the heating chamber of the furnace when properly handled and operated under the conditions specified.” The latter provided that oil should be used at a pressure of 25 to 30 pounds per square inch, and compressed air or steam at 20 to 25 pounds, to secure the results intended, except when oils of a standard heavier than that named were employed, in which case the pressure was to be increased and the oil heated. It was set forth that there were no understandings or agreements other than those contained in the written contract.

The work contemplated was completed in January, 1921. Payment was not made as agreed upon, and, in April following, plaintiff filed a mechanic’s lien to secure the balance due. Later, on December 1st, an agreement was entered into between the parties, recognizing the validity of the lien, and declaring it not subject to “set-offs, counterclaims or defenses.” In consideration of this acknowledgment, the plaintiff extended the time of settlement by permitting payment in three installments, covering eighteen months, with the provision that all should become due if a default occurred as to any. Since the furnaces had not as yet been put in operation by the defendant, it was further provided that plaintiff should “at its own expense, do all such work and furnish all such materials as will be necessary to make them comply with the contract, and will at all times make good its guaranty contained in said contract, which guaranty shall remain in full force and effect and be unaffected by anything herein contained.”

The operation of the plant, — which had been in place for nearly a year, though not in actual service, apparently because of lack of business demand, — commenced in January of 1922. With the exception of one furnace, all were made use of until the summer following, when *453 two were removed, and the others are still in place and at least in part employed in the buyer’s business. On July 1st, the first installment, as fixed by the supplementary agreement, became due, and remained unpaid. Ten days later defendant gave notice of the discovery of numerous defects in workmanship and design, and of an inability to secure uniform and controllable temperatures as promised. It was demanded that the necessary alterations be made, or the furnaces taken out and removed. A scire facias was then issued on the mechanic’s lien. The affidavit of defense filed denied liability because of the alleged breach of the agreement to make good the guaranty, as set forth in the original contract, setting up, in addition, certain oral representations by the seller as to the amount of work possible to be economically performed if proper operation was had, and claiming damages for loss sustained. On the trial of the issue, the learned court below submitted to the jury the question whether there had been a breach proven, and, if so, what loss, if any, had been suffered. A verdict was rendered for plaintiff in a sum less than that sought to be recovered. Judgment n. o. v. was later entered, on motion of the plaintiff, for the full amount of the claim, and that for a new trial, presented by defendant, overruled. This appeal followed.

It will be remembered that the specifications, — a part of the contract (9 C. J. 737), — were prepared by the plaintiff, submitted to defendant, and the offer accepted. The builder was therefore bound to strictly comply with the provisions set forth in constructing the furnaces, but, if this was done, he satisfied his obligation, and was not liable for results obtained, except as expressly or impliedly warranted: 9 C. J. 746; Filbert v. Phila., 181 Pa. 530; Harlow & Co. v. Homestead Boro., 194 Pa. 57; Wiggins v. Columbian Fire Proofing Co., 227 Pa. 511. In discussing the case the court below said, and the statement is not challenged here: “The defendant gave no evidence tending to show that the furnaces *454 were not built in accordance with the plans and specifications, but did undertake to show a breach of warranties contained in said contract.” Appellant insists that proof of certain defects in building showed the plant to be inefficient, but the question here is whether it would do the work as agreed, under the circumstances expressly defined. And within this complaint comes that directed to construction of the brick arches over the doorway, which, it is insisted, fell an excessive number of times, requiring repairs. It is to be noted that there was no evidence that they were not built according to the accepted plans, and, when broken, and plaintiff notified, the expenses incident to renewal were paid by it.

It further contends that, the designs having been prepared by the plaintiff, there is an additional implied warranty that the work shall be done so that upon completion it may be used satisfactorily and economically, but this is not what the contract provided. In plain words, it fixed the obligation of the seller, and also declared no other understanding existed than those set forth in writing, a stipulation binding on the purchaser: Ridgeway Dynamo & Engineer Co. v. Pa. Cement Co., 221 Pa. 160; Gross v. Exeter Machine Works, 277 Pa. 363. There was no proof of any contemporaneous parol agreement, broadening the responsibility of the plaintiff, which induced defendant to accept the proposal. We are not, therefore, concerned with alleged defects in design and workmanship, but only with the question as to whether the terms of the guaranty were complied with. What has been said disposes of the ninth assignment of error adversely to appellant.

Plaintiff guaranteed, — or warranted, for the effect is the same (28 C. J. 894), — that the furnaces would supply certain temperatures if properly operated, and fixed the pressure of oil and steam to be employed to reach this end. Defendant permitted the plant to be installed and made use of it, — in fact still operates some of the units. It matters not whether, in commenting on this *455 conduct as constituting an acceptance, the lower court, in referring to the legal result of so doing, called attention (the fourth assignment of error) to the rule to be applied in such cases as defined by the Sales Act. If that legislation does not apply to personalty, which has become attached to realty, — and this question it is not necessary to decide, — the common law principle, which brings us to the same conclusion, does. The work was completed in 1921; the agreement to pay, subject to the right to reimbursement, if a breach subsequently appeared, was made many months later; and a final refusal to accept not expressed until after nearly seven months of actual operation. Clearly, the only redress remaining to the defendant, under the circumstances, was to secure an award for a loss which it sustained, if a default on the part of plaintiff could be shown.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Moss Theatres, Inc. v. Turner
616 P.2d 1127 (New Mexico Court of Appeals, 1980)
Book Metals Corp. v. Sitkin Smelting & Refining, Inc.
385 A.2d 504 (Superior Court of Pennsylvania, 1978)
Turkish State Railways Administration v. Vulcan Iron Works
153 F. Supp. 616 (M.D. Pennsylvania, 1957)
California Fruit Exchange v. Henry
89 F. Supp. 580 (W.D. Pennsylvania, 1950)
Shipley v. Pittsburgh & L. E. R. Co.
83 F. Supp. 722 (W.D. Pennsylvania, 1949)
Commonwealth v. Moyer
53 A.2d 736 (Supreme Court of Pennsylvania, 1947)
Nicholson v. Feagley
14 A.2d 122 (Supreme Court of Pennsylvania, 1940)
Mannella v. Pittsburgh
6 A.2d 70 (Supreme Court of Pennsylvania, 1939)
Canuso v. Philadelphia
192 A. 133 (Supreme Court of Pennsylvania, 1937)
Fisher Et Ux. v. Allegheny County
188 A. 196 (Supreme Court of Pennsylvania, 1936)
Parker v. Tilghman v. Morgan, Inc.
183 A. 224 (Court of Appeals of Maryland, 1936)
Carroll v. Hannan
137 A. 127 (Supreme Court of Pennsylvania, 1927)
Electric City Motors, Inc. v. Ross
87 Pa. Super. 327 (Superior Court of Pennsylvania, 1925)
Hauer v. Martin
131 A. 187 (Supreme Court of Pennsylvania, 1925)
Duncan v. Pittsburgh-Florida Fruit Growers Ass'n
128 A. 441 (Supreme Court of Pennsylvania, 1925)

Cite This Page — Counsel Stack

Bluebook (online)
126 A. 813, 281 Pa. 448, 1924 Pa. LEXIS 641, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tate-jones-co-v-union-electric-steel-co-pa-1924.