Gross v. Exeter Machine Works, Inc.

121 A. 195, 277 Pa. 363, 1923 Pa. LEXIS 422
CourtSupreme Court of Pennsylvania
DecidedApril 30, 1923
DocketAppeals, Nos. 153 and 281
StatusPublished
Cited by42 cases

This text of 121 A. 195 (Gross v. Exeter Machine Works, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gross v. Exeter Machine Works, Inc., 121 A. 195, 277 Pa. 363, 1923 Pa. LEXIS 422 (Pa. 1923).

Opinion

Opinion by

Mr. Justice Walling,

On December 27,1919, a written contract was executed between Max dross, the plaintiff, and Exeter Machine Works, Inc., located at West Pittston, Pa., by which the latter undertook to make and deliver to the former five hundred complete silk throwing machines, or a total of fifty thousand spindles, for a consideration therein stated. The first two machines were to be delivered on or before February 15, 1920, and at least two machines each and every day thereafter until the contract was filled. Plaintiff advanced the ten thousand dollars as the contract stipulated, but none of the machines was made or delivered and because of such failure he wrote defendant, on May 19, 1920, rescinding the contract and then brought this suit for the ten thousand dollars advanced and also for a like sum claimed as liquidated damages. Defendant filed an affidavit of defense and later an amended affidavit setting up divers matters in defense, and also a counterclaim, to all of which plaintiff replied, raising legal questions only, as provided by the Practice Act of 1915. Thereupon the trial court entered judgment for the plaintiff for the ten thousand dollars advanced, with interest thereon, refused judgment for the ten thousand dollars claimed as liquidated damages and dismissed defendant’s counterclaim as insufficient in law; from which each side has appealed and we will here dispose of both.

Defendant sets up an alleged contemporaneous parol agreement, vitally changing the written contract, on the faith of which it executed the latter. The written contract provides that, “It is understood and agreed that all previous communications, either verbal or written, with reference to the subject-matter of this agreement, are hereby withdrawn and annulled, and this contract shall be modified only by written agreement between the parties hereto.” In view of which, the trial court properly rejected the alleged parol modification. Where the parties, as here, have deliberately put their agree[367]*367ment in writing stipulating therein that it contains the entire contract and shall be modified only by the parties’ written agreement, such stipulation forms a material part of the contract and is enforceable as such: Dynamo & Engine Co. v. Cement Co., 221 Pa. 160, 165; Phila. and Gulf S. S. Co. v. Pechin, 61 Pa. Superior Ct. 401; Colt Company v. Evans, 74 Pa. Superior Ct. 73; Holcomb & Hoke Mfg. Co. v. Gamba, 80 Pa. Superior Ct. 191; Oxweld Acetylene Co. v. Hastings, 71 Pa. Superior Ct. 178; Tranter Mfg. Co. v. Blaney, 61 Pa. Superior Ct. 379. Parties having taken the precaution to put their agreement in writing may further safeguard their rights by such a stipulation as above quoted, otherwise a contracting party is powerless to protect himself against parol modifications of his solemn contract.

The contract states, “It is understood that the date of the delivery of the above described machinery, whether expressed or implied, is subject to delays caused by common carriers or rolling mills in delivering to us the materials out of which said machinery is to be made, and subject to delays occasioned to us by reason of strikes, labor troubles, fires, accidents at our shops or other causes beyond our control,” and thereunder defendant seeks to escape the consequences of its failure to perform. But the affidavit of defense fails to aver sufficient facts to enable it to do so. An affidavit of defense must state the facts specifically (Frick & Lindsay Co. v. Kent & Kervin, 265 Pa. 264; Little v. Thropp, 245 Pa. 539; Gowan v. Boney, 74 Pa. Superior Ct. 123; Hallowell v. Paige, 46 Pa. Superior Ct. 108; Berko v. Kemper Construction Co., 65 Pa. Superior Ct. 589), and mere general averments are insufficient: Franklin Sugar R. Co. v. Hanscom Bros., 273 Pa. 98; Com. v. Bader et al., 271 Pa. 308; Wright v. General Carbonic Co., 271 Pa. 332; Iron Trade Products Co. v. Wilkoff Co., 272 Pa. 172. There is no averment as to what common carrier or what rolling mill failed to deliver the necessary material, or of what material, if any, defendant was de[368]*368prived. True, a railroad strike and one in defendant’s factory are averred as beginning in April 1920, but that was two months after defendant had breached the contract and of course could not excuse it: see Wigton, Receiver, v. Climax Coal Co., 270 Pa. 420. The affidavit avers generally extraordinarily severe weather conditions during the first quarter of 1920, causing delay in transportation and its affiant expresses the belief that defendant was substantially hindered thereby, but fails to state what transportation companies were blockaded by storms, or for how long, or of what material defendant was thereby deprived. Moreover, he who undertakes to perform a contract during the winter months in this northern country cannot be excused because of general severity of the weather: Texter v. Wachs, 73 Pa. Superior Ct. 19. The affidavit also avers that, owing to the abnormal demand for rolling mill products, defendant was unable to obtain the required material “within any reasonable bounds of effort or expense”; but that is unavailing; mere hardship or difficulty is no excuse for failure to perform a contract: Com. v. Neff et al., 271 Pa. 312; Corona C. & C. Co. v. Dickinson, 261 Pa. 589.

Defendant’s counterclaim consists of the lump sum of $39,925.61, claimed to have been expended by it, on the faith of the contract, for labor and material and $50,000 as its anticipated profits. As the trial court rightly held the contract was breached by defendant, its counterclaim, based on the theory that plaintiff breached the contract, falls. Furthermore, the counterclaim on its face is fatally defective in that it fails to state when, to whom, or for what the items comprising the lump sum were paid, or any sufficient facts to justify the claim for anticipated profits. It would be worthless as a plaintiff’s statement of claim and is equally so as a counterclaim, which must be stated with the same certainty: O’Neil v. Burnett, 263 Pa. 216, and see Frick & Lindsay v. Kent & Kervin, supra. It follows judgment was rightly entered [369]*369for the plaintiff on the questions of law raised as to the counterclaim.

The contract contained a further stipulation as follows, “In the event the Exeter Machine Works, Inc., fail or neglect to comply with the terms and conditions of this contract, then it is agreed between the parties hereto, that the stipulated damages shall be fixed in the sum of ten thousand ($10,000) dollars, that being agreed upon as the amount of damages which the said Max Gross would be entitled to as a result of the failure on the part of the said Exeter Machine Works, Inc., to carry out the terms of their contract; and also agree in addition thereto to return to the said Max Gross, the said sum of ten thousand ($10,000) dollars, which has been paid to the Exeter Machine Works, Inc., as an advanced payment.” This, plaintiff contends, entitles him to the stipulated ten thousand dollars as liquidated damages; but the trial judge properly held otherwise. Whether the parties have denominated the sum specified in any given case a penalty or liquidated damages is of little moment in determining its real character: Kunkel & Jordan v. Wherry, 189 Pa. 198.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Traylor v. Grafton
332 A.2d 651 (Court of Appeals of Maryland, 1975)
Wills v. Shockley
157 A.2d 252 (Superior Court of Delaware, 1960)
Raymond A. McPherson, Inc. v. Veneziale
18 Pa. D. & C.2d 757 (Bucks County Court of Common Pleas, 1959)
Commonwealth v. Musser Forests, Inc.
146 A.2d 714 (Supreme Court of Pennsylvania, 1958)
Wissahickon Realty Corp. v. Boyle
122 A.2d 720 (Supreme Court of Pennsylvania, 1956)
Smiler v. Toll
94 A.2d 764 (Supreme Court of Pennsylvania, 1953)
Heller v. First National Bank & Trust Co. of Newtown
38 Pa. D. & C. 79 (Bucks County Court of Common Pleas, 1940)
Whiteside v. Rocky Mountain Fuel Co.
101 F.2d 765 (Tenth Circuit, 1938)
Dahath Electric Co. v. Suburban Electric Development Co.
2 A.2d 765 (Supreme Court of Pennsylvania, 1938)
Burns Trading Co. v. Welborn
81 F.2d 691 (Tenth Circuit, 1936)
Gehret v. Mitten Bank Securities Corp.
182 A. 125 (Superior Court of Pennsylvania, 1935)
Lloyd & Elliott, Inc. v. Lang
180 A. 71 (Superior Court of Pennsylvania, 1935)
Badenhausen Corp. v. Lang Co.
170 A. 294 (Supreme Court of Pennsylvania, 1933)
Sentry Safety Control Corp. v. Jaybee Amusement Co.
169 A. 419 (Superior Court of Pennsylvania, 1933)
Kittleberger & Evans v. Home Builders Co.
164 A. 821 (Superior Court of Pennsylvania, 1932)
East Coast Fi. Corp. v. Linck
159 A. 468 (Superior Court of Pennsylvania, 1931)
Trust Co. of Glen Rock v. Shrewsbury Furniture & Mfg. Co.
158 A. 641 (Superior Court of Pennsylvania, 1931)
Roth Downs Manufacturing Co. v. Profy
16 Pa. D. & C. 138 (Bucks County Court of Common Pleas, 1930)
80th Div. Vet. Assn. v. Johnson
159 A. 467 (Superior Court of Pennsylvania, 1930)
Metropolitan Refining Co. v. Beaver Valley Mill Supply Co.
14 Pa. D. & C. 454 (Beaver County Court of Common Pleas, 1930)

Cite This Page — Counsel Stack

Bluebook (online)
121 A. 195, 277 Pa. 363, 1923 Pa. LEXIS 422, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gross-v-exeter-machine-works-inc-pa-1923.