Philadelphia Housing Authority v. Turner Construction Co.

23 A.2d 426, 343 Pa. 512, 1942 Pa. LEXIS 306
CourtSupreme Court of Pennsylvania
DecidedDecember 3, 1941
DocketAppeal, 298
StatusPublished
Cited by38 cases

This text of 23 A.2d 426 (Philadelphia Housing Authority v. Turner Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Philadelphia Housing Authority v. Turner Construction Co., 23 A.2d 426, 343 Pa. 512, 1942 Pa. LEXIS 306 (Pa. 1941).

Opinion

Opinion by

Mr. Chief Justice Schaffer,

The court below set aside an award of arbitrators, amounting to $20,709.22, in favor of Turner Construction Company and against The Philadelphia Housing Authority, and entered judgment in favor of the latter. From this action Turner Construction Company appeals.

The proceeding in the court below was begun by a petition by the Housing Authority for a rule to show *514 cause on the Construction Company why an order should not be made invalidating the award, to which an answer was filed by the Construction Company asserting validity.

The controversy grows out of a contract between the parties for the building of 1,000 houses. While the Construction Company was the general contractor, the matter in dispute concerns only that part of the undertaking covering the painting of the interior of the houses. As to this, the contract says: “Paint for Interior Concrete and Interior Masonry Surfaces: (a) Cement-water Paint shall be a hydraulic base paint, delivered in powder form, ready for use, with the addition of water only. The powder shall consist of not less than 85% Portland cement, hydrated lime, hygroscopic salt, a small amount of water repellant metallic soap and small amounts of other agents or chemicals to impart workability. Small percentage of titanium oxide may be included. Limeproof pigment colors shall be added at the factory to provide the desired color tone, but the amount of color used shall not be in excess of 4 percent by weight. The paint shall be suitable for brush application to clean unpainted porous surfaces (such as concrete or masonry) and when applied shall flow evenly and cover solidly. When hardened and cured, the paint shall form a dampproof film that will not powder, chip or rub off, and may be washed repeatedly without damage to the surface film.”

The contract provides that bidders shall visit the site of the proposed work and acquaint themselves with conditions attending the execution of the work and that they shall thoroughly examine and be familiar with the drawings and specifications. It then proceeds: “By submitting a bid the bidder agrees that he has examined the site and the specification and drawings and, where the specification requires in any part of the work a given result to be produced, that the specification and drawings are adequate and the required result can be produced under the specification and drawings. No claim for any extra *515 work will be allowed because of alleged impossibilities in the production of the results specified or because of inadequate or improper plans and specifications and wherever a result is required, the successful bidder shall furnish any and all extras and make any changes needed to produce, to the satisfaction of the Local Authority, the required result.”

After some of the surfaces had been painted with the designated kind of paint, it was found that it powdered, chipped and rubbed off. Both sides concur that this could not be prevented, if cement water paint was used, due to the fact that the walls were not porous but smooth. When this situation developed, oil paint was used instead of cement water paint and it ivas agreed that the question of liability should be submitted to arbitration under the general arbitration clause of the contract.

There can be no question that under the language of the contract, as a matter of law, the contractor should not be permitted to maintain a claim against the Authority for the extra cost the contractor was put to by the necessity of using another kind of paint than that mentioned in the specifications. The contractor covenanted that the specifications were adequate, that the result required by them could be produced, that no claim for any extra cost would be allowed because of impossibilities in the production of the result or because of inadequate specifications and that wherever a result was required, it should furnish any and all extras and make any changes needed to produce to the satisfaction of the Authority the required result. Had claim been made for the extra cost by the contractor in the ordinary way by suit in assumpsit, the court would have been required to give binding instructions against it.

It is argued by appellant that the rulings in Filbert v. Phila., 181 Pa. 530, 37 A. 545, and in Canuso v. Phila., 326 Pa. 302, 192 A. 133, permit the contractor to recover the extra cost he was subjected to as a result of substituting another kind of paint. We are here dealing with *516 the language of the contract in the case before us and under it the claim is not maintainable. The situations in the two cited cases and in the case of Mannella v. Pittsburgh, 334 Pa. 396, 6 A. 2d 70, are entirely different from that in the pending case, because of the language of the contract we are considering. In none of these cases did the contract unequivocally state that the contractor assumed responsibility for the desired result of a particular part of the work or agree that any claim for any extra work would not be allowed because of impossibilities in the production of the results.

Does the fact that the parties resorted to arbitration alter the situation and enable the contractor to recover his claim? This turns upon whether the arbitration-was at common law or under the Act of April 25,1927, P. L. 381, 5 PS §161.

It is argued by counsel for the contractor that the arbitration was at common law with all its incidents, including finality of the award, with no power of court review, and by counsel for the Authority that it was under the statute, with court dominion over it as the statute prescribes: Act of 1927, Secs. 10 and 11, 5 PS §§170,171.

The contract, after stating that all disputes arising under certain sections shall be decided by the Local Authority, provides: “All other disputes arising under this contract shall be decided by the Local Authority subject to arbitration as hereinafter provided. . . . One arbitrator shall be appointed by the Local Authority and one arbitrator shall be appointed by the Contractor, ... In the event the arbitrators so appointed shall not agree within a period of ten days, then a third arbitrator, who shall be a competent and disinterested person, shall be appointed, and the decision of any two of the three arbitrators, shall be conclusive. The third arbitrator shall be appointed by the two arbitrators theretofore appointed and acting, .... The arbitrators shall have the right to retain and consult experts and competent authorities skilled in the matter or matters under arbi *517 tration. Tlie fees, cost and expense of the arbitrators shall be borne by the party against whom the arbitration is determined, or partially by each party according to the determination if it is not entirely against one party, or, in the case of a determination by compromise, by such party or parties as may be designated by the arbitrators.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Flamini v. General Accident Fire & Life Assurance Corp.
477 A.2d 508 (Supreme Court of Pennsylvania, 1984)
State v. Lundgren Pacific Const. Co., Inc.
603 P.2d 889 (Alaska Supreme Court, 1979)
Abramovich v. Pennsylvania Liquor Control Board
12 Pa. D. & C.3d 115 (Dauphin County Court of Common Pleas, 1978)
Pennsylvania Turnpike Commission v. Sanders & Thomas, Inc.
336 A.2d 609 (Supreme Court of Pennsylvania, 1975)
Litton RCS, Inc. v. Pennsylvania Turnpike Commission
376 F. Supp. 579 (E.D. Pennsylvania, 1974)
Pennsylvania Turnpike Commission v. Sanders & Thomas, Inc.
316 A.2d 127 (Commonwealth Court of Pennsylvania, 1974)
J. A. & W. A. Hess, Inc. v. Hazle Township
305 A.2d 404 (Commonwealth Court of Pennsylvania, 1973)
Remsco Associates, Inc. v. Beaver Falls Municipal Authority
63 Pa. D. & C.2d 561 (Beaver County Court of Common Pleas, 1973)
Brandywine Area Joint School Authority v. Van Cor, Inc.
57 Pa. D. & C.2d 606 (Chester County Court of Common Pleas, 1971)
Commonwealth v. Sloan
52 Pa. D. & C.2d 283 (Pennsylvania Court of Common Pleas, 1971)
Weiss v. Zerman Realty & Construction Co.
251 A.2d 810 (Superior Court of Pennsylvania, 1969)
J. L. Turner Co. v. General State Authority
41 Pa. D. & C.2d 118 (Dauphin County Court of Common Pleas, 1966)
JA Robbins Co., Inc. v. Airportels, Inc.
210 A.2d 896 (Supreme Court of Pennsylvania, 1965)
Amalgamated Transit Union, Division 85 v. Port Authority
208 A.2d 271 (Supreme Court of Pennsylvania, 1965)
Munson v. Dury Clothing Co.
33 Pa. D. & C.2d 450 (Luzerne County Court of Common Pleas, 1964)
Monte v. Southern Delaware County Authority
212 F. Supp. 604 (E.D. Pennsylvania, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
23 A.2d 426, 343 Pa. 512, 1942 Pa. LEXIS 306, Counsel Stack Legal Research, https://law.counselstack.com/opinion/philadelphia-housing-authority-v-turner-construction-co-pa-1941.