Litton RCS, Inc. v. Pennsylvania Turnpike Commission

376 F. Supp. 579, 1974 U.S. Dist. LEXIS 8528
CourtDistrict Court, E.D. Pennsylvania
DecidedMay 15, 1974
DocketCiv. A. 73-1902
StatusPublished
Cited by33 cases

This text of 376 F. Supp. 579 (Litton RCS, Inc. v. Pennsylvania Turnpike Commission) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Litton RCS, Inc. v. Pennsylvania Turnpike Commission, 376 F. Supp. 579, 1974 U.S. Dist. LEXIS 8528 (E.D. Pa. 1974).

Opinion

OPINION [MEMORANDUM AND ORDER]

HUYETT, District Judge.

Litton RCS, Inc. (Litton) moves for confirmation of an arbitrators’ award entered in its favor by a panel of the American Arbitration Association. The arbitration proceeding was conducted pursuant to the following arbitration provision contained in a contract between Litton’s corporate predecessor Taller & Cooper, Inc. (“T&C”) and the Pennsylvania Turnpike Commission (“Commission”):

Any dispute between the parties hereto arising out of and under this agreement shall be submitted by them to the American Arbitration Association for arbitration of said dispute in accordance with its rules and the decision of said Association shall be binding upon all of the parties hereto. 1

The Commission vigorously opposes confirmation of the award raising questions concerning the jurisdiction of this court, the authority of the arbitrators to enter the award, and the merits of the award.

The contract between T&C and the Commission, dated August 10, 1967, was a research and development agreement in which T&C agreed to use its best efforts to develop a modern weight classification system of toll collection equipment. Pursuant to a notice to proceed, Litton began work on the project on August 11, 1967. With the-exception of research and development work on a “solid state” axle counting treadle, the agreement specified completion of all work up to installation of the equipment and personnel training within six months of the notice to proceed. Compensation was established on a cost plus a $20,000 fixed fee basis with T&C estimating total costs of $148,000. The Commission reserved the right to terminate the work required under the agreement at any time upon thirty (30) days prior written notice. It was contemplated by the parties that the toll equipment developed by T&C would be used to replace the Commission’s existing equipment.

After an initial billing of $74,594.92 on April 30, 1968, it became evident that the project would not be completed within the agreed upon time and the cost restraints. On March 6, 1969, the Commission gave notice of termination effective April 6, 1969. Litton made further billings for which the Commission refused to make payment. The matter was submitted to arbitration and an award in favor of Litton for $228,897.54 was entered on July 20, 1973. 2

The Commission has filed a motion to dismiss the action, and a motion to vacate or modify the arbitration award. Three grounds are urged in support of the motion to dismiss.

First, it is argued that only the Common Pleas Courts of the Commonwealth of Pennsylvania have jurisdiction to confirm the arbitrators’ award. The contract between the parties does not express any understanding regarding a specific court to confirm the award. The Commission contends, however, that pursuant to the provisions of the Pennsylvania Arbitration Act of April 25, 1927, P.L. 381, § 1 et seq., 5 P.S. § 161 et seq., only the Pennsylvania Common Pleas Courts can confirm an arbitrator’s award based on a contract involving a public agency or instrumentality. Section 16 of the Pennsylvania Arbitration Act, 5 P.S. § 176, states as follows: *582 Federal and state court cases are relied on by the Commission for the proposition that § 16 of the Pennsylvania Arbitration Act, 5 P.S. § 176, is mandatorily applicable to all contracts to which the Commonwealth or its instrumentalities are a party. See Merritt-Chapman & Scott Corporation v. Pennsylvania Turnpike Commission, 387 F.2d 768 (3 Cir. 1967); Acchione v. Commonwealth, 347 Pa. 562, 32 A.2d 764 (1943). This is so even though applicability of the Act contravenes the express terms of the contract. See Seaboard Surety Co. v. Commonwealth, 345 Pa. 147, 27 A.2d 27 (1942); Philadelphia Housing Authority v. Turner Construction Co., 343 Pa. 512, 23 A.2d 426 (1942). Since the Commission is an instrumentality of the Commonwealth, Act of May 21, 1937, P. L. 774, No. 211, § 4 as amended 36 P.S. § 652d, any contract entered into by the Commission is governed by the Pennsylvania Arbitration Act.

*581 The provisions of this act shall apply to any written contract to which the Commonwealth of Pennsylvania, or any agency or subdivision thereof, or any municipal corporation or political division of the Commonwealth shall be a party.

*582 Section 9 of the Pennsylvania Arbitration Act, 5 P.S. § 169, provides that “any party to the arbitration may apply to the court having jurisdiction for an order confirming the award, and thereupon the court shall grant such an order. .” Section 18 of the Pennsylvania Arbitration Act, 5 P.S. § 178, then defines “courts” as the “common pleas courts of the county having jurisdiction of the parties or the subject matter.” Thus, it is reasoned that only the Pennsylvania Common Pleas courts have authority to entertain the motion to confirm the arbitrators’ award.

Secondly, it is argued that as a result of the failure to state in the contract that a judgment of a court shall be entered upon the arbitrators’ award, a federal court under § 9 of the United States Arbitration Act, 9 U.S.C. § 9 (1970) 3 lacks power to confirm the award. Varley v. Tarrytown Associates, Inc., 477 F.2d 208 (2d Cir. 1973) so held with respect to a contract arbitration clause that stated: “Any controversy arising under this agreement or breach thereof shall be settled by arbitration pursuant to the rules of American Arbitration Association.” See also, Lehigh Structural Steel Co. v. Rust Engineering, 61 App.D.C. 224, 59 F.2d 1038 (1933).

Finally, with respect to the motion to dismiss, the Commission argues that the contract between the parties does not evidence a transaction involving commerce as required by § 2 of the United States Arbitration Act, 9 U.S.C. § 2 (1970). 4 It is thus contended that this court lacks jurisdiction to confirm the arbitrators’ award under that Act.

In its motion to vacate or modify the arbitrators’ award the Commission makes essentially three arguments. First, it is contended that the arbitrators lacked jurisdiction to grant an award because exclusive jurisdiction to hear claims against the Commission is cognizable only before the Board of Arbitration of Claims established pursuant *583 to the Board of Arbitration of Claims Act, Act of May 20, 1937, P.L. 728, No. 193, § 1 et seq. as amended, 72 P.S. § 4651-1 et seq. 5 In support of this position the Commission does not rely on any explicit provision of exclusivity contained in the Board of Arbitration of Claims Act. Rather the Commission bases its argument of exclusivity on the state doctrine of sovereign immunity.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Baltin v. Alaron Trading Corp.
Eleventh Circuit, 1997
Allied Fire & Safety Equipment Co. v. Dick Enterprises, Inc.
972 F. Supp. 922 (E.D. Pennsylvania, 1997)
Christy v. Pennsylvania Turnpike Commission
845 F. Supp. 1097 (E.D. Pennsylvania, 1994)
TM Marketing, Inc. v. Art & Antiques Associates, L.P.
803 F. Supp. 994 (D. New Jersey, 1992)
Klein v. Drexel Burnham Lambert, Inc.
737 F. Supp. 319 (E.D. Pennsylvania, 1990)
Kumagai v. Commonwealth
1 N. Mar. I. Commw. 942 (Northern Mariana Islands, 1984)
Ex Parte Alabama Oxygen Co., Inc.
433 So. 2d 1158 (Supreme Court of Alabama, 1983)
General Atomic Co. v. United Nuclear Corp.
655 F.2d 968 (Ninth Circuit, 1981)
Devlin v. Shearson Hayden Stone, Inc.
21 Pa. D. & C.3d 213 (Delaware County Court of Common Pleas, 1981)
Nichols v. Department of Corrections
1981 OK 83 (Supreme Court of Oklahoma, 1981)
Burke County Public Schools Board of Education v. Shaver Partnership
279 S.E.2d 816 (Supreme Court of North Carolina, 1981)
Sear v. Cadillac Auto. Co. of Boston
501 F. Supp. 1350 (D. Massachusetts, 1980)
INTERN. ASS'N OF BRIDGE, ETC. v. Koski Const. Co.
474 F. Supp. 370 (W.D. Pennsylvania, 1979)
United Nuclear Corp. v. General Atomic Co.
597 P.2d 290 (New Mexico Supreme Court, 1979)
Else v. Inflight Cinema International, Inc.
465 F. Supp. 1239 (W.D. Pennsylvania, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
376 F. Supp. 579, 1974 U.S. Dist. LEXIS 8528, Counsel Stack Legal Research, https://law.counselstack.com/opinion/litton-rcs-inc-v-pennsylvania-turnpike-commission-paed-1974.