Pierce Steel Pile Corp. v. Flannery

179 A. 558, 319 Pa. 332, 104 A.L.R. 706, 1935 Pa. LEXIS 689
CourtSupreme Court of Pennsylvania
DecidedApril 26, 1935
DocketAppeals, 167, 168, 169, 170 and 224
StatusPublished
Cited by22 cases

This text of 179 A. 558 (Pierce Steel Pile Corp. v. Flannery) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pierce Steel Pile Corp. v. Flannery, 179 A. 558, 319 Pa. 332, 104 A.L.R. 706, 1935 Pa. LEXIS 689 (Pa. 1935).

Opinion

Opinion by

Mr. Justice Schaffer,

As we visualize the real situation brought to our attention by the defendant’s appeals in this case its boundaries are very narrow. Did the court properly vacate an award of arbitrators because it was not final and definite as to the matters submitted? Incidental to the court’s determination in this respect is the question whether the court properly confirmed the subsequent award.

At the outset of the discussion it is proper to observe that both parties were dissatisfied with the first award and both asked the court to modify it. The court, instead of modifying, vacated it for the reason given above and referred the controversy back to the arbitrators. The arbitrators made a second and definite award, which *334 the court confirmed. In disposing of the matter in the way we view it, it is not necessary to state the details of the controversy, but to comment upon only one feature of it.

The dispute to be arbitrated grew out of the erection by the parties to this litigation of part of a large building in the City of Philadelphia. The requirement to arbitrate was part of their written contract, which stipulated that the arbitration should be held in accordance with the Act of April 25, 1927, P. L. 381, 5 P. S., section 163.

Plaintiff was a subcontractor under appellant. In their written contract, plaintiff undertook to do certain waterproofing in connection with the erection of the substructure of the building. Defendant was under contract with the owner to do the work provided for in his contract with plaintiff, as well as other work. The specifications required that the contractor for the waterproofing should give a written guarantee.

The provision in the contract covering arbitration is as follows: “In case of any dispute or question between the parties hereto which shall arise under this contract, the same shall be submitted to two disinterested arbitrators, one to be appointed by each of the parties to this contract, and the arbitrators so chosen shall, if themselves unable to agree, choose a third without unnecessary delay, and the decision in writing signed by those assenting thereto- of any two of the arbitrators, shall be final and binding on the parties hereto ...”

After plaintiff had been paid approximately ninety per cent of the aggregate contract price, disputes arose between it and defendant, and plaintiff presented a petition to the court below to compel defendant to proceed to arbitration. The court made an order granting the prayer therefor, which we affirmed on appeal (Pierce Steel Pile Corp. v. Flannery, 312 Pa. 5). Thereupon arbitrators were chosen and the parties presented to-them their respective claims. Hearings were held and *335 the arbitrators made a unanimous finding as follows: “The arbitrators find the contract to be in the sum of $500,000. The amount paid on account of contract, including cash and credits, is the sum of $446,850. The balance to the credit of the plaintiff is $53,150. The plaintiff shall, within 30 days, proceed with the repairs to the waterproofing: And shall furnish, within 30 days, to the defendant, a satisfactory guarantee of the waterproofing, which guarantee shall'extend to November 18, 1941: And shall furnish, within 30 days, a maintenance bond for $100,000 guaranteeing the waterproofing until November 18, 1941, in a company satisfactory to the'defendant, and the costs of the bond shall be paid by the defendant. When the plaintiff has made the substructure waterproof and furnished the guarantee and the maintenance bond, he shall be entitled to payment of this balance.”

The plaintiff sought modification of this finding by requesting the court to strike out all portions which required it to give a guarantee, a maintenance bond and to complete the waterproofing of the substructure as conditions precedent to being paid the balance of the contract price. Upon defendant’s claims against plaintiff, the arbitrators awarded the defendant certain sums. The award provided that these claims should be settled at the same time and under the same conditions as the award made to plaintiff. The defendant also filed a petition for modification, requesting that the arbitrators’ awards on its claims be modified to make the awards immediately payable to it.

In disposing of the rules granted on these petitions, the court in its opinion said: “We are impressed by the argument that the award of the balance conditioned upon the doing of certain acts within thirty days his tantamount to a refusal of the claim for the balance in default of the doing of such acts within the time limit. Unless and until the condition is performed plaintiff is not to be entitled to recover. . . . The arbitrators *336 awarded a specific sum to plaintiff upon certain conditions. . . . The plaintiff was to have been entitled to payment on completion of the work directed by the arbitrators to be done. Thus, by the terms of the award, failure of the plaintiff to complete the work bars recovery, and upon such failure the defendant is relieved of liability for the amount of the award. . . . By providing that the awards upon defendant’s claims be settled at the same time and under the same conditions as the award upon plaintiff’s claim 1, we think the arbitrators placed plaintiff in a position which enabled it similarly to avoid its liability to defendant. This feature of the award makes plaintiff’s liability to defendant subject to plaintiff’s option. The award of the arbitrators on the defendant’s claims [numbering them] is indefinite and inconclusive, in that it did not give rise to an immediate cause of action, and nothing the defendant can do would fulfill the conditions under which only he may acquire a right to demand the amounts awarded to him. The acts directed by the arbitrators to be done by plaintiff have not been done, and the time allowed therefor has expired; the arbitrators’ decision makes no provision for payment of the awards to defendant on the happening of such a contingency as has occurred, and, now that it has come about, the award leaves the parties in statu quo through no fault of defendant. The arbitration by its own terms, as modified by subsequent events, vitiates the awards made upon defendant’s claims. . . . The arbitrators have ordered that all awards be settled at the same time after fulfillment by plaintiff of the things required of it to be done. The entire award is thus infected by the error of the arbitrators in failing to provide for settlement in the event of plaintiff’s default, and is therefore void in toto.

“The Arbitration Act of 1927, P. L. 381, provides in section 10 that the court ‘shall make an order vacating the award upon the application of any party to the arbitration . . . (d) where the arbitrators exceeded their *337 powers or so imperfectly executed them that a final and definite award upon the subject-matter submitted was not made.’ In substance, this paragraph is a restatement of the law, and is not a substantial modification thereof. It is true that neither party to this arbitration has made application specifically for an order vacating the award, but each has petitioned for relief of a comparable sort, and this we regard as tantamount to a specific application. . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Titus & McConomy v. Jalisi
713 A.2d 646 (Superior Court of Pennsylvania, 1998)
Junta de Relaciones del Trabajo v. Otis Elevator Co.
105 P.R. Dec. 195 (Supreme Court of Puerto Rico, 1976)
LaVale Plaza, Inc. v. R. S. Noonan, Inc.
41 F.R.D. 4 (M.D. Pennsylvania, 1966)
Moran v. Paine, Webber, Jackson & Curtis
220 A.2d 624 (Supreme Court of Pennsylvania, 1966)
Kociuba v. Stubnitz Greene Corp.
36 Pa. D. & C.2d 246 (Delaware County Court of Common Pleas, 1964)
Ench Equipment Corp. v. Enkay Foods, Inc.
129 A.2d 313 (New Jersey Superior Court App Division, 1957)
Technical v. United States Steel Co.
88 Pa. D. & C. 464 (Alleghany County Court of Common Pleas, 1954)
International Ladies' Garment Workers' Union v. Nazareth Mills Co.
87 Pa. D. & C. 589 (Northampton County Court of Common Pleas, 1954)
Electric Power Construction Co. v. Allen, Lane & Scott, Inc.
80 A.2d 799 (Supreme Court of Pennsylvania, 1951)
Westinghouse Air Brake Co. Appeal
70 A.2d 681 (Superior Court of Pennsylvania, 1949)
In re McDevitt
66 Pa. D. & C. 290 (Philadelphia County Court of Common Pleas, 1948)
Bowles v. Biberman Bros.
61 F. Supp. 614 (E.D. Pennsylvania, 1945)
Schroeder Bros., Inc. v. Sabelli
40 A.2d 170 (Superior Court of Pennsylvania, 1944)
Sydnor Pump & Well Co. v. County School Board
28 S.E.2d 33 (Supreme Court of Virginia, 1943)
Philadelphia Housing Authority v. Turner Construction Co.
23 A.2d 426 (Supreme Court of Pennsylvania, 1941)
Britex Waste Co. v. Nathan Schwab & Sons, Inc.
12 A.2d 473 (Superior Court of Pennsylvania, 1939)
State Highway Department v. MacDougald Construction Co.
6 S.E.2d 570 (Supreme Court of Georgia, 1939)
Goldstein v. International Ladies' Garment Workers' Union
328 Pa. 385 (Supreme Court of Pennsylvania, 1938)

Cite This Page — Counsel Stack

Bluebook (online)
179 A. 558, 319 Pa. 332, 104 A.L.R. 706, 1935 Pa. LEXIS 689, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pierce-steel-pile-corp-v-flannery-pa-1935.