Sydnor Pump & Well Co. v. County School Board

28 S.E.2d 33, 182 Va. 156, 1943 Va. LEXIS 144
CourtSupreme Court of Virginia
DecidedDecember 6, 1943
DocketRecord No. 2705
StatusPublished
Cited by16 cases

This text of 28 S.E.2d 33 (Sydnor Pump & Well Co. v. County School Board) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sydnor Pump & Well Co. v. County School Board, 28 S.E.2d 33, 182 Va. 156, 1943 Va. LEXIS 144 (Va. 1943).

Opinion

Gregory, J.,

delivered the opinion of the court.

The appellant, Sydnor Pump and Well Company, Inc., was the complainant below, and filed its suit in equity against the County School Board of Henrico County, J. W. Atkinson and W. F. Gerhardt as defendants. The purpose of the suit was to have declared void an alleged arbitration award which grew out of a certain school building contract between the County School Board, on the one hand, and J. W- Atkinson, general contractor, on the other. If the award is held valid, then the prayer is that it be held not binding on the complainant, and, further, the complainant asks for a judgment against W. F. Gerhardt for $1,212.20 with interest and costs.

The court below denied every, ground of relief. It held the award of the arbitrators valid and binding upon all the parties including the complainant and that the complainant was not entitled to a judgment against Gerhardt. Costs were awarded against the complainant.

There is no dispute about the material facts. The contract was made between the County School Board and J. W. Atkinson, general contractor. It comprehended that portions of the work would be let to subcontractors. W. F. Gerhardt was a subcontractor, agreeing to perform all of the plumbing including the drilling of a well. The appellant for many years had operated a business which was that of drilling wells and it became a sub-subcontractor under- Gerhardt for the drilling of the well required under the original contract. Its contract consisted of certain proposals embraced in the specifications for the construction of the school build[161]*161ing. These proposals were the basis upon which, the appellant made its bid and read thus:

“Well:
“General: It is the intent to drill a well at Virginia Randolph School to furnish ten (zy) gallons of water per minute. It is estimated that to secure this amount of pure water the well is to be 200 ft. deep and a minimum diameter of 6"..
“If the well is drilled deeper than 200 ft. the extra depth shall be determined and fixed by the Architect with the approval of the School superintendent.
“Location: Well shah be located at a point designated in the plans and specifications of the Virginia Randolph School.
“Size of Well: The casing of the well shall be 6 inches.
“It is not. anticipated that any rock will be encountered when driving the well, but if rock is encountered the well shall be cased to rock, and the contractor will be paid for drilling through the rock at price bid in his proposal. Payment will be made at price bid in proposal—requirements to be made from existing surface of ground at well sites to the greatest depth drilled.
“Depth: It is intended to drive the casing approximately 200 ft. in depth and secure if possible a supply of 15 gallons per minute from the well. If, however, a suitable supply of water can be obtained at a less depth and below 100 ft. from the surface, the well will not be driven deeper. Should the contractor fail to secure a satisfactory supply of water at a depth of 200 ft. he shall drill deeper, if required to do so by the County School Board.
% # # . # # #
“The general contractor will be required to set. up in his proposal the following segregated items:
“Additional cost per lineal foot for a depth beyond 200 ft. from surface of ground.
[162]*162“Additional cost per lineal foot for drilling 6" inside diameter hole through rock if encountered.”

These proposals were considered by the appellant and through its proper agents a bid was made for the job of drilling the well. It was in writing addressed to Gerhardt and in this language:

“Gentlemen:
“We have examined the specifications covering the well with its extras and pumping unit and the proposal form, and we desire to submit the following figures which it will be necessary for you to have for the preparation of your bid:
“6"x 200 ft. specification well............$200.00
“Extra drilling well in rock, per foot...... 6.00
“Extra drilling well beyond 200 ft. well
depth specified, per foot............. 6.00”

The bid of the appellant was duly accepted and the contract closed. Special attention is directed to the proposals which required the appellant to segregate (a) the cost per. lineal foot for a depth beyond 200 feet from the surface and (b) the additional cost per lineal foot “for drilling 6" inside diameter hole through rock if encountered” because the appellant’s claim, as we will see later, has its background in those extra items. In response to those directions the appellant did segregate those items in its bid as will be observed by a reference to it.

The two events which the parties hoped would not happen actually did happen. First, the well had to be drilled more than 200 feet. Actually it was drilled to a depth of 393 feet and 9 inches, in order to obtain the required flow. Secondly, rock was encountered at a depth of 23 feet and 6 inches, and from that point to completion It was drilled through rock for 370 feet and 3 inches. Accordingly, the appellant billed Gerhardt as follows:

[163]*163“Sold to
“W. F. Gerhardt,
“2007 West Broad Street,
“Richmond, Virginia.
“To drilling, casing and testing well as per specifications at Virginia Randolph School........$ 200.00
“Extra for drilling in rock from 23/6" to 393V' 37o'3" @ $6.00 per foot..................... 2,221.50
“Extra for drilling beyond 200 ft. well depth specified from 200' to 393'9" 193V' @ $<5.oo per foot. 1,162.50
“Credit by check April 25
$3,584.00
498.93
$3,085.07"

Bills in like amount were sent by Gerhardt to the general contractor, Atkinson, and by him sent to the School Board. All but $1,212.20 has been paid on the account. Payment of that balance was refused by the School Board, Atkinson and Gerhardt, though Gerhardt in his letter transmitting the account to Atkinson expressed satisfaction with the account. He wrote that the well complied with the plans and specifications and with his contract. He also wrote that the extras shown on the account for drilling through rock and for drilling below 200 feet were correct. He requested that the account be paid.

The reason assigned by the School Board for its refusal to pay the account is contained in a letter from the Director of School Buildings to J. W. Atkinson. The Director construed the appellant’s contract with Gerhardt to mean that appellant was to receive only $6.00 per foot below the [164]*164200 feet regardless of whether the drilling was through solid rock or through earth without any rock.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hassett v. WaveCrest Laboratories, L.L.C.
75 Va. Cir. 122 (Fairfax County Circuit Court, 2008)
Virginia Eastern Co. v. N. C. Monroe Construction Co.
56 Va. Cir. 220 (Salem County Circuit Court, 2001)
Ferk, Ltd. v. Turner Enterprises, Ltd.
43 Va. Cir. 238 (Charlottesville County Circuit Court, 1997)
Trustees of Asbury United Methodist Church v. Taylor & Parrish, Inc.
452 S.E.2d 847 (Supreme Court of Virginia, 1995)
TRUSTEES OF ASBURY CHURCH v. Taylor
452 S.E.2d 847 (Supreme Court of Virginia, 1995)
Primoff v. Slocum, Boddie & Murry
33 Va. Cir. 225 (Fairfax County Circuit Court, 1994)
Rosenstiel v. Fair
23 Va. Cir. 331 (Virginia Circuit Court, 1991)
Trustees of Asbury United Methodist Church v. Taylor & Parrish, Inc.
26 Va. Cir. 18 (Chesterfield County Circuit Court, 1991)
Home Oil Co. of Hot Springs v. Home Oil Co.
393 S.E.2d 188 (Supreme Court of Virginia, 1990)
Spotsylvania County School Board v. Sherman Construction Corp.
14 Va. Cir. 333 (Spotsylvania County Circuit Court, 1989)
Howerin Residental Sales Corp. v. Century Realty of Tidewater, Inc.
365 S.E.2d 767 (Supreme Court of Virginia, 1988)
United Paperworkers International Union v. Chase Bag Co.
281 S.E.2d 807 (Supreme Court of Virginia, 1981)
Weaver Associates, Inc. v. Bell
7 Va. Cir. 537 (Alexandria County Circuit Court, 1979)
Gramling v. Food MacHinery and Chemical Corp.
151 F. Supp. 853 (W.D. South Carolina, 1957)
Cassara v. Wofford
55 So. 2d 102 (Supreme Court of Florida, 1951)

Cite This Page — Counsel Stack

Bluebook (online)
28 S.E.2d 33, 182 Va. 156, 1943 Va. LEXIS 144, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sydnor-pump-well-co-v-county-school-board-va-1943.