Brandywine Area Joint School Authority v. Van Cor, Inc.

57 Pa. D. & C.2d 606, 1971 Pa. Dist. & Cnty. Dec. LEXIS 84
CourtPennsylvania Court of Common Pleas, Chester County
DecidedMay 24, 1971
Docketno. 100
StatusPublished
Cited by1 cases

This text of 57 Pa. D. & C.2d 606 (Brandywine Area Joint School Authority v. Van Cor, Inc.) is published on Counsel Stack Legal Research, covering Pennsylvania Court of Common Pleas, Chester County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brandywine Area Joint School Authority v. Van Cor, Inc., 57 Pa. D. & C.2d 606, 1971 Pa. Dist. & Cnty. Dec. LEXIS 84 (Pa. Super. Ct. 1971).

Opinion

MARRONE, J.,

— Brandywine Area [607]*607Joint School Authority (Authority) brought suit against Van Cor, Inc. (Van Cor) for breach of a contract for construction of three school buildings and against its surety, Aetna Casualty & Surety Company (Aetna) for breach of contract under its bond for Van Cor s faithful performance of the construction contract. The case was tried before the court without a jury pursuant to the provisions of the Act of April 22, 1874, P. L. 109, sec. 1, 12 PS §688, and a stipulation of the parties filed of record that the trial judge return a general verdict only without the necessity of making special findings of fact.

Following lengthy trial, arguments of counsel and careful consideration and review of the voluminous record, as well as the able briefs of counsel, the trial judge filed his decision in which he made six findings, the import of which was a determination that Van Cor was liable for breach of its contract with Authority and that Aetna was liable as surety on the contract performance bond. Liability was found to be in the sum of $212,762.93. Van Cor and Aetna have filed exceptions to each of those findings and to three specific rulings on evidence made by the trial judge in the course of the trial. Argument on the exceptions having been heard, the matter is now before us for decision.

Findings by a trial judge sitting without a jury have the force and effect of a jury’s verdict, and the party favored by those findings is entitled to have the evidence viewed in the light most favorable to him, and to have all conflicts in testimony resolved in his favor: Krobat v. Ganzak, 194 Pa. Superior Ct. 49; Colish v. Goldstein, 196 Pa. Superior Ct. 188; D’Angelo Estate v. Armor Co., 198 Pa. Superior Ct. 283. Accordingly, the record discloses and the credible evidence establishes the following facts.

Plaintiff, a corporation organized and existing under [608]*608the Municipality Authorities Act of 1945, and Van Cor, a Pennsylvania corporation, as prime contractor entered into a construction contract dated November 18, 1960, for the general construction of the Rainbow Elementary School, North Brandywine Elementary School and Iiustonville Elementary School in accordance with contract documents including plans and specifications for a total contract price of $557,368. Aetna, a paid surety, with Van Cor as principal, executed and delivered a performance bond, pursuant to the contract provisions, for the faithful performance of the contract and undertaking to indemnify plaintiff from any expenses incurred should Van Cor fail to complete the work specified or from damages to plaintiff growing out of Van Cor’s or its subcontractors’ manner of performance, and further agreeing to remedy without cost to plaintiff all defects which might develop during a one-year period from the date of completion and acceptance of the work, which, in plaintiff’s judgment, were caused by defective or inferior materials or workmanship. Construction of each of the three schools was begun in January 1961, and was substantially completed in early September 1961. During the construction, payments were made by the Authority to Van Cor in accordance with an agreed payment schedule, the final progress payment being made on or about October 6, 1961, and the final retention payment on May 31, 1962. Roof leaks began to appear almost immediately upon completion of the construction and were first brought to the attention of Van Cor by the Authority through its architect, Buchart Associates, in a letter of November 28, 1961, requesting that the leaks be corrected within 14 days. Subsequent notices from the Authority to Van Cor of December 20 and 21, 1961 resulted in attempts by Van Cor, through Atlas Roofing & Sheet Metal Company, [609]*609its roofing subcontractor, and the Flintcote Company, its roof bonding contractor, to correct the leaks. The various repairs made failed to correct the roof leaks for reasons that became more apparent in January 1963, when the Authority’s architect inspected the three schools and reported to the Authority that, in addition to other specified defects and deficiencies involving the skylights and various roofing materials, fascia, coping and other flashings, they observed excessive deflection of the Flexicore roof slabs on which the built-up roof was applied at each of the three schools. At a meeting with the Authority on March 14, 1963, Van Cor was provided a copy of this report and was thereafter advised by the Authority on April 1, 1963, to replace all defective roofing, flashing and other roofing materials, including the Flexicore roof slabs where necessary and repair all damage done to the three schools as a result of water leakage. Certain repairs, not including the Flexicore roof slabs, were thereafter effected by George H. Duross, Inc., an independent roofing contractor, at Van Cor’s expense. Notwithstanding those repairs, the roof leaks persisted until and after this action was brought.

We shall first consider defendants’ three exceptions to the trial judge’s rulings on evidence. The first goes to the ruling asserted to have been made on cross-examination of plaintiff’s witness, Shields, that evidence as to design of the buildings was not admissible. In fact, no such ruling was made. The trial judge took that testimony subject to objection and reserved ruling upon its admissibility. We now hold that evidence to have been relevant and admissible. While the basic issue between the parties was that of faulty materials and faulty workmanship, and at the stage of the case while Shields was on the stand the issue of improper design was not strictly relevant, cross-examination [610]*610about faulty design, as against faulty materials or workmanship, was relevant at least as an attack on the witness’s credibility. In addition, plaintiff later showed through its witness, Frank, that the design of the buildings was proper. Thus, on the whole record we cannot say that the questioned crossexamination of Shields was irrelevant or improper. Furthermore, if it would have been error to permit Shields to testify as to what Frank told him was his, Frank’s, engineering opinion as to design, such error was harmless error in light of Frank’s own testimony as to propriety of design when he was later called as plaintiff’s witness.

The second and third exceptions to rulings on evidence go on the one hand to exclusion of the American Concrete Institute’s Code, 6-1963, setting forth deflection in prestressed concrete slabs and on the other to exclusion of the testimony of defendants’ expert, Caplan, with respect to provisions of the same 1963 code relating to specifications as to span lengths for precast concrete. The answer to those questions seems to us obvious. The Code of 1963 was promulgated and published more than two years after the contract documents were executed and the construction work was commenced. Such a code, not adopted by the institute until March 1963, or ratified by it until May 1963, is so clearly after the fact as to be wholly irrelevant. Whether earlier contracts, construction or design conformed to the 1963 Code provisions, adopted and published more than two years later in light of more recent studies and developments, had no relevancy whatever, those rulings were correct.

Van Cor and Aetna both except to the trial judge’s finding that Van Cor failed to erect and install the roofs, roof structures and skylights on each of the three school buildings in a good and workmanlike manner and used defective materials in the erection and instal[611]*611lation thereof.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
57 Pa. D. & C.2d 606, 1971 Pa. Dist. & Cnty. Dec. LEXIS 84, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brandywine-area-joint-school-authority-v-van-cor-inc-pactcomplcheste-1971.