Teufel v. Wienir

411 P.2d 151, 68 Wash. 2d 31, 1966 Wash. LEXIS 699
CourtWashington Supreme Court
DecidedFebruary 17, 1966
Docket37944
StatusPublished
Cited by7 cases

This text of 411 P.2d 151 (Teufel v. Wienir) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Teufel v. Wienir, 411 P.2d 151, 68 Wash. 2d 31, 1966 Wash. LEXIS 699 (Wash. 1966).

Opinion

Weaver, J.

This case poses the question of whether a contractor is liable under his guaranty in a standard form *32 construction contract of the American Institute of Architects when the construction failure is due to a design and not to a construction defect.

Defendants, William S. Wienir and Birdye F. Wienir, his wife, appeal from a money judgment against them. The judgment is based on two promissory notes given as partial payment on a construction contract.

The basic question on this appeal is whether plaintiffs, the prime contractors for the erection of a building, are liable in damages for the inadequacy of the curtain wall installed on the “high rise building.” This requires an interpretation and a determination of the legal effect of the terms of the construction contract and of a stipulation between the parties for a dismissal of a prior court action.

The unchallenged findings establish the following: Plaintiffs, doing business as George E. Teufel Company contracted with defendants, Wienir, to build a 117 unit, high-rise apartment building in Seattle.

The construction specifications prepared by defendants’ architect prescribed the use of a trade name type of curtain wall: “Teclar Projected Casement Series No. 1600.” The specifications were modified by defendants’ architect by a reduction to “Casement Series No. 1400.” No error is assigned to the court’s finding that:

This change resulted in a less costly curtain wall and one of lighter construction which was not suitable to this high rise building. Leaks in the curtain wall have developed and are due to the inadequacy of the prescribed curtain wall for the high rise building.

The specifications required that the curtain wall be fabricated by a subcontractor:

Workmanship
Only first quality workmanship executed by skilled mechanics shall be acceptable. All fabrication shall be done at the factory by a manufacturer regularly engaged in the manufacture of this kind of work with sufficient experience in the opinion of the Architect to execute the work for this project. It shall be the responsibility of this subcontractor to produce curtain walls and windows of first class quality which will not leak or allow any weather *33 infiltration, will permit free movement without generation of such infiltration nor of noises or visible ■ distortion of any kind and which will meet all other requirements of this specification regardless of the materials, workmanship and methods specified or shown. If, in the opinion of the curtain wall subcontractor, it is necessary to modify the materials, workmanship, and methods specified to produce work which will meet the above requirements, he shall so state in writing to the architect before commencing any work, or be bound by the specifications to construct the work to meet the above requirements. However, any change in the materials, workmanship or methods specified shall first be approved in writing by the architect, and shall involve no additional cost to the owner. This responsibility extends to and includes responsibility for glass and glazing of window walls (which is specified as a separate subcontract) and the curtain wall subcontractor shall similarly indicate any change he may require in such work as specified. (Italics ours.)

Further, the specifications required that the curtain wall be installed by the subcontractor.

All erection shall be by the manufacturer of the curtain wall and shall not be sublet by the General Contractor to any other subcontract. (Italics ours.)

Thus the curtain wall was designated by defendants’ architect by trade name, standard and type. The contract specifications required that it be fabricated and erected by a subcontractor “with sufficient experience in the opinion of the architect to execute the work for this project.”

Teclar Aluminum Company, later acquired by Fentron Industries, Inc., manufactured and erected the curtain wall. Neither Teclar nor Fentron gave any statement to the architect that it was necessary to modify the materials, workmanship and methods specified to produce work which would meet the requirements of the contract specifications.

The contract was made subject to the Standard General Conditions for the Construction of Buildings of the American Institute of .Architects. Article 20 thereof is a guaranty clause which states:

*34 Neither the final certificate nor payment nor any provision of the Contract Documents shall relieve the Contractor of responsibility for faulty materials or workmanship and, unless otherwise specified, he shall remedy any defects due thereto and pay for any damage to other work resulting therefrom, which shall appear within a period of one year from the date of substantial completion. The Owner shall give notice of observed defects with reasonable promptness. All questions arising under this article shall be decided by the Architect subject to arbitration. (Italics ours.)

Upon completion of the building and acceptance by defendants’ architect, numerous defects were found to exist. Final payment was withheld pending correction. Plaintiffs filed a lien for the balance due and commenced suit against defendants seeking payment for the sums withheld. Defendants counterclaimed for damages for breach of contract.

Prior to trial the parties entered into a stipulation for dismissal, which provided:

(1) The action would be dismissed with prejudice;
(2) Plaintiffs would do all things necessary to correct the defective conditions existing at the date of the stipulation that would normally be corrected under the one-year guaranty of the contract;
(3) The Wienirs [defendants] would pay the promissory notes which they had delivered to Teufels [plaintiffs] and waive any defenses thereto.

Thereafter plaintiffs and some of the subcontractors attempted to repair and correct existing defects which would normally be corrected under the one-year guaranty referred to in the stipulation. No attempt was made to correct the leaking curtain wall. Plaintiffs’ demand for payment of the promissory notes was refused; hence plaintiffs commenced this action in which defendants defend on the basis that the leaking curtain wall was a defective condition that would normally be corrected under the terms of the one-year guaranty. They ask for damages for the curtain wall and for other uncompleted work.

*35 The trial court awarded plaintiffs a $28,900 judgment with interest on the two promissory notes plus $2,000 attorney fees. It awarded defendants a $3,300 setoff for plaintiffs’ breach of the stipulation for failing to correct certain other defects in the building.

The focal point of this appeal is the trial court’s finding that:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bruce Martin Construction, Inc. v. CTB, Inc.
735 F.3d 750 (Eighth Circuit, 2013)
Bhattarai v. Stein
849 P.2d 1153 (Court of Appeals of Oregon, 1993)
Marine Colloids, Inc. v. M. D. Hardy, Inc.
433 A.2d 402 (Supreme Judicial Court of Maine, 1981)
Weston v. New Bethel Missionary Baptist Church
598 P.2d 411 (Court of Appeals of Washington, 1979)
ATLANTIC NAT. BK, ETC. v. Modular Age, Inc.
363 So. 2d 1152 (District Court of Appeal of Florida, 1978)
Brandywine Area Joint School Authority v. Van Cor, Inc.
57 Pa. D. & C.2d 606 (Chester County Court of Common Pleas, 1971)
Kubby v. Crescent Steel
466 P.2d 753 (Arizona Supreme Court, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
411 P.2d 151, 68 Wash. 2d 31, 1966 Wash. LEXIS 699, Counsel Stack Legal Research, https://law.counselstack.com/opinion/teufel-v-wienir-wash-1966.