Marine Colloids, Inc. v. M. D. Hardy, Inc.

433 A.2d 402, 1981 Me. LEXIS 910
CourtSupreme Judicial Court of Maine
DecidedAugust 10, 1981
StatusPublished
Cited by4 cases

This text of 433 A.2d 402 (Marine Colloids, Inc. v. M. D. Hardy, Inc.) is published on Counsel Stack Legal Research, covering Supreme Judicial Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Marine Colloids, Inc. v. M. D. Hardy, Inc., 433 A.2d 402, 1981 Me. LEXIS 910 (Me. 1981).

Opinion

GODFREY, Justice.

Plaintiff Marine Colloids, Inc. appeals from a judgment of the Superior Court in favor of the defendant, M. D. Hardy, Inc., in an action arising from a contract to construct a firewall. The Superior Court based its judgment on a referee’s report which absolved Hardy of all liability for negligence or breach of warranty. On appeal Marine Colloids argues that the referee erred as a matter of law in concluding that because Hardy followed Marine Colloids’ specifications for the construction of the firewall, Hardy could not be liable for damages resulting from the firewall’s collapse. We affirm the judgment below.

On February 7, 1977, Marine Colloids filed in Superior Court a complaint against M. D. Hardy, Inc., a construction firm. The complaint alleged that Marine Colloids, a seaweed processor, had retained Hardy to design and construct a firewall for one of Marine Colloids’ buildings; that because Hardy held itself out to the public as knowledgeable and experienced in construction work while Marine Colloids lacked any special expertise in that area, Hardy assumed a duty of care in designing and constructing the firewall; that Hardy breached that duty by designing and constructing a firewall that “violated widely accepted standards of engineering practice.” Furthermore, the complaint alleged that Hardy breached its express or implied warranties that the firewall would be constructed in a workmanlike manner, that the materials used in the firewall would be reasonably suited for their use, and that the design of the firewall would “conform to all reasonable standards and practices of the construction trade.” As a proximate result of Hardy’s negligence and breach of warranties, Marine Colloids claimed, the firewall collapsed during a storm and damaged certain buildings and equipment owned by Marine Colloids.

Hardy’s answer denied all Marine Colloids’ allegations concerning its liability.

A hearing in the matter, held before a referee, began on January 21,1980. During five days of testimony the following evidence was presented which, if believed, would have tended to exonerate Hardy from any liability to Marine Colloids:

On November 22, 1974, Marine Colloids sent to three contractors, including Hardy, a request for the submission of bids on a construction project. Among other aspects of the project, Marine Colloids sought estimates of the cost of building a large metal-clad building with an accompanying firewall, plus a slab foundation for the future expansion of an existing building known as the “Pilot Plant.” The description of the firewall in the bid request read in its entirety:

Firewall.
A firewall is to be constructed at the north end adjacent to the slab area described under Item 1. The wall is to be constructed of 12" block construction for a two hour fire rating. The top edge of *404 the structure is to be concrete capped, with a 22 GA galvanized iron flashing covering this concrete. The firewall will be flashed to the building at both side walls and roof.
A sleeve of 12" channel shall be set in the wall to allow access of necessary service piping, etc. and will receive a plate assembly on each side of the block wall, filled with insulation. A design of the holes for the two plates will be provided the contractor at a later date.
This firewall must meet with approval of Factory Mutual or equivalent representative agency.

Accompanying the bid request was a drawing of the entire proposed project. If a contractor’s bid were accepted by Marine Colloids, that contractor was obliged under the terms of the bid request to “guarantee soundness of construction for a minimum period to be specified as one year from completion of the contract.”

Malcolm Hardy, President of M. D. Hardy, Inc., and William Greet, the Special Projects Engineer for Marine Colloids, had met two days before the bid request was drafted. At that meeting Greet had explained the scope and purpose of the proposed construction project and also many specific dimensions of the works to be built. Such pre-bid consultation was natural, for Hardy had earlier built several structures for Marine Colloids and had willingly made himself available to answer the company’s questions. Hardy was not employed by Marine Colloids as a consultant, however, but maintained contact with Marine Colloids merely as a matter of courtesy to a good customer.

During their meeting, Greet had told Hardy that the firewall must be built of twelve-inch concrete blocks, extend two feet beyond the walls and eaves of the building, and be able to restrain a fire for a minimum of two hours. Thus, Greet had already defined the height and width of the wall and the basic materials of which it would be constructed. Although Hardy inferred that further design of the firewall might be necessary, he assumed that Marine Colloids would make design alterations through subsequent change orders issued to the contractor. Furthermore, Hardy was not too concerned about the stability of the firewall inasmuch as the project called for the ultimate erection of buildings abutting the wall on either side. As far as Hardy knew, the contractor was required to build only a free-standing curtain wall that would stand between two buildings without being bonded to them; he was not asked to construct either a weight-bearing wall or an end wall that would be exposed to the elements.

The bid request was sent to M. D. Hardy, Inc. and to two other construction firms. Hardy was the low bidder, but the bids from the other two firms on the firewall were so similar to Hardy’s as to indicate that all three firms had the same understanding of how the firewall was to be built. Marine Colloids accepted Hardy’s bid and included in its acceptance the following language: “Above construction to be all as per W. E. Greet specifications and dwgs. by M. D. Hardy, Co.” Hardy had drafted certain drawings of the projected construction, but those drawings only followed specifications and plans that had already been created by Greet.

When Greet attempted to secure a building permit for the project, the Building Inspector for the City of Rockland informed him that the Rockland Building Code required firewalls of the proposed height to be at least sixteen inches thick. At Marine Colloids’ request, Hardy submitted an estimate of the cost occasioned by expanding the firewall’s thickness from twelve to sixteen inches. Marine Colloids accepted the proposal and authorized Hardy to construct the wall at the revised thickness.

In accordance with Marine Colloids’ specifications Hardy erected the metal-clad building, constructed the firewall, and poured the foundation for the Pilot Plant expansion. Hardy completed the firewall on July 9, 1975. One day later, Marine Colloids told Hardy that the Pilot Plant expansion was to be held in abeyance indefinitely. In the fall of 1975 Greet communi *405 cated to Hardy his concern that the firewall might not be stable in the absence of the abutting Pilot Plant expansion. After examining the firewall in Greet’s presence, Hardy told Greet that he had no confidence in the firewall’s ability to serve as an exposed end wall rather than as an interior curtain wall.

The firewall stood for nearly seven months, exposed on the northern end of the metal-clad building.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Associated Builders, Inc. v. Oczkowski
2002 ME 115 (Supreme Judicial Court of Maine, 2002)
Paine v. Spottiswoode
612 A.2d 235 (Supreme Judicial Court of Maine, 1992)
Cianci Constr. Co. v. Griffin Constr. Co., No. 27 77 93 (Feb. 4, 1991)
1991 Conn. Super. Ct. 1461 (Connecticut Superior Court, 1991)
Shaw v. General Motors Corp.
727 P.2d 387 (Colorado Court of Appeals, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
433 A.2d 402, 1981 Me. LEXIS 910, Counsel Stack Legal Research, https://law.counselstack.com/opinion/marine-colloids-inc-v-m-d-hardy-inc-me-1981.