This text of 278 F. Supp. 345 (Wilmar Marine Engineering & Sales Corp. v. M/V Perseo) is published on Counsel Stack Legal Research, covering District Court, E.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wilmar Marine Engineering & Sales Corp. v. M/V Perseo, 278 F. Supp. 345, 1967 U.S. Dist. LEXIS 9160 (E.D. La. 1967).

Opinion

WEST, Chief Judge:

Libelant, Wilmar Marine Engineering & Sales Corporation, brings this suit to recover for work allegedly performed by it in connection with the cleaning of the tanks of the M/Y PERSEO, a vessel owned and operated by respondent, Sicula Oceánica, S.A., hereafter called Siosa. Respondent, Siosa, answered, denying owing libelant anything, basing its denial on an alleged breach of contract by Wilmar, and then counterclaiming against Wilmar for damages allegedly resulting from the breach of contract. After reviewing the extensive record in this case, the Court concludes that Wilmar is entitled to recover from respondent the total sum of $46,764.41, and in connection with this conclusion makes the following Findings of Fact and Conclusions of Law.

FINDINGS OF FACT

1.

At all times pertinent hereto, libelant, Wilmar Marine Engineering & Sales Corporation, hereafter referred to as Wilmar, was a corporation organized pursuant to the laws of the State of Louisiana with its principal place of business being located at Arabi, Louisiana.

[347]*3472.

At all times pertinent hereto, the respondent, Sicula Oceánica, S.A., hereafter referred to as Siosa, was a foreign corporation organized under the laws of Italy, with its principal place of business being located in Genoa, Italy, and was, at all times pertinent hereto, the owner and operator of the M/Y PERSEO.

3.

The M/V PERSEO is an ocean-going merchant vessel of 9493 net tons with a carrying capacity of approximately 23,-000 tons. She is compartmented into 27 compartments or tanks, arranged three abreast with the nine center tanks measuring about 40 feet square by 45 feet deep, and the nine port and nine starboard tanks measuring each about 40 feet long, 20 feet wide, and 45 feet deep.

4.

On March 12,1965, while the PERSEO was discharging a cargo of oil in Belgium, her owner, Siosa, entered into a charter party with Tradex Export, S.A., the time charterer, pursuant to which the PERSEO was to make three voyages carrying grain out of United States gulf ports. Baton Rouge, Louisiana, was nominated as the first port at which a cargo of grain was to be loaded aboard. The charter party provided that the PERSEO was to be inspected and approved by the proper officials at the loading port for hauling of grain on or before 12:00 o’clock noon on April 8, 1965, and if this condition was not met, the charterer had the option of cancelling the entire contract.

5.

In order to obtain the approval of the inspectors for hauling grain in the PER-SEO, it was necessary that all of her tanks be properly cleaned and made free of any oil residue to avoid contamination of the grain by the residue of the previous cargo of petroleum products. In ■order to accomplish this by the time the vessel was due to arrive in Baton Rouge, Siosa intended to have the ship’s crew, under the supervision of Mr. Christiansen, a technician brought aboard for the purpose, clean the tanks while en route from Europe to Baton Rouge by a process known as butterworthing. This ^ a cleaning process that requires the use of water and chemicals applied under pressure by use of specially designed nozzles and hose connectors.

6.

While it was expected that the tanks could be adequately cleaned by this process before the vessel reached Baton Rouge, such was not the case. Bad weather was encountered on the crossing and other difficulties, such as clogged condenser pipes, inadequate number of “butterworthing holes,” and difficulty in obtaining water of the proper temperature. All of these difficulties combined to defeat the efforts of the crew to complete the butterworthing process on time. The vessel was diverted to Bermuda for the installation of new condenser pipes where it remained for 48 hours before proceeding to New Orleans, Louisiana. What was begun as a more or less routine cleaning job turned out to be a rather complicated and extensive undertaking.

7.

When the PERSEO arrived at Pilot-town, below New Orleans, Louisiana, on April 6, 1965, Dr. Aldo Grimaldi, a director and representative of Siosa, came aboard. After checking on the progress of the tank cleaning, he realized that there was much more to be done than could be accomplished by the ship’s crew in the short time remaining before April 8, so he decided to employ the services of a tank cleaning firm to complete the job. When the vessel arrived at New Orleans, a Mr. Peterson, the head of a tank cleaning firm, came aboard. After discussing the job with Grimaldi, he, Peterson, decided he could not complete the job by April 8. He further indicated that the job might cost as much as $50,000 — a figure which Grimaldi held “to be completely fair.”

[348]*3488.

When Peterson refused to do the job, Grimaldi realized the impossibility of meeting the April 8 deadline so he arranged with the charterer, Tradex, for an extension of seven days, or until noon, April 15. After this extension was obtained, Grimaldi contacted plaintiff Wilmar sometime during the night of April 6, or early morning of April 7, and the following contract was entered into:

“April 7,1965
“We propose to clean M/T PERSEO to load a cargo of com. We will clean center tanks # 1-9 and port and starboard tanks 1-9 to be cleaned to the satisfaction of the National Cargo Bureau and the Board of Trade Inspectors.
“Work will be performed at the regular rate of $4.20 per man hour. Work will probably be completed by Monday night midnight April 12th. Anyway vessel must be in Baton Rouge by 12 noon on April 13th. Normal overtime rate will be charged if necessary.
“Terms: 75% of invoice to be paid on securing of certificate of readiness from National Cargo Bureau and Board of Trade Inspectors.
“Maximum price for cleaning vessel will be $31,000.00 (Thirty One Thousand Dollars).
(Signed) (Signed)
“Aldo Grimaldi Raymond Willhoft
Wilmar Marine Engineering”

9.

On April 7, prior to executing this contract, Mr. Raymond George Willhoft, Secretary-Treasurer of Wilmar, boarded the PERSEO pursuant to Grimaldi’s request conveyed to him by telephone call from one Mr. Piccolo, who was acting as translator, and upon this first visit, when asked by Grimaldi to give a firm bid for doing the work, refused to do so and left the ship. Later in the day, upon being asked to return to the ship, Willhoft did so, and after discussing the matter with Grimaldi and Christiansen, he agreed to do the job on a “time and material basis” using $4.20 an hour as a man-hour cost. When Grimaldi insisted that a maximum figure be agreed upon, the contract appearing in Finding No. 8 was executed.

10.

When the contract was entered into Wilmar, through its representative Willhoft, was given to understand that the vessel had been completely butterworthed and that nothing remained to be done but to clean out the residue left after butterworthing has been completed. Wilmar was not advised of the fact that the butterworthing had not, in fact, been completed and that much more than a “clean-up” job was involved.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
278 F. Supp. 345, 1967 U.S. Dist. LEXIS 9160, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wilmar-marine-engineering-sales-corp-v-mv-perseo-laed-1967.