Roberts, Johnson & Rand Shoe Co. v. Westinghouse Electric & Mfg. Co.

143 F. 218, 74 C.C.A. 348, 1906 U.S. App. LEXIS 3725
CourtCourt of Appeals for the Eighth Circuit
DecidedJanuary 15, 1906
DocketNo. 2,207
StatusPublished
Cited by5 cases

This text of 143 F. 218 (Roberts, Johnson & Rand Shoe Co. v. Westinghouse Electric & Mfg. Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Roberts, Johnson & Rand Shoe Co. v. Westinghouse Electric & Mfg. Co., 143 F. 218, 74 C.C.A. 348, 1906 U.S. App. LEXIS 3725 (8th Cir. 1906).

Opinion

HOOK, Circuit Judge.

The Westinghouse Electric & Manufacturing Company sued the Roberts, Johnson & Rand Shoe Company to recover the value of certain electrical machinery sold and delivered to the latter. By its answer, which was in two counts, and the evidence in support thereof, the defendant asserted (1) that the machinery had been sold to defendant and installed in its factory pur[219]*219suant to a written contract dated July 17, 1903, which provided that the entire installation be completed and ready for service by November 1, 1903; that the plaintiff had been duly informed of the great importance to the business of defendant of full performance of the contract within the time specified, but that through inexcusable delay of the plaintiff the machinery was not furnished and fully installed until February 22, 1904, and the defendant thereby sustained damage in an amount largely in excess of the plaintiff’s claim; that, having made its claim for the damage sustained, both parties, in compliance with the provisions of the contract, submitted the differences between them to the engineer in charge of the electric construction and his decision thereon was in favor of the defendant, and that such decision was in full force and effect and constituted a bar to the prosecution of the plaintiff’s action; and (2) an affirmative counterclaim for the damage averred to have been sustained by defendant, with prayer for judgment therefor against the plaintiff.

During the trial, which was to a jury, the Circuit Court held that the provisions of the contract with reference to submission of differences between the parties to the engineer and what appeared to have been done thereunder were insufficient to constitute a defense to the plaintiff’s action. Thereafter, and at the conclusion of the evidence, the Circuit Court in charging the jury also announced its opinion that, while defendant had doubtless sustained damage by the plaintiff’s delay in installing the machinery, the evidence introduced furnished no reliable data for the ascertainment of the amount thereof. Thereupon the defendant withdrew its counterclaim set up in the second count of its answer. The charge of the court was in effect a direction to find for the plaintiff for the amount of its claim and a verdict of that character was accordingly rendered. The defendant now asks to have the action of the Circuit Court reviewed as to both branches of its defense. It contends that it suffered an involuntary nonsuit as to its counterclaim, and that it is therefore the duty of this court to review the evidence and the ruling of the court thereon. We do not think so. At the conclusion of the charge to the jury, in the course of which the Circuit Court announced that the evidence under the counterclaim was insufficient to show with proper definiteness the amount of damage sustained, the defendant reserved a general exception, but failed to indicate any part thereof which it claimed to be objectionable. With the permission of the court the defendant then withdrew its counterclaim. In other words, it voluntarily dismissed it without prejudice. It did not comply with the practice which obtains in respect of involuntary nonsuits, and no exceptions were preserved so as to impose upon this court the duty to review the evidence to determine whether the view of the Circuit Court was well founded. We therefore turn to a consideration of that branch of the case which relates to the submission of the controversies between the parties to the engineer, and his decision.

The evidence conclusively showed that a draft of a written contract between the parties had been prepared, and, although it was not signed by them, it was thereafter recognized as containing the [220]*220evidence of their agreements and stipulations excepting as to certain-modifications which were subsequently made. The written correspondence between the parties contained frequent allusions to the writing as being their contract, and frequent references were also made to definite and specific provisions in it. So conclusive was the evidence upon the subject that the case should be considered as though, subject to the modifications referred to, the original draft of the contract had been duly executed by both parties. This was also the theory of the Circuit Court. The sixth and ninth paragraphs of the contract are important in the consideration of the question-now before us, and it is not contended that they were subsequently eliminated or modified in any way. The sixth paragraph will be referred to hereafter. The ninth is as follows:

“Changes: Should it prove desirable to make any changes in the work, the architect or engineer may direct such changes in writing, and a fair and equitable addition to or deduction from the contract price shall be made, the amount to be determined by the architect or engineer. Such changes shall not extend the date of completion, nor modify the obligations of the contractor in any way.”

The only important change in the contract which we need advert to here was one in respect of an item of machinery. A few days 'after the date of the contract the defendant found that it was advisable to have a generator of lower speed than the one specified, and it was thereupon ordered of the plaintiff by the engineer in-charge. The letter which contained the order, July 29, 1903, recited: “The contract of July l? 'to remain unchanged in all other respects.” There was a conflict in the testimony whether this change was responsible for the delay of between three and four months in the final installation of the machinery and whether there was' an agreement or understanding that the time limitation in the written contract for full compliance, namely, November 1, 1903, was thereby dispensed with. But whether this question was open to investigation under the defense now being considered depends upon the proper construction of the sixth paragraph of the contract and the effect to be attributed to the submission by the parties of the matters in controversy between them to the engineer and the decision which he rendered.

Paragraph 6 of the contract:

“Questions arising. Should any questions arise during the progress of the work, at the acceptance of the plant, or regarding settlement, such questions shall be referred to the architect or engineer for decision; but there is reserved the right of final decision by two disinterested parties; one chosen by each party to this agreement, and in the event of the parties so chosen failing to agree, they are to choose a third, the decision of two of said referees to be binding upon both parties.”

The differences which arose between the parties resulted in the. following correspondence:

March 4, 1904, a letter from the engineer to the plaintiff, the Westinghouse Company:

“I beg to acknowledge receipt of your Mr. Baetz several favors of 11th ult. reference f. o. b., and 1st inst. reference F. P. B., regarding payments on the Roberts, Johnson & Rand Shoe Co. contract of July 17th, 1903. Answering will say, that paragraph 6 of this contract reads as follows:
[221]*221“ ‘Questions Arising. Should any questions arise during the progress of this work, at the acceptance of the plant, or regarding settlement, such questions shall be referred to the architect or engineer for decision.’

Free access — add to your briefcase to read the full text and ask questions with AI

Related

JA La Porte Corporation v. Mayor and City Council
13 F. Supp. 795 (D. Maryland, 1936)
Corporation of Charles Town v. Ligon
67 F.2d 238 (Fourth Circuit, 1933)
Frisco Lumber Co. v. Hodge
218 F. 778 (Eighth Circuit, 1914)
Bates County v. Wills
200 F. 143 (Eighth Circuit, 1912)
City of Trinidad v. Hokasona
178 F. 438 (Eighth Circuit, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
143 F. 218, 74 C.C.A. 348, 1906 U.S. App. LEXIS 3725, Counsel Stack Legal Research, https://law.counselstack.com/opinion/roberts-johnson-rand-shoe-co-v-westinghouse-electric-mfg-co-ca8-1906.