Northeastern Const. Co. v. City of Winston-Salem

83 F.2d 57, 104 A.L.R. 1142, 1936 U.S. App. LEXIS 2439
CourtCourt of Appeals for the Fourth Circuit
DecidedApril 6, 1936
DocketNo. 3976
StatusPublished
Cited by4 cases

This text of 83 F.2d 57 (Northeastern Const. Co. v. City of Winston-Salem) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northeastern Const. Co. v. City of Winston-Salem, 83 F.2d 57, 104 A.L.R. 1142, 1936 U.S. App. LEXIS 2439 (4th Cir. 1936).

Opinion

NORTHCOTT, Circuit Judge.

This is an action at law instituted by the appellee, the city of Winston-Salem, a municipal corporation of the state of North Carolina, herein referred to as the plaintiff, against the Northeastern Construction Company, a corporation organized under the laws of the state of New York, herein referred to as the Construction Company, and the United States Guarantee Company, a corporation organized under the laws of the state of New York, herein referred to as the Guarantee Company. The action was originally instituted in the superior court of Forsyth county, N. C., but was removed to the United States District Court for the Middle District of North Carolina and was brought to recover on a bond given by the Construction Com-1 pany as principal, and the Guarantee Company as surety, in support of a bid or proposal for the construction of a sewer system for the plaintiff. In November, 1934, a jury being waived, the cause was submitted to the judge upon the pleadings, certain stipulated facts, and evidence taken before the court, and in September, 1935, the judge below filed his findings of fact, conclusions of law, and written opinion, and gave judgment for the plaintiff in the full amount of the bond ($12,00.0), from which action this appeal was brought.

The facts as found by the court below show that the board of aldermen of the city of Winston-Salem, by resolution adopted the 12th day of January, 1934, authorized the commissioner of public works and the public works committee of the board of aldermen to receive until 3 o’clock p. m. February 21, 1934, bids for the construction of an extension of its public sewer system in accordance with specifications and requirements on file in the office of said commissioner of public works; that, after due advertisement, bids were received from four contractors, including the defendant Construction Company, whose bid was the lowest. The bid of the Construction Company was accompanied by a bond of the Guarantee Company, as required by the specifications, in the sum of $12,000. The .condition of this obligation was as follows: “That, if the Obligee shall make any award to the Principal for Extension to South-Side Section Sewerage System of the City of Winston-Salem, N. G, according to plans and specifications • on file with Commissioner of Public Works of the City of Winston-Salem, N. G, according to the terms of the proposal or bid made by the Principal therefor, and the Principal shall duly make and enter into a contract with the Obligee in accordance with the terms of said proposal or bid and award and shall give bond for the faithful performance thereof with the United States Guarantee Company as Surety, or with other Surety or Sureties approved by the Obligee; or if the Principal shall, in case of failure so to do, pay to the Obligee the damages which the obligee may suffer by reason of such failure, not exceeding the penalty of this bond, then this obligation shall be null and void; otherwise it shall be and remain in full force and effect.”

This bond accompanying the bid of the Construction Company was in lieu of a cash deposit or certified check as was required by the North Carolina Statutes.

On March 9, 1934, the board of aider-men adopted a resolution accepting the proposition (bid) of the Construction Company, but, as stated in the resolution, eliminated from the contract about 20,000 feet of sewer lines that were included in the original advertisement for bids. This resolution stated that this exclusion of a part of the work was done upon the recommendation of the public works committee of the board. On March 10, 1934, the secretary of the board addressed a letter to the bidder giving notice of this action. The Construction Company under date of March 19, 1934, sent a letter. [59]*59signed by its president, to the secretary of the board stating that it was considered by the Construction Company that this elimination of 20,000 feet of sewer lines from the proposal, as originally advertised, cutting down the project to about 85 per cent, of the whole, constituted a substantial change or departure from the original terms, that such a change amounted to a rejection of the offer, and that the Construction Company did not care to accept the proposal as changed and was not prepared to renew its original offer.

On March 20, 1934, the board of aider-men passed a resolution setting out that, as the Construction Company had attempted to withdraw its bid by letter of March 9, 1934, before the award was made, but after its officers had knowledge of the fact that it was the low bidder, without giving any reason for such attempted withdrawal, and as the Construction Company had by letter of March 19 refused to comply with the terms of its proposal or execute the contract, therefore the bond accompanying the bid signed by the Guarantee Company be forfeited and that proper steps be taken to secure payment of the same. A copy of this resolution was forwarded to each of the defendants, by the city attorney, under date of May 2, 1934.

On March 21, 1934, the plaintiff caused to be prepared a formal contract in accordance with the terms of its resolution of March 9, 1934, and duly tendered said contract to the Construction Company, which company refused to execute same. The vice president of the Construction Company represented it in submitting the bid in question and was present when the bids were opened, and was then informed by the city manager of public works that a part of the work would be eliminated on account of lack of funds.

During the period between February 21 and March 9, 1934, the city manager of public works and the vice president of the Construction Company had several conferences, in the course of which the vice president of the Construction Company indicated a desire to withdraw his bid. On March 2, 1934, the board of aldermen, being informed that the Construction Company desired to cancel its bid, delayed action for, one week in an effort to get the matter adjusted.

After the Construction Company refused to execute the contract, the plaintiff relet the work to the lowest bidder, and the cost to the city was approximately $25,000 more than the Construction Company’s bid.

The court found as a fact that the change in the proposal as made by the city did not materially alter its terms, and reached the conclusion, as a matter of law, that the acceptance of the bid by the plaintiff (eliminating a portion of the work) made the contract complete and that the refusal of the Construction Company to enter into its performance was a breach that entitled the plaintiff to the penalty of the bond which, in amount, was less than the damages the city sustained by reason of the breach; that the clause in the specifications accompanying the advertisement for the bids, giving the commissioner of public works the right to eliminate any portion of the work,' coupled with the fact that the work was to be paid for by the unit of work, authorized the elimination of a part of the proposal by the plaintiff without materially altering the proposal, and did not therefore justify or excuse the Construction Company for its refusal to carry out the contract.

The sole question necessary to be considered upon this appeal is whether the alteration made by the board of aider-men of the plaintiff after the bids had been opened, in the amount of work to be contracted, was such a material alteration, in the terms of the proposal, as justified the Construction Company in refusing to carry out the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Singleton v. District of Columbia
198 F.2d 945 (D.C. Circuit, 1952)
Hillcrest Inv. Co. v. United States
55 F. Supp. 147 (W.D. Missouri, 1944)

Cite This Page — Counsel Stack

Bluebook (online)
83 F.2d 57, 104 A.L.R. 1142, 1936 U.S. App. LEXIS 2439, Counsel Stack Legal Research, https://law.counselstack.com/opinion/northeastern-const-co-v-city-of-winston-salem-ca4-1936.