United States v. P. J. Carlin Const. Co.

224 F. 859, 138 C.C.A. 449, 1915 U.S. App. LEXIS 1938
CourtCourt of Appeals for the Second Circuit
DecidedMay 12, 1915
DocketNo. 4
StatusPublished
Cited by14 cases

This text of 224 F. 859 (United States v. P. J. Carlin Const. Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. P. J. Carlin Const. Co., 224 F. 859, 138 C.C.A. 449, 1915 U.S. App. LEXIS 1938 (2d Cir. 1915).

Opinion

ROGERS, Circuit Judge.

The government of the United States, acting through its agents, advertised, in March, 1908, that it would receive sealed proposals for the construction of certain improvements to be made at Ft. Mason, San Francisco, Cal., which work was to be done in .strict accordance with drawings and specifications. Bids were to be received until noon May 4, 1908, when they were to be publicly opened. The specifications required each bidder to submit with his proposals either a certified check for $10,000, or a surety company bond equal to 10 per cent, of the amount of his proposal, as a guaranty that the contract and bond required by the specifications would be executed within 10 days after the successful bidder had been notified that his bid had been accepted.

The Carlin Company in due time submitted its proposal to1 do the work for $1,178,000 and to complete it within 30 months. This was its “Rump Bid A.” In its “Rump Bid B” it proposed to complete the work on alternative drawings and specifications of its own, using reinforced concrete caisson construction, and agreeing to complete it in 27 months. With its proposal it submitted a bond of the Illinois Surety Company, whereby the latter guaranteed that, if the bid of the Carlin Company was accepted within 60 days from the opening of the proposals, the latter would enter into a contract for the performance of the work and give bond' for the faithful fulfillment thereof within 10 days after notice of acceptance, or the Surety Company would pay the United States the difference in money between the amount of the bid and the amount for which the United States might contract with another, not exceeding $125,000. Upon the opening of the bids the Carlin Company was found to be the lowest bidder.

The drawings and specifications which the Carlin Company submitted with its “Rump Bid B” were not sufficiently in detail to be satisfactory to the officials of the government, and the Carlin Company agreed to submit more complete plans and specifications. But there-was delay in so doing, and on June 18, 1908, and before the Carlin Company had furnished the completed plans and specifications, which-it was to submit in connection with its “Rump Bid B,” a letter was sent to the Construction Company by the Quartermaster General of the United States Army informing it that instructions had been issued to make award of the contract—

“to your company in accordance with your proposals, based upon the government plans and specifications as follows: The entire work called for by plans and specifications, except sheds on wharf No. 1 and wharf No. 3. He has been further instructed to insert a clause in the contract whereby the government reserves the right to enter into supplementary agreement with your company for the construction of the sea wall, in accordance with your alternative bid, at a reduction of $80,000, provided satisfactory plans and specifications for tins alternative design shall be submitted to and approved by this office within six months from the date of award. This has been rendered necessary because certain minor points in your design for the sea wall recently submitted to this office are not satisfactory. This clause in the contract is desired in order to enable the immediate award of contract, and to give your company ample time in which to submit completed plans for the alternate sea wall; it being understood that it is entirely optional with the government to decide whether or not the sea wall shall be built according to the original plans and specifications or in accordance with the alternate bid, provided a decision is arrived at within six months from date of award* [861]*861Additional clauses for the specifications will provide for certain other omissions and additions which were verbally agreed to by Mr. Carlin while in this office.”

Correspondence followed between the parties, the Construction Com-' pany making objection to the contract as proposed by the government in the letter of June 18, 1908, and declining to accept it. In a letter dated June 20th, Mr. Carlin after stating objections wrote:

“It is manifestly impossible for us to consider the signing of a contract, which places in abeyance, for a period of six months, the determination of a question, without which determination it will be impossible for us to begin. VVe should be glad to know what provision it is proposed to insert in the form of contract, regarding responsibility for the construction of the work, if the original plans are followed.”

To this the government replied on June 24th:

“The award for the construction of the wharves at Ft. Mason, San Francisco, Cal., was ordered made to you on your straight bid for this work. Had you complied strictly with the specifications and instructions to bidders, and submitted complete plans and specifications of the alternate sea wall, the question of a delay in definitely determining the type of sea wall to be used would have been entirely obviated. As it now stands the bid on the government design has been accepted, and the proposed clause in the specifications simply gives you an opportunity to submit an entirely satisfactory design under your alternate bid within six months from the date of the award of the contract. It therefore gives you an opportunity to build the sea wail in accordance with your own design. This clause was inserted in the contract to give you every opportunity to use your alternate design, and you have had no reason at any time for assuming that only the alternate plan would lie considered. Your bid is definite, and the acceptance is definite.”

On the same date the government wrote the Construction Company that its proposal opened on May 4th was — -

“hereby accepted as follows: (1) Item 1 of the bid, $1,178,000, being the lump bid for the construction of the sea wall, crib wall, transport wharves, and sheds conrplete, as shown by drawings and specifications, deducting item 7, being a reduction of $03,000 for omitting shed complete on wharf No. 1, and item 9, being a reduction of $60,000 for the omission of shed complete on wharf No. 3, making a total award of $l,0.'io,000 Cor the construction complete, including sea wall, necessary dredging, and filling for the entire project as covered by plans and specifications, except sheds on wharf No. 1 and wharf No. 3.”

The letter then went on to state three separate modifications of the contract which the government desired:

“It is desired that a clause be inserted into the contract reserving to the government the right within six months from the date of award to enter into an extra agreement for the construction of the sea wall under the alternative bid of the I*. J. Carlin Construction Company at a reduction in price <>C $80,000, provided satisfactory plans and specifications, based upon their alternative bid, be submitted to and approved by this office within the time mentioned.
“III. It is further desired that a clause be inserted in the specifications providing for the omission of the crib wall along the Laguna street side of file reservation, in accordance with item 10 of the bid, at a reduction of $90,-000, provided written notice is served on the contractor prior to six months after date of award of contract.
“IV. It is further desired that a clause be inserted in the contract providing for the construction of sheds on wharf No. 1 and wharf No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Consarc Corporation v. Marine Midland Bank, N.A.
996 F.2d 568 (Second Circuit, 1993)
Dohrman v. Sullivan
220 S.W.2d 973 (Court of Appeals of Kentucky (pre-1976), 1949)
Department of Banking v. Stenger
272 N.W. 403 (Nebraska Supreme Court, 1937)
Northeastern Const. Co. v. City of Winston-Salem
83 F.2d 57 (Fourth Circuit, 1936)
Zinco v. Reisenfeld
129 Misc. 582 (New York Supreme Court, 1927)
American Smelting & Refining Co. v. Hyman
16 F.2d 39 (Sixth Circuit, 1926)
American Merchant Marine Ins. v. Letton
9 F.2d 799 (Second Circuit, 1926)
Crancer v. Lareau
1 F.2d 117 (Eighth Circuit, 1924)
Frank Bowman Co. v. Lecato
292 F. 73 (Fourth Circuit, 1923)
Norris, Inc. v. M. H. Reed
278 F. 19 (Fifth Circuit, 1922)
Reynolds v. Omaha General Iron Works
180 N.W. 584 (Nebraska Supreme Court, 1920)
Union Bag & Paper Corp. v. Bischoff
255 F. 187 (E.D. New York, 1918)

Cite This Page — Counsel Stack

Bluebook (online)
224 F. 859, 138 C.C.A. 449, 1915 U.S. App. LEXIS 1938, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-p-j-carlin-const-co-ca2-1915.