Coulter, Inc. v. Allen

624 P.2d 1199, 1981 Wyo. LEXIS 305
CourtWyoming Supreme Court
DecidedMarch 13, 1981
Docket5396
StatusPublished
Cited by14 cases

This text of 624 P.2d 1199 (Coulter, Inc. v. Allen) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Coulter, Inc. v. Allen, 624 P.2d 1199, 1981 Wyo. LEXIS 305 (Wyo. 1981).

Opinions

ROONEY, Justice.

Appellant-defendant appeals from a judgment rendered on a jury verdict which awarded appellee-plaintiff $6,595.54 damages for breach of contract.

Appellant words the issues on appeal as follows:

“I. DID THE TRIAL COURT ERR BY ADMITTING EVIDENCE OF AN OFFER TO COMPROMISE AND STATEMENTS MADE IN COMPROMISE NEGOTIATIONS?
“II. WAS THE AWARD OF DAMAGES TO APPELLEE AN ERROR AS A MATTER OF LAW BECAUSE THERE WAS NO EVIDENCE TO SUBSTANTIATE THE FINDING?
“HI. DID THE TRIAL COURT ERR IN GIVING THE JURY THE INSTRUCTION ON PLAINTIFF’S DAMAGES AS IT DEMONSTRATES THE TRIAL COURT DISREGARDED THE OFFERED LIEN RELEASES?”

We reverse and remand the case for a new trial.

Appellant and appellee entered into an agreement by which appellee was to perform certain concrete construction work on appellant’s real estate development projects in Campbell County. Two “job work orders” were introduced into evidence and accepted by the parties as setting forth at least some of the terms of the agreement. Appellee testified on cross-examination:

“Q. And would you agree that those were your contract with Coulter, Inc.?
“A. Yes, along with the verbal contract[1] we had, this is the contract. It’s even [1201]*1201marked up here ‘contract’ in a little square.
“Q. And this contains all of the important parts of your contract; doesn’t it?
“A. Well, it pertains to most of the important parts, yes.
* * * * * *
“Q. (By Mr. Walker) You put contracts in writing so that there’ll be no misunderstanding; don’t you?
“A. Yes.
“Q. And you put in writing what the important parts of the contract are; don’t you?
“A. Yes.”

The work orders were on preprinted forms, reflecting the work to have been ordered by Milt Coulter. They were signed by appellee. Instead of setting forth the contract amount in the sections of the form provided for doing so, “(as per certified amount)” was typed in. Appellee was designated as the contractor. One of the forms was dated August 27, 1979 for “PARKSIDE APARTMENTS” job and was to be billed to Coulter, Inc. The following was typed under the heading “DESCRIPTION OF WORK”:

“Pour and finish all remaining curbs, sidewalks and Trash enclosure for Park-side Apartments at the following prices:
“$3.00 per running foot for all curbs.
“.45 per sq. foot for all sidewalks.
“$100.00 per each trash enclosure.
“Coulter, Inc. will pay for all concrete. “Will be pay [sic] on a weekly basis for work done the previous week.”

The other form was dated September 17, 1979 for “Fox Park Subdivision” job and was to be billed to Fox Park Development.2 The following was typed under “DESCRIPTION OF WORK”:

“Pour and finish street repair for $.45 per sq. ft. — Fox Park will furnish concrete. “Will be paid on a weekly basis for work done the previous week.”

Payment for the work was made weekly. Each time, appellee signed a “CERTIFICATE FOR PAYMENT” which included the following:

“In consideration of the payment of the amount of this certificate/request for payment the undersigned does hereby release any and all claims and/or rights arising under or by virtue of the contract/agreement, waives any and all rights of lien and certifies that all subcontractors, material suppliers and labor have been paid in full for material, services and/or labor arising under or by virtue of the contract/agreement.”

In mid-October, a disagreement developed between appellant and appellee, and the contractual relationship was terminated. Appellee then presented a claim to appellant for work which he contended was performed but for which he was not paid. If not all, most of this work was performed during the periods for which appellee had signed a “CERTIFICATE FOR PAYMENT.”

Before trial, appellant’s motion in limine was denied. The motion was to prohibit the introduction into evidence of two letters. One was a letter dated November 30, 1979 from appellee’s attorney to appellant advising of a claim for $5,508.15 and stating in part:

“I am advising you of this claim as a courtesy before suit is filed. If you are interested in negotiating or in paying the account, contact me at your earliest convenience. * * * ”

The other letter was a one-page letter with a two-page enclosure. It was dated December 10, 1979 from Deb Bricker, the Assistant Secretary/Treasurer of appellant to ap-pellee’s attorney. It was in response to the November 30, 1979 letter from such attorney. It reads in pertinent part:

“Please find enclosed sheets explaining the payments and the overages incurred while Rocky Mountain Concrete was doing contract labor for us. These sheets [1202]*1202certainly are not complete by any standard; but hopefully it will help give you an idea of the promblems [sic] we had with Dale. It would have taken me a solid month to type the whole story. “Please call me when you finish going over the breakdowns and I can explain any part that I didn’t make clear.
“ * * * I am sure Dale Allen cost me way more then [sic] he was ever worth. I would like to settle this out of court, but if Dale insists on not accepting our settlement, I will get the rest of my bills together.
“I appreciate you taking time to hear my side of the story and I hope we can work some arrangement out.”

• The two enclosed sheets (hereinafter referred to as enclosures) contained figures on amounts billed and paid to appellee on the two projects. They concluded with the following:

“With this amount of $1,225.73 less the amount he owes Fox Park, I am willing to settle with Dale for $576.93. I have already offered him this amount and explained all the overages, but he would not accept this amount.”

At trial, appellee offered the enclosures in evidence. They were admitted over objection that they were part of the settlement negotiations and were only part of an entire letter. Thereafter, appellant offered the December 10, 1979 cover letter into evidence, and it was admitted without objection.

We are here concerned only with the possibility of error in the admission of the enclosures.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Arychuk v. Star Valley Association
997 P.2d 472 (Wyoming Supreme Court, 2000)
City of Cheyenne v. Reiman Corp.
869 P.2d 125 (Wyoming Supreme Court, 1994)
Haderlie v. Sondgeroth
866 P.2d 703 (Wyoming Supreme Court, 1993)
Harvey v. State
835 P.2d 1074 (Wyoming Supreme Court, 1992)
Kelliher v. Herman
701 P.2d 1157 (Wyoming Supreme Court, 1985)
Bjork v. Chrysler Corp.
702 P.2d 146 (Wyoming Supreme Court, 1985)
Anderson v. Foothill Industrial Bank
674 P.2d 232 (Wyoming Supreme Court, 1984)
Horgan v. Industrial Design Corp.
657 P.2d 751 (Utah Supreme Court, 1982)
Coulter, Inc. v. Allen
624 P.2d 1199 (Wyoming Supreme Court, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
624 P.2d 1199, 1981 Wyo. LEXIS 305, Counsel Stack Legal Research, https://law.counselstack.com/opinion/coulter-inc-v-allen-wyo-1981.